top of page

Table of Contents

• Reasons why as-built management is attracting attention in drone surveying

• Point 1: The more a type of work needs to be measured by area, the more suitable it is

• Point 2: The important thing is to decide the required accuracy first

• Point 3: Results change depending on the choice of reference points and the georeferencing approach

• Point 4 Decide in advance what to use as the outcome

• Point 5: Consider it on the premise of being combined with conventional surveying.

• Point 6 Design an operational framework capable of sustained operation

• Summary


Can as-built management be done with drone surveying? This is a question often asked by practitioners involved in civil engineering, land development, exterior works, and infrastructure construction. To answer briefly, drone surveying can be used for as-built management. However, it cannot unconditionally replace other methods on every site. There are types of work and situations where it is suitable and others where it is not, and practical usability varies greatly depending on how required accuracy is considered and whether supplementary ground-based measurements are performed.


Conventional as-built management has centered on confirming height, width, and length at predetermined survey points and cross-sections, then organizing and recording the results. While this method remains important, it has the drawback of making it difficult to capture the entire site as a surface. For example, measurements at a few points may not reveal problems, but when viewed as a surface, localized irregularities or variability in shaping can remain. What has attracted attention, therefore, is broad-area three-dimensional acquisition using drone surveying. If the entire site can be photographed in a short time and visualized as point clouds, orthophotos, and elevation models, it becomes easier to grasp construction progress and any biases in the finished work at an early stage.


On the other hand, it is also true that expecting too much from drone surveying makes failure more likely. At worksites there are many factors that affect measurement results, such as wind, lighting conditions, ground surface patterns, slope angles, the movement of heavy equipment, and mud after rain. Moreover, as-built management is not merely the task of checking appearance; it is the work of objectively showing how much deviation there is from design values and control standards. Therefore, if you introduce drone surveying, you must design the process not around flying and capturing images as an end in itself, but including which stage, what information, at what accuracy, and who will use it.


This article outlines six key points that are particularly important in practice for practitioners who want to advance as-built management using drone surveying. Focusing on perspectives for judging whether it can actually be used on site, it should be useful both for organizing considerations before implementation and for reviewing operations.


Why As-Built Management Is Attracting Attention in Drone Surveying

The main reason drone surveying is attracting attention in as-built management is that it makes it easier to understand the site in terms of surfaces. For example, on sites such as embankments, cuttings, development faces, slopes, temporary roads, and material yards—where a large area needs to be finished to a consistent shape—looking at the condition of the entire surface provides a judgment closer to the actual situation than managing by surveying only points. If aerially captured data is processed and converted into a three-dimensional model, it becomes easier to comprehensively confirm differences between the existing ground and the design surface, increases or decreases in earth volume before and after construction, the positional relationships of slope shoulders and slope toes, and subtle elevation differences that affect drainage direction.


Another major advantage is that it is easy to perform repeated measurements. As-built management isn't only meaningful at completion. If deviations in shape can be identified during construction, rework can be reduced. For example, if you check the rough shaping of each layer of embankment, you can lower the risk that major corrections will be required at the final finishing stage. Taking photographs weekly or at the end of each work stage makes it easier to compare construction progress and the finished result over time, providing more information to support site management decisions.


However, the important point here is that drone surveying does not magically automate as-built management itself. Simply taking photos does not constitute management. Only after converting the acquired data into georeferenced deliverables, comparing them with design values and control standards, and organizing them as necessary records does it become usable for as-built management. In other words, drone surveying is a means, not the management itself. Worksites that understand this premise tend to be more likely to realize the benefits of its adoption.


Point 1: Better suited to trades that you want to understand at the surface level

Whether drone surveying is suitable for as-built management is primarily determined by its compatibility with the type of work. The best match is earthwork sites that have large surface areas. Typical examples where drone surveying tends to show its strengths are grading of development sites, progress checks of cut-and-fill, slope shaping, and estimating the volumes of surplus or temporarily stockpiled soil. The reason is simple: in these types of work, quality is directly tied to the continuity of surfaces rather than to individual points. Being able to check local elevation differences, overall undulations, and deviations from the planned surface as continuous areas is highly valuable, and it is easy to assess wide areas in a short time.


