top of page

In construction projects, additional costs can arise during work due to conditions that were not apparent at the time of contracting, ambiguity in drawings or specifications, or differing judgments on site. Additional costs themselves are not necessarily a bad thing. Some changes are necessary to complete the building safely or to accommodate the owner's requests. However, if pre-contract checks are insufficient, items that could have been resolved beforehand become additional work during construction, making schedule and budget management difficult.


This article organizes six points that construction site personnel should check before signing a contract, from the perspective of minimizing additional costs. These are practical items to confirm in order to align understanding among contractors, designers, clients, and site managers, and to reduce later misunderstandings such as “I wasn’t told” or “I thought it was included.”


Please translate the following input into English.

Table of contents

Reasons Additional Costs Tend to Arise in Construction Projects

Check 1: Specifically Confirm the Construction Scope and the Quotation Scope

Check 2: Identify Undetermined Parts of Drawings and Specifications

Check 3: Verify Existing Conditions and Site Conditions Before Contracting

Check 4: Establish Decision Rules for Changes and Additional Work

Check 5: Confirm Conditions Where Schedule Changes or Standby Affect Costs

Check 6: Organize Records, Photographs, and Approval Workflows

Summary of Pre-contract Checks to Reduce Additional Costs


Why Additional Costs Often Occur in Construction Projects

Additional costs in construction work are more likely to arise not simply because the contractor bills afterward, but when there is a gap between the assumptions at the time of contracting and the actual conditions on site. Because construction projects proceed with overlapping design drawings, specifications, estimates, schedules, site conditions, and stakeholders’ requests, if any ambiguity remains anywhere, its effects will surface during the work.


What deserves particular attention is when the work items listed on an estimate do not match the finished state envisioned by the client or the site manager. For example, interior finishes, the scope of equipment connections, how the work ties into exterior landscaping, temporary works, and repairs after removal are items whose extent is hard to convey with words alone. If you proceed without confirming these before contracting, once work begins you can end up with a gap in understanding, such as “I thought this was included.”


Also, in renovation or extension work on existing buildings, there are elements that only become apparent once demolition has been carried out. The interiors of walls and floors, pipe routing, the condition of the underlying structure, underground buried objects, and discrepancies between existing drawings and actual conditions may not be fully ascertainable before signing the contract. When such uncertainties exist, it is more important to define in advance the conditions that would trigger additional costs and the procedures for determining them than to try to eliminate additional costs entirely.


In pre-contract checks for building construction, you need to clarify not only price but also what is included, what is not included, and in which cases separate negotiations will be required. If you judge solely by comparing estimate amounts, you may later discover that necessary items are missing, which can increase the management burden. If you organize the scope of work, specifications, site conditions, rules for changes, and recordkeeping methods at the pre-contract stage, you can better reduce the likelihood of additional costs and, if additional work becomes necessary, make it easier to explain.


Check 1 Confirm the construction scope and the scope of the estimate in detail

When trying to keep additional costs in construction work down, the first thing to confirm is that the scope of the work matches the scope shown in the estimate. If many items in the contract documents or estimate are listed as "lump sum," it can be hard to tell what is covered by the contract unless you check the details carefully. The use of lump-sum notation itself is not necessarily a problem, but in practice it is important to confirm the breakdown and the underlying assumptions.


In construction work, there are many tasks that are not obvious in the finished product, not only the main construction itself but also temporary works, protective measures, deliveries, removals, waste disposal, repairs, cleaning, test runs, and auxiliary tasks related to permit applications. If you sign a contract without confirming whether these are included in the estimate or are separate, they may be added as necessary work during construction. This is especially true for renovation work, where protective measures to avoid damaging existing parts and the scope of restoration after construction tend to be unclear, so extra caution is required.


Before signing the contract, it is useful to check the items on the estimate while cross-referencing them with the drawings and specifications. Identify items that are shown on the drawings but missing from the estimate, items that appear on the estimate but whose scope on the drawings is unclear, and items for which the basis of the quantities is not apparent. Rather than simply recalculating the quantities in detail, you can more easily find omissions by confirming which drawings and which areas of those drawings were used to derive the quantities.


Also, in construction projects, classifications such as "main construction work", "separate work", "owner-supplied items", "owner-arranged", and "reuse of existing items" are important. For example, even if the owner provides equipment, it is necessary to clearly specify how far the contractor is responsible for delivery, installation, connection, adjustment, and warranty coverage. Equipment itself may be owner-supplied while mounting materials or connection work are treated as separate work. If such classifications are left only to words, the scope of responsibility will become ambiguous later.


