top of page

In building construction, if you feel secure just by looking only at the estimated amount at the time of contract, negotiations over additional costs may become necessary after work begins, making budget management and internal explanations difficult. An additional claim is not necessarily unjustified. There are items that are difficult to determine before the start of work due to the nature of construction—deterioration discovered after demolition of existing buildings, underground obstacles, design changes, additional requests from the client, and so on. However, additional claims that arise from insufficient pre-checks or vague records can be reduced through adequate pre-construction preparation and management during construction. This article explains seven points that practitioners looking for information on "建築 工事" should check to avoid additional claims, following the flow from pre-contract through construction to completion.


Table of Contents

Main causes of additional charges in construction work

Checkpoint 1: Make the scope of work clear in words and on drawings

Checkpoint 2: Confirm the estimate breakdown and work not included

Checkpoint 3: Conduct a site survey and keep records of existing conditions

Checkpoint 4: Establish approval rules for specification changes and additional requests

Checkpoint 5: Check the impacts of schedule changes and temporary construction conditions

Checkpoint 6: Centralize management of records and meeting histories during construction

Checkpoint 7: Agree on final inspection and settlement terms in advance

To prevent additional charges, accurate sharing of site information is crucial

Summary: Additional charges in building construction can be minimized through prior confirmation and record-keeping


Main causes of additional charges in building construction

In construction, additional charges can arise because differences emerge between what was decided at the time of the contract and the work actually required on site. While the factors that tend to cause this vary depending on the type of work—new construction, renovation, repair work, equipment replacement work, etc.—what they have in common is that the project proceeds without clarity about what was included in the original contract.


For example, when many items on an estimate are listed as "lump-sum," it becomes difficult to determine to what extent that covers material costs, construction costs, transportation, protective measures, disposal of waste materials, cleaning, temporary works, and adjustments to surrounding areas. Work that the person in charge assumed was obviously included may be regarded by the contractor as a separate item. If that difference in understanding surfaces after work has begun, negotiations over additional costs will be necessary.


Moreover, in construction work the scope of work can change depending on site conditions. The interior of existing buildings, the backs of finishes, subsurface conditions, deterioration of the structural frame, and the routes of building services piping are examples of things that may not be fully understood from pre-construction investigations alone. If such uncertainties exist and the allocation of risk is not decided before contracting, it easily becomes a problem of who will bear the cost after they are discovered.


Furthermore, changes in the client's requests during construction are also a major cause of additional charges. Even changes that seem small on their own—such as changing finish materials, relocating equipment, adding partitions, altering openings, or adding storage or lighting—can lead to material procurement, rescheduling of tradespeople, drawing revisions, and adjustments to the work schedule. If work proceeds based only on verbal confirmation at the site, it becomes difficult to verify the reasonableness of the costs later.


To avoid additional charges, you should not simply choose the cheapest estimate; you need to align the scope of work, estimate breakdown, site conditions, change rules, work schedule conditions, record-keeping methods, and settlement terms. From here, we'll examine seven concrete points to check in practice.


Checkpoint 1 Clarify the construction scope in words and drawings

The first thing to confirm to avoid additional charges is a clear definition of the scope of work. In building construction, multiple parties are involved—the client, the designer, the contractor, subcontractors, and others. Even when they use the same words, the scope each party assumes can differ. For example, “interior work” may refer only to wall and floor finishes, or, depending on the project, it may include substrate repairs, adjustment of fixtures and joinery, coordination with electrical installations, removal of existing elements, and disposal of waste materials.


Rather than relying solely on verbal explanations, it is important to confirm the scope of work by combining drawings, specifications, estimates, and site photos. Indicate the construction scope on the floor plan and make clear which rooms, which walls, which floors, and which ceilings are included. For renovation work, separating the parts to be retained from the parts to be removed helps reduce later misunderstandings. If exterior works or outdoor equipment are involved, also confirm the boundary with the main building, the work area within the site, the delivery routes, and temporary storage locations.