Also, even on sites with long linear layouts, it can be effective if a certain width and a relatively open line of sight can be secured. For example, on long, extended construction yards, management access paths, or access routes within a development area, it can be faster to capture the whole site from the air than to track it in detail on the ground. Drone surveying can be an easy-to-use method in situations where site staff want to check the overall picture before or after the morning briefing, or want to grasp work progress and as-built condition at the same time.


Conversely, there are situations where drone surveying alone is difficult. For example, areas where trees are densely clustered and the ground surface is hard to see; places that cannot be observed from above, such as the backs of structures or under eaves; narrow locations with significant flight restrictions; parts that are buried underground; and portions that will become invisible after completion, such as internal structures before rebar placement or backfilling. For these locations, there are limits to managing them with aerial photography alone. Such areas need to be combined with other measurement methods, photographic records, and on-site inspections during construction.


In other words, the first step to succeeding in as-built management with drone surveying is not to try to replace everything. Understand that its strength is in area-focused parts, and carefully distinguish which trades, which processes, and which scopes it is most effective to apply to. If you try to apply it uniformly across the entire site from the start, unnecessary shooting and excessive processing will increase, making operations more burdensome. It is realistic to begin by using it in situations where area-based understanding directly translates into results, such as earthworks and grading.


Point 2: It is important to decide the required accuracy first

In as-built management using drone surveying, the most commonly misunderstood concept is accuracy. In practice, people often assume that if a drone can produce a 3D model, it can be used as-is for all as-built verifications. However, in reality the required accuracy varies depending on the type of work and the application. The accuracy needed to check trends during construction is not the same as the accuracy required for the control values submitted as final deliverables. If this distinction is left ambiguous when introducing the technology, it often leads later to the assessment that it’s “not as useful as expected.”


In as-built management, it is necessary to be aware of both absolute accuracy and relative accuracy. Absolute accuracy refers to how correctly the on-site data are positioned in coordinate space. Relative accuracy, on the other hand, refers to how stably differences or changes on the surface can be compared when the same site is measured repeatedly. If you only want to observe the amount of change during construction or overall trends, it is important to be able to acquire data consistently under the same conditions each time. Conversely, if you need to rigorously judge the final error relative to reference values, alignment with ground control is more important.


There are many factors that affect the accuracy of drone surveying. If the flight altitude is too high, ground resolution becomes coarse, and if overlap is insufficient, 3D reconstruction becomes unstable. In areas with few surface features, alignment becomes weak, while conversely, if patterns are too fine, noise can increase. On slopes, shadows and texture bias tend to appear, and even in clear weather results change depending on the time of day. Furthermore, at sites where the soil surface is soft and heavily rutted, an interpretive issue arises about where to read the as-built surface. In other words, accuracy is not determined by equipment alone but is the combined result of site conditions and processing conditions.


Therefore, in practice you need to decide in advance "how many centimeters (cm; in) of difference you want to detect," "which surface will be the target of assessment," and "whether you will use it for final confirmation or for interim checks." For interim management, being able to quickly grasp broad trends over a wide area has value. For final confirmation, it is safer to secure key points by ground surveying while using a drone as an auxiliary means to obtain an overall picture. If you determine the required accuracy beforehand, the flight conditions, the placement of ground control points, and how you produce the deliverables will naturally be decided. Conversely, if those points are vague, both how you fly and how you process the data will vary each time, and the reliability of the results will not be stable.


Point 3: Results Vary Depending on the Treatment of Reference Points and Calibration

If you want to stabilize as-built management using drone surveying, you must not overlook the concepts of control points and georeferencing. On site, attention tends to focus on imaging and analysis, but what actually determines the reliability of the results is how you establish references on the ground. Even when surveying the same site repeatedly, if the coordinate reference is ambiguous it becomes difficult to tell whether differences from the previous survey are real changes or simply misalignments in positioning. That undermines the credibility of your as-built management.


What is particularly important is to have reference points located in stable places that will not move during construction. If you place references in areas where the terrain changes as the work progresses, they will not only become unusable at the next survey but will undermine the very basis for comparison. On land development and earthwork sites, it is important to set references near the perimeter or close to fixed objects that are less affected by construction, and to operate under the same reference system even when measurement timing changes. If the positions of the ground control points used for each capture are inconsistent, it may look fine on the surface, but over long-term comparisons subtle shifts will accumulate.