In pre-contract meetings, it is important to confirm not only what is included but also what is not included. To keep additional costs down, it is important to recognize items that are not included in the estimate in advance, rather than trying to blame the estimate. If you know which items are not included, you can adjust them before signing the contract, arrange them separately on the client’s side, or stagger the construction schedule. Conversely, if you do not notice that something is not included until during construction, you will have to make decisions under schedule pressure, which narrows your options.


When confirming the scope of work, it's easier to organize if you review it by room, by element, and by process. You then follow the tasks required to completion in order—floors, walls, ceilings, doors/fixtures, equipment, exterior, sitework, temporary works, removal, disposal, finishes, and inspections. Conducting this review before signing the contract reduces overlooked items on the estimate and assumptions about the scope, laying the groundwork to minimize additional costs.


Check 2: Identify unresolved items in drawings and specifications

In construction work, drawings and specifications serve as an important basis of the contract. However, not all specifications are necessarily finalized at the pre-contract stage. There may be items that proceed to contract while still undecided, such as finishing materials, colors, equipment specifications, types of doors and fittings, locations of lighting and wiring, storage details, exterior finishes, and detailing of how elements fit together. If these undecided items are left as they are, decisions made during construction are more likely to lead to additional costs.


What makes undecided parts problematic is not so much that the specifications haven't been finalized, but that it's unclear which specifications the estimate at the time of contracting was based on. For example, even for the same component, if the type of finish or the installation method changes, the required materials, surface preparation, labor, and construction process will change. If, after the contract, a specification is selected and the construction conditions differ from the assumptions of the original estimate, additional negotiations may be necessary.


Therefore, before signing a contract, it is important to review the drawings and specifications and separate and organize the items that have been finalized from those that are still undecided. For undecided items, confirm which specifications were assumed when preparing the estimate and how they will be handled if changed later. Even if specifications remain undecided, clearly stating the standard assumptions will make later decisions easier.


Particular attention should be paid to areas that are simply shown on drawings but actually require detailed detailing. Junctions between walls and ceilings, floor level changes, connections with existing parts, penetrations for equipment piping, locations involving waterproofing, and areas around exterior fittings are parts that often need on-site adjustment. If detailed drawings or construction assumptions are lacking before the contract, on-site decisions during construction tend to increase and can become a cause of additional work.


Also, be careful if the specifications contain many expressions such as "equivalent products", "on-site adjustments", and "to be discussed separately". These expressions are sometimes used in practice, but if their meaning remains unclear, differences in interpretation may arise after the contract is signed. By confirming the criteria for determining equivalence, the scope of on-site adjustments, and the conditions that will require separate consultation, you can more easily avoid unnecessary disputes.


When checking drawings and specifications, it is also important to verify how fully the client's requests have been reflected. Even requests that were raised during meetings may not be treated as part of the contract if they are not reflected in the drawings or specifications. Items that you think were agreed to verbally are particularly likely to lead to differences in understanding during construction. Before signing the contract, you need to cross-check meeting minutes, drawings, specifications, and estimates to ensure nothing has been omitted.


The process of identifying undetermined items is not intended to delay the contract. Rather, it is preparation to reduce confusion and rework after construction begins and to stabilize the schedule. Even if you cannot decide everything completely, listing the undetermined items and setting decision deadlines and decision-makers will make it easier to avoid incurring additional costs.


Check 3: Verify existing conditions and site conditions before signing the contract

Additional costs in construction work often arise from overlooking site conditions. Even in new construction, site elevation differences, the adjacent road, delivery routes, distance to neighboring properties, temporary onsite space, and ground and drainage conditions affect construction. In renovation or extension work, the condition of the existing building, hidden piping and wiring, deterioration of the substrate, and discrepancies between the drawings and the actual conditions can necessitate additional work.


During pre-contract on-site inspections, we verify conditions that drawings alone cannot reveal: whether vehicle access to the site is easy, whether there is space to temporarily store materials, whether working hours are restricted, whether there are conditions requiring consideration for neighbors, and whether work must be carried out while using existing facilities. These conditions affect estimates and schedules. If they are not shared in advance, additional temporary facilities or work adjustments may be required after construction begins.


In renovation work, inspection of the existing portions is especially important. Because there are elements that cannot be determined without dismantling walls or floors, it can be difficult to finalize everything before signing the contract. Even so, you can check for visible deterioration, traces of past repairs, signs of water leaks, tilting or cracking, aging equipment, and the presence or absence of inspection openings. If you record what was confirmed in advance, it becomes easier to judge whether defects discovered after the contract were foreseeable from the outset or were difficult to predict.