When confirming the scope of work, how exclusions are treated is also important. If only the included work is listed, stakeholders may unconsciously interpret it in a self‑serving way. Therefore, it is desirable to explicitly state, before contracting, the work that is not included. For example: relocation of existing equipment is not included; moving furniture is handled separately; night work is handled separately; additional substrate repairs are subject to consultation. Organizing foreseeable exclusions in this way makes it easier to make decisions during the construction.


Particular attention should be paid to the interface between architectural work and equipment work. If the scope between the architectural side, which constructs walls and ceilings, and the equipment side, which handles wiring, piping, air conditioning, sanitary, and low-voltage systems, is unclear, additional work is likely to occur for reinforcement at openings, inspection openings, penetration treatments, and restoration work. It is important to confirm in advance which estimate includes these items, who will perform the work, and who will finish it.


The purpose of clarifying the scope of work is not to impose detailed restrictions on the contractor. Rather, it is to make the initial conditions clear so that, if changes occur, they can be properly discussed. If the initial agreement is clear, it will be easier to organize the reasons, scope, cost, and impact on the schedule when additions become necessary.


Checkpoint 2: Confirm the estimate breakdown and the work not included

When reviewing construction estimates, it is important not to judge them based solely on the total amount. When comparing bids from multiple companies, you tend to focus on whether the price is high or low, but in reality the scope of work and the underlying assumptions can differ. Even an estimate that appears cheap at first glance may treat necessary tasks as extras, resulting in additional charges after work has started and ultimately causing you to exceed your budget.


In an estimate, first check the granularity of the items. By checking how materials, construction, removal, disposal, delivery, protection, cleaning, temporary works, safety measures, and management fees are itemized, you can assess the transparency of the contents. The term "lump-sum" is not always bad, but when important construction items are broadly consolidated, it's safer to check what is included. This is especially important in renovation work: be careful to confirm whether the scope of repairs after removal, measures for existing defects, substrate adjustments, and finish restoration are listed separately.


Next, check the conditions for the estimate. The required effort will vary depending on site conditions such as construction hours, work days, delivery requirements, parking, material storage, elevator use, neighbor coordination, restrictions on noise and vibration, and work carried out while the building is occupied. Even if the estimate assumes normal working conditions, if night work or staged construction becomes necessary in practice, it is likely to incur additional costs.


Also, estimates may include phrases such as "separate work," "not included," "to be discussed," and "after on-site inspection." These are important signs indicating the possibility of additional charges. If you find them, confirm under what circumstances additional charges will be applied and the extent to which the original amount will cover costs. Entering into a contract while leaving vague wording in place will make it difficult to make judgments later.


Care is also required when there are owner-supplied or client-arranged items. When the client provides materials or equipment, you must decide the delivery timing, storage location, receipt procedures, how damage will be handled, and whether the contractor can install them; otherwise, this can cause schedule delays or reordering. If the delivery of supplied items is delayed and the scheduled tradespeople are left idle, it may be necessary to negotiate additional costs or schedule changes.


The purpose of reviewing an estimate is not to question the construction company's price, but to align the assumptions included in the estimate. By checking not only the total amount but also what is included, what is excluded, and which conditions would trigger additional charges, you can more effectively reduce the risk of exceeding your budget.


Checkpoint 3: Document on-site surveys and existing conditions

In construction projects, the accuracy of site surveys has a major impact on the occurrence of additional charges. Even if drawings and historical records exist, the actual building or site may not match them. It is not uncommon for drawings and current conditions to differ due to post-completion renovations, equipment upgrades, partial repairs, or changes in use. If estimates or contracts proceed without thoroughly confirming on-site conditions, unforeseen work is more likely to arise after construction begins.


During on-site surveys, we check dimensions, deterioration conditions, finishing materials, substrates, locations of piping and wiring, delivery routes, work space, and the surrounding environment. In renovation work there are parts that can only be understood after removing existing walls or floors, but it is important to record at least the visible areas. If you photograph cracks, traces of water leakage, corrosion, tilting, level differences, interference from existing equipment, and lifting of finishes, it will be easier later to determine whether a defect was caused by the work or was pre-existing.


Recording the existing conditions is effective for both the client and the contractor. For the client, it provides a basis to avoid unnecessary additional charges. For the contractor, it serves as documentation to explain defects that existed from the outset. If both parties share the same site information, discussions when problems arise are less likely to become emotional and decisions can be made based on facts.