Also, it is useful to have ground control points. Even if the drone uses position-correction features, don’t rely on them alone; establishing points on the ground that can be independently verified makes it easier to assess the validity of the analysis results. In as-built management, being able to explain how much confidence can be placed in the results is more important than the results merely appearing good. With control points, it becomes easier to share on site that the current data falls within a certain level of deviation.


Furthermore, from the perspective of construction quality control, it is important not only to leave references but also to keep records. If you organize the installation positions of reference points, their names, photographs, observation dates and times, the coordinate system used, processing conditions, and so on, it will be easier to maintain reproducibility even if the person in charge changes. Drone surveying does not guarantee that a method that worked once will be automatically reproducible the next time. That is precisely why the concept of references needs to be established as an on-site rule. If you are serious about using drone surveying for construction quality control, it is essential to include not only flight planning but also reference management in the operational design.


Point 4 Decide in advance what to use as the deliverable

When conducting as-built management with drone surveying, you need to decide before shooting which deliverables you will use to make judgments. This is a point that is surprisingly easy to overlook. On site, teams sometimes only start thinking about what to produce after flying and collecting data. However, the deliverables required for as-built management differ from site to site. Whether you prioritize planar positional checks, elevation difference checks, wanting to know earthwork volume changes, or comparing cross-sections will change the types of deliverables used, the processing methods, and the required resolution.


For example, orthophotos can be useful for visually organizing the construction area and sharing planimetric positions. They are suitable for checking construction boundaries and progress areas, organizing heavy equipment movement routes, and getting an overview of the entire site. On the other hand, if you want to evaluate heights and shapes, point clouds and elevation models are required. If you want to check the shaping condition of slopes, the height of the top of embankments, whether cut faces have been over‑excavated, or differences from the design surface, you cannot make those judgments without three-dimensional deliverables. Furthermore, to fulfill accountability for as‑built conditions, it is necessary to convert the data into easily comparable formats such as cross-sections, difference maps, and volume calculation results.


What’s important here is not to create too many deliverables. Drone surveying can produce a wide variety of outputs, but only a limited number are actually used in practice. What field staff check each time are often drawings that show deviations from the design and comparative outputs that can be used to judge progress, and simply storing point cloud data alone does not lead to practical use. Conversely, if the required deliverables are clear, it becomes easier to organize acquisition conditions. For example, if you want to examine slope geometry in detail, you need a flight plan that prioritizes reproducible reconstruction of the slope, whereas if earthwork volume comparison is the main objective, stable capture of the entire surface takes priority.


How results are presented is also important. As-built management should not be something only the analyst can understand. It needs to be prepared in a form that the site representative, construction management staff, partner companies, and, in some cases, the client can all understand. Converting data into formats that are easy for anyone to interpret—colored difference maps, cross-section comparisons at regular intervals, overlays by construction stage—speeds up on-site consensus. Even if you introduce drone surveying, if the intended use of the outputs is unclear they tend to remain merely reference materials. Deciding before you capture data what will be retained as deliverables and what will serve as the basis for decisions is the key to practical use.


Point 5 Consider it on the premise of combining with conventional surveying

Drone surveying can be used for as-built management, but in practice it works better to assume it will be combined with conventional surveying. If you get this wrong, expectations tend to be high immediately after introduction, but dissatisfaction often grows during the operational phase. This is because drone surveying has clear strengths and weaknesses. While it excels at wide-area surface management and progress tracking, there are many situations where ground-based surveying is more effective for checking fine edges, measuring hidden parts, and rigorously verifying critical control points.


A practical division of roles is to use drone surveying to grasp the overall situation and to verify the key points on the ground. For example, drone surveys are well suited to detect deviations in embankment surfaces during construction, slope continuity, overall height trends, and increases or decreases in earth volumes. On the other hand, items that become critical in the end—corner points, edges, interfaces with structures, narrow passages, shaded areas, and locations that are frequently disturbed by construction equipment—are more reliably supplemented by ground surveys. Clarifying this division of roles helps avoid placing excessive expectations on drone surveying and makes it easier to improve efficiency while maintaining the necessary accuracy.


Also, in construction quality control, it is not necessary to read every value directly from the surface data. Rather, it is more reasonable to review the surface data to extract locations that are likely to be anomalous and focus on conducting ground verification there. This reduces the need to chase every detail across the whole site as before, allowing labor savings without reducing the thoroughness of monitoring. In other words, the value of drone surveying lies not in replacing everything, but in making it easier to find the places that need to be checked.