Even if existing drawings are available, they do not necessarily reflect the current on-site conditions. Past renovations or equipment upgrades may not have been incorporated into the drawings. If you prepare an estimate based solely on existing drawings, piping routes or substrate locations may differ during construction, requiring additional work. Before signing a contract, existing drawings should be treated as reference materials and cross-checked against what can be confirmed by on-site inspection.


Also, for areas where pre-inspection is limited—such as underground or inside structures—we will identify and document them as uncertain factors before the contract. If parts that cannot be confirmed are arbitrarily asserted, the allocation of responsibility becomes unclear when problems arise during construction. By separating the confirmed scope, the unconfirmed scope, and the scope to be discussed upon discovery, it becomes easier to explain any additional costs that may be required.


It is preferable not to leave verification of site conditions solely to the contractor; the client and the project manager should also attend to align their understanding. By inspecting the site together, you can share conditions that will limit work during construction and the aspects the client prioritizes. Take photographs, record the inspection date and the inspector, and retain them as assumptions for the estimate to reduce discrepancies in understanding after the contract is concluded.


Check 4: Establish rules for deciding on change orders and additional construction work

In building construction, it is not uncommon for changes or additional work to occur during the course of a project. For various reasons—such as changes in the client’s requirements, the discovery of site conditions, responses to laws or inspections, adjustments to detailing or coordination, and remedies for existing defects—decisions that differ from the original contract may become necessary. What is important is to decide before entering into the contract who will approve changes or additions, at what stage they will be approved, and on the basis of which documents.


If change rules have not been established, verbal instructions may be given on site that seem necessary at the time but later lead to disputes over cost allocation and responsibility. Especially on sites where the schedule is tight, the rush to make decisions can cause records and approvals to be postponed. To prevent this, you need to confirm before signing the contract how to submit change requests, how estimates will be presented, and the rules for starting work after approval.


When deciding on additional work, first confirm whether the work is included in the original contract or is outside the contract. Then organize the reasons for the addition, the required scope of work, the impact on the project schedule, and the impact on the quality of the finished work. Focusing only on costs makes it difficult to convey why the work is necessary. In practice, it is important to record the reason for the change together with the construction details.


Also, changes can be due to the client’s requests or to site conditions. If a change is requested by the client, it is easier to organize as a specification change or an addition to the scope, but changes caused by site conditions are more difficult to assess. For example, if the deterioration of the existing substrate is worse than anticipated, it is necessary to confirm whether repairs are included in the contract scope or should be treated as separate work. To prepare for such cases, it is reassuring to decide before contracting how consultations will be handled if unforeseen conditions arise.


You should also clearly identify who is authorized to approve changes and additional work. Distinguishing the scope that on-site personnel can approve, the scope that requires the client's authorization, and the scope that needs confirmation from the designer or supervisor will reduce confusion on site. If work proceeds with approval authority unclear, it later becomes a problem of "who approved it."


Furthermore, it is important to document changes in writing or in records. The format may be adapted to on-site operations, but it should record the change details, the reason, the scope of impact, the approver, the approval date, and the timing of implementation. Attaching photos or marked-up drawings makes later verification easier. If this rule is decided before the contract, it will be easier to maintain transparency if additional costs arise and to prevent unnecessary disputes.


Check 5: Verify the conditions under which process changes or waiting affect costs

Additional costs in building construction can arise not only from changes in materials or the scope of work but also from schedule changes and waiting times. Because construction involves multiple trades working in sequence, delays in earlier stages, delayed decisions by the client, restrictions on material deliveries, coordination with other works, and changes to inspection schedules all affect subsequent stages. If the handling of schedule changes is not confirmed before the contract, the coordination burden during construction will increase significantly.


The construction schedule is not merely a timetable but a management document that ensures all parties operate under the same assumptions. Before a contract is signed, it is necessary to confirm not only the start date, major milestones, inspection timing, and handover date, but also the deadlines for items the client must decide. If decisions on finish specifications, equipment locations, colors, fittings, or additional requests are delayed, they can affect construction arrangements and material procurement and may lead to schedule changes.


Also, some sites have restrictions on working hours and delivery times. In places such as commercial facilities, apartment complexes, occupied offices, or densely clustered residential neighborhoods, consideration must be given to noise and vibration, delivery routes, and permissible working hours. If these restrictions are not reflected in estimates and schedules, work efficiency may decline after construction begins and additional measures may be required. It is important to confirm site conditions and incorporate them into the construction plan before signing the contract.


Conditions for standby and revisits are also items that are easy to overlook. For example, situations such as having entered the site but the preceding work not being completed, being unable to work because client confirmation has not been obtained, required supplied materials not having arrived, or being unable to perform work because it overlaps with another contractor's tasks can affect the arrangement of craftspeople and managers. By confirming in advance how such cases will be handled, it becomes easier to clarify the scope of responsibility.