Pre-construction documentation is particularly important when work is carried out while a building remains in use. In offices, shops, facilities, apartment buildings, warehouses, and similar places, if existing furniture, fixtures, scratches on floors and walls, and the operational status of equipment are not recorded, the extent of responsibility for damage or dirt after the work can become unclear. Taking photographs before work begins and sharing them with the relevant parties makes it easier to prevent unnecessary disputes.


Also, the results of the site survey must be reflected in the estimate conditions. If a narrow delivery route was identified during the survey but not reflected in the estimate, if relocation of existing equipment appears necessary but is left for separate negotiation, or if work hours are restricted but the estimate is based on standard processes, additional costs are likely to arise after construction begins. The site survey should not end with simply observing; it is important to link it to the estimate, the schedule, and the construction plan.


Checkpoint 4: Decide the approval rules for specification changes and additional requests

During construction, the client may request changes to the specifications or additional requests. It is natural to want to change finishes after seeing the actual space, adjust equipment locations, increase storage, or improve usability. However, if changes are made without checking their impact on costs and the schedule each time, you may receive a lump-sum additional charge after completion, making budget management difficult.


To avoid additional charges, you need to establish approval rules for changes and additional requests in advance. If the contractor proceeds based on verbal requests made by on-site personnel, internal approvals and budget authorization may not catch up later. Especially when multiple people in charge are involved on-site, it is important to clarify whose instructions are to be regarded as official.


When a change occurs, confirm the change details, the reason, the scope of impact, a rough estimate or quotation, the effect on the schedule, and the approver before starting work. Even when emergency response is required, it is desirable to at least keep a record and整理 the approval details afterward. Small changes can accumulate into significant additions. What may appear minor on site can still require reordering materials or additional visits from craftsmen.


When specifications change, you must also check the impact on already-completed work. For example, even if you only intend to change finish materials, the substrate dimensions, detailing, drying periods, and interfaces with adjacent components may change. Changing equipment locations can require rewiring and replumbing, adding access panels, and repairing walls or ceilings. Clients tend to judge solely by the finished appearance, but on the contractor’s side unseen rework can occur, affecting costs and the construction schedule.


When setting approval rules, the objective should be not to prohibit changes but to make them manageable. In construction work, there are times when better decisions are made on site. By confirming whether costs will be incurred, the schedule will be extended, or other trades will be affected before deciding, you can achieve change management that people can accept.


Checkpoint 5 Verify the impact of process changes and provisional conditions

Additional charges arise not only from changes in materials or the scope of work, but also from changes in the construction schedule or temporary site conditions. In building construction, the coordination of craftsmen, delivery of materials, use of equipment, installation of scaffolding and protective coverings, delivery timing, and the sequence of tasks are all organized according to the schedule. Therefore, if the schedule changes due to the client’s circumstances or changes in site conditions, extra work not included in the original estimate may occur.


For example, construction that was originally planned to proceed continuously may have to be carried out in phases due to the facility users' schedule. When work is repeatedly interrupted and restarted, each time preparation, protective measures, cleanup, material delivery, and inspections are required. Even if the overall construction period does not extend significantly, the contractor's workload increases, so the project may become subject to additional negotiations.


Temporary arrangements are also important. Scaffolding, work platforms, protective coverings, temporary enclosures, delivery routes, material storage areas, temporary power, temporary water supply, and safety passages are conditions necessary to carry out construction. If the workspace is smaller than originally anticipated, there is no place to store materials, access routes are restricted, or work must be performed while maintaining user traffic flow, the temporary works plan will need to be revised. Temporary works are often overlooked because they do not remain after completion, but in reality they are indispensable for ensuring safety and quality.


To assess the impact of schedule changes, it is important to share a rough construction schedule before work begins and for the client to communicate any constraints. If days when work cannot be performed, time periods when noise is prohibited, permitted delivery times, periods requiring consideration for neighbors and tenants, and equipment that cannot be shut down for operational reasons are organized in advance, the contractor will find it easier to put together a realistic schedule.