Furthermore, combining it with conventional surveying increases the explanatory power on site. If the overall view obtained by the drone and the numerical measurements taken at key ground points agree, it becomes easier to justify the validity of the as-built condition. Conversely, relying on only one of the two weakens the supporting evidence when judgments are difficult. For practitioners, what matters is not the purity of the methodology but whether it can be relied on for management. In that sense, drone surveying is more likely to succeed in on-site adoption if it is regarded not as an independent alternative but as a means to strengthen conventional surveying.


Point 6 Design a structure that enables continuous operation

If you plan to use drone surveying for as-built management, it's important to design a system that supports continuous operation rather than just taking measurements once and stopping. Data only becomes truly valuable on site when it's accumulated under the same conditions, according to the same standards, and using the same decision criteria. Even if you happen to get a good measurement once, comparisons lose meaning if next time a different operator flies, the flight altitude and time of day differ, and the processing settings are not the same. As-built management is continuous quality control, so operational reproducibility is indispensable.


First of all, what you should set up are the rules for flight conditions and measurement timing. Decide on site rules such as at which milestone of the process to take photos, whether to avoid just after rain, how to handle times when slope shadows are strong, and whether to avoid periods with many heavy machines—doing so stabilizes data quality. On earthwork sites, appearance changes easily depending on surface moisture and the way ruts form, so the effect of standardizing shooting conditions is greater than you might expect. If the conditions differ each time, it becomes difficult to determine whether differences are caused by construction or by acquisition conditions.


Next, the rules for organizing data are important. If you don't standardize items such as the shooting date, process name, scope of coverage, standards used, processing conditions, and the storage location for results, it will be difficult to compare later. In as-built management, data that is meaningful when compared is more important than the data as recorded at the time of capture. Nevertheless, in practice file names and storage locations are often inconsistent, and just locating the previous data from the same site can take a long time. This causes it to stop being used on site. Including data management as part of the system is a prerequisite for ongoing operation.


Furthermore, it is necessary to clearly define who will make which decisions. The person in charge of imaging, the analyst, and the verifier of the as-built assessment can be different people, but if the evaluation criteria are not shared, the results will not be useful on site. For example, if you align in advance what level of deviation should prompt consideration of rework, which ranges should be treated as reference values, and which cross-sections should be prioritized for inspection, the data will not remain mere images or point clouds but will directly inform decision-making. Drone surveys are visually attractive, but that very attractiveness can make it easy to get lost in too much information. Precisely for that reason, it is important to share on-site the indicators that should be checked.


Additionally, organizing safety and regulatory aspects is indispensable for continued operation. Depending on site conditions, permitted flight times and methods may be restricted, and consideration for the surrounding environment is also necessary. As-built management is a continuous task, so it will not become established if work is halted for adjustments each time. By preparing in advance whether flight is permissible, work procedures, perimeter checks, and communication protocols, you can reduce the burden on the site. To make a system usable in practice, it is essential to design not only the technology but also the ease of operation.


Summary

Drone surveying can be used for as-built management. However, that answer is not a simple “yes.” It is particularly well suited to work types that you want to capture as surfaces, and only when you first define the required accuracy, tie measurements to ground control, clarify the deliverables to be used, appropriately divide roles with conventional surveying, and establish a system for continuous operation will it become usable for practical as-built management. Conversely, simply taking aerial photos and converting them into 3D models is not sufficient for as-built management.


What is really needed on site is not clean three-dimensional data but reliable information that leads to construction decisions. If you can quickly tell where elevations are high, where they are low, where construction is uneven, and at what stage corrections should be made, you can reduce rework and more easily improve the quality of management. In that sense, it is more practical to regard drone surveying not as a tool to replace as-built management but as a means to better visualize as-built management and enable faster decision-making.


To link the results obtained by drone to on-site verification and supplementary surveying, it is also important to have an environment on the ground where coordinates can be captured quickly and accurately. For example, in situations where you want to smoothly perform verification of control points, supplementary measurements, positioning of photos, and additional on-site checks, an iPhone-mounted high-precision GNSS positioning device like LRTK can be useful. If you can use drone surveying to view the whole site and then quickly secure the necessary locations on-site, the operation of as-built management becomes more practical. Rather than treating drone surveying as a one-off capture, thinking in terms of connecting it to the entire on-site measurement workflow will become increasingly important for future as-built management.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

​

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page