It is difficult to completely avoid changes to the process, but we can share in advance the conditions under which changes will affect costs. Before contracting, we confirm which kinds of changes can be adjusted within the process, which cases will require separate consultation, and what the impacts will be if the decision deadline is missed. This makes it easier for the client to understand the importance of timely decisions.


In construction projects, the earlier decisions are made once work has started on site, the easier it is to contain additional costs and schedule delays. Conversely, the later decisions are made, the more likely it becomes that already-planned tasks will need to be reorganized or completed portions will have to be reworked. Establishing rules for schedule management before signing the contract is an important checklist item for controlling additional costs.


Check 6: Organize records, photos, and the approval workflow

To minimize additional construction costs, it is important to decide how records will be kept before signing the contract. Meetings during construction, site inspections, specification decisions, change orders, and the conditions before and after construction should be documented in a form that can be reviewed later. If records are insufficient, contemporaneous judgments and agreements become unclear, making it difficult to justify the reasonableness of additional costs.


Photographic records, in particular, play a major role in construction management. Keeping photos of the site conditions before work begins, the condition of existing elements, substrates and piping that will be concealed, the before-and-after states of changes, and any areas requiring repair makes it easier to verify conditions later. If there are few photos, what happened on site must be explained in words alone, which increases the likelihood of misunderstandings.


Decide before contracting who will record, how records will be shared, and when approvals will take place to stabilize operations. Even if the contractor manages site photos, it is important to make them accessible to the client and supervisors. If you organize photos so the shooting date, photo location, subject area, and details of changes are clear, they will also be easy to use as explanatory materials for additional work.


Approval flow is also important. When specification changes or additional work occur, don’t proceed based on verbal agreement alone; establish a process to document and obtain approval. If work is started before approval, it becomes difficult later to confirm who will bear the costs. However, because situations requiring emergency responses can arise, also decide on the communication methods and post-action confirmation procedures for such cases so the site is less likely to be halted.


The purpose of keeping records is not to assign blame but to align the understanding of the parties involved. In construction projects, many stakeholders are involved, such as the client, the contractor, the designer, the supervisor, and subcontractors. Even when they attend the same meeting, people may interpret things differently. By keeping and sharing records, differences in understanding can be corrected at an early stage.


Also, keeping records not only reduces additional costs but also helps verify construction quality. If you document by photo the condition of concealed parts, the substrate before finishing, the locations of equipment piping, and the status of reinforcement and waterproofing work, those images can be used for checks before handover and for future maintenance. Putting record-keeping procedures in place before signing the contract supports management not only during construction but also after completion.


Summary of Pre-contract Checks to Minimize Additional Costs

To keep additional costs in building construction down, pre-contract confirmation is indispensable. If you try to resolve problems after the work has begun, options are limited by the schedule and arrangements. Conversely, if you organize the scope of work, specifications, site conditions, rules for changes, impact on the schedule, and methods of record-keeping at the pre-contract stage, you can more easily reduce unnecessary additional costs and misunderstandings.


First, confirming the construction scope and the estimate scope clarifies what work is included and what is not. Next, identifying undetermined parts of the drawings and specifications makes it easier to prevent specification changes and delays in decision-making during construction. Furthermore, checking existing conditions and site conditions in advance reduces constraints that would otherwise be discovered after construction begins.


It is also important to decide the rules for judging changes and additional work before the contract. Even if additional work becomes necessary, if the reasons, scope, approvers, and recording method are determined, discrepancies in understanding among stakeholders can be reduced. By confirming the conditions under which schedule changes or standbys affect costs, you can make the burdens caused by delays in the client's decisions or coordination with other works visible.


Finally, organizing records, photos, and approval workflows makes it easier to verify decisions made during construction later on. On building construction sites, conditions change daily. Keeping records of the pre-construction condition, changes made during construction, and parts that will be concealed is useful not only for explaining additional costs but also for quality control and post-handover maintenance.


Pre-contract checks for building construction are not merely a defensive measure to avoid additional costs. They are practical preparations to ensure all parties proceed on the same assumptions and to reduce problems after completion. By not relying solely on drawings and estimates and instead combining verification of site conditions with records, you can improve the overall accuracy of construction management.


If you want to efficiently keep records of on-site checks and pre- and post-construction, combining photo records, location-tagged records, cloud sharing, and meeting records can be effective. If you decide in advance how records will be kept at a construction site, inspection work and information sharing will run more smoothly, and it will be easier to explain any additional costs that arise.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page