Also, if there is a possibility that the work schedule will change, you need to confirm which kinds of changes will lead to additional costs. Interruptions due to the client’s circumstances, waiting caused by delays in other works, changes in arrangements due to approval delays, and delays in client‑supplied materials can all be factors that result in additional charges or extensions of the project schedule. By clarifying the scope of responsibilities, it becomes easier to avoid situations in which later claims are perceived as unilateral.


The work schedule and temporary site conditions are aspects that are not easy to discern from the estimate amount alone. However, because they directly affect how work proceeds on site, confirming them in advance can help prevent additional charges.


Checkpoint 6: Centralize on-site construction records and meeting histories

When disputes arise over additional charges in construction work, in many cases the problem is not “who said what” but that no record remains. Various decisions are made on site every day. Adjustments to details, material changes, changes to the sequence of work, responses to existing defects, confirmations of additional requests, and so on cannot all be managed by the contract alone. Therefore, it is important to centrally manage records and meeting histories during construction.


When a meeting is held, record the date and time, participants, items to be confirmed, decisions made, items on hold, and the person responsible until the next meeting. Matters related to costs or the schedule, in particular, should not be handled verbally; make sure they are documented so they can be verified later. Treat issues that cannot be answered immediately on site as “under review” and set a deadline for the formal response to reduce the risk that the contractor will proceed prematurely.


Photographic records are also effective. By keeping photos taken before, during, and after construction, you can verify which work was carried out at each stage. Parts that will become concealed—such as the substrate, rebar, piping, wiring, insulation, waterproofing, and repaired areas—are particularly important because they will no longer be visible afterward. If photos alone are difficult to interpret, organize them so that the location, shooting direction, date, and content are clear.


In records concerning changes and additions, clearly identify the requester and the approver. When there are multiple stakeholders on site, the representative from the user department may request something for convenience that the person with ordering authority is unaware of. If work proceeds in this state, it can lead to disputes later over approval of additional charges. There needs to be a mechanism to route on-site requests through the formal approval process.


Centralized management means not only keeping records but ensuring that all relevant parties can view the same information. When information is scattered across personal devices, individual messages, paper notes, and verbal communications, it becomes difficult to reconstruct the overall picture later. By deciding in advance the storage location for records, file-naming conventions, rules for updates, and how the latest version is handled, you make it easier to prevent information gaps and duplication.


Construction records are not just material for refusing extra charges. If additional work is necessary, having records makes it easier for the client to accept it. Conversely, if a claim lacks sufficient justification, it can be verified against the records. Recording the facts helps protect both the client and the contractor.


Checkpoint 7: Align final inspection and settlement terms in advance

Additional charges for construction work can become an issue not only during the work but also at the settlement stage upon completion. When additional costs are explained all at once after the work is finished, the client finds it difficult to verify the details. Because the work has already been completed, it is hard to verify the necessity and reasonableness on-site, and internal approval also takes time. Therefore, it is important to align the completion inspection and settlement conditions in advance.


In the final inspection, you check whether the work has been completed in accordance with the contract, whether there are any problems with the finish, and whether there are any items requiring correction. At that time, it is necessary to separate and organize the original contracted work, approved additional work, unapproved changes, and outstanding items. If there are additional charges, confirm which instruction they are based on, when they were approved, and which records they correspond to.


In the settlement terms, confirm the timing for submitting estimates for additional work, the approval method, the timing of invoicing, payment terms, and how items subject to reductions are handled. It's important to consider not only additions but also reductions when the scope of work decreases. Deciding in advance how to settle accounts if originally planned work becomes unnecessary or specifications are simplified makes fair management easier.


Also confirm the scope of post-handover support. Defects found immediately after completion of the work, adjustments found to be insufficient after the start of use, and defects caused by the client’s method of use tend to make the scope of responsibility ambiguous. By clarifying in advance what constitutes corrective action and what counts as additional work, you can more easily prevent billing disputes after handover.


At completion, we also check the handover materials such as drawings, photographs, warranty documents, operating manuals, and inspection records. If these are missing, additional investigations may be required for later repairs or maintenance. Construction work does not end when it is completed; it leads into subsequent operation and maintenance. Preparing and organizing the records together with the final settlement helps with long-term cost management.


If you decide on the completion inspection and settlement terms in advance, you’ll be less likely to be rushed toward the end of the construction. To avoid additional charges, management must be planned with an eye not only to the pre-construction and construction phases but also to the verification at completion.


Preventing Additional Charges Requires Accurate Sharing of On-Site Information

As we have seen, avoiding additional charges in building construction requires considering the contract, estimates, site surveys, change management, schedule management, recordkeeping, and settlement as an integrated whole. Among these, the practical key is the accuracy of shared site information. Whether determining the scope of work, verifying estimate breakdowns, describing existing conditions, or judging the necessity of changes, decisions become unclear without accurate site information.


When on-site information is lacking, stakeholders tend to make judgments based on their own experience and assumptions. The client may assume something is obviously included, the contractor may think they explained it would be handled separately, and the designer may believe they made decisions within the scope shown on the drawings. Such differences in understanding are not caused solely by one person's lack of attention. The root cause can sometimes be that information has not been shared in the same form.


Organizing on-site photos, measurements, location data, inspection records, pre- and post-construction comparisons, and records of concealed elements makes it easier to objectively determine whether additional work is necessary. Recording the existing conditions is especially important in renovation projects and building works that involve ongoing maintenance. Accurately preserving the site's condition also serves as a useful reference for subsequent work and future repair planning.


In recent years, it has become necessary to establish an environment where information obtained on site can be shared immediately and verified among stakeholders. Relying only on paper drawings and verbal communication has limits when it comes to updating information and managing records. If on-site measurements, photo organization, position verification, and record sharing can be made more efficient, it becomes easier to reduce misunderstandings that lead to additional charges.


Measures to address additional claims in construction work are not merely contract management but also information management to accurately understand site conditions. It is important for the client's operational staff to be aware not only of comparing estimates but also of how to obtain site information, how to share it, and how to link it with approval records.


Therefore, if you want to streamline on-site measurement and recordkeeping, you should consider options such as photo management, drawing sharing, cloud-based construction management tools, and site-recording tools capable of handling location information, selected according to the scale of the work and your company rules. More important than whether to adopt any particular tool is standardizing the format of records, storage locations, approval histories, and how they are shared with stakeholders as a measure against additional billing.


Summary: Additional charges for construction work can be minimized through prior confirmation and documentation

Completely eliminating additional charges in construction work is not easy. There are uncertainties on site, and depending on the condition of existing buildings and decisions made during construction, responses different from those initially anticipated may be required. However, many additional charges can be prevented or negotiated to a mutually acceptable outcome by confirming in advance the scope of work, terms of the estimate, site conditions, change approvals, construction schedule conditions, record management, and final settlement.


First, it is important to clearly define the scope of work in words and on drawings, and to identify work that is excluded. Next, verify not only the total amount on the estimate but also the itemized breakdown and any separate conditions. Furthermore, during the site survey, document the existing conditions with photos and records and reflect them in the estimate and the schedule. For specification changes or additional requests during construction, establish approval rules and proceed only after confirming the impact on cost and schedule.


Also, because schedule changes and temporary site conditions tend to lead to additional claims, it is important to share site constraints before construction begins. During construction, centrally manage meeting records, photos, and change histories so that all stakeholders can confirm the same information. Upon completion, organize inspections, corrective actions, additional work, and settlement/payment terms to prevent billing details from becoming unclear after the project.


In construction practice, it is ultimately more important to establish conditions that make additional charges less likely than to choose the cheapest estimate. To avoid additional charges, it is essential not only to carry out pre-contract checks but also to maintain ongoing information sharing and thorough record-keeping during construction. By accurately grasping site conditions and putting in place a system that allows all stakeholders to make decisions based on the same information, budget management tends to become more precise.


When planning building construction, it is important to treat the process as a continuous flow—from the estimate stage through site surveys, record keeping, and change management. To keep site information accurate and reduce misunderstandings that often lead to additional charges, review your company's approval rules and recording methods, and, where appropriate, implement systems to support construction management and on-site record keeping.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page