How to Accurately Calculate Embankment Volume|Practical Techniques for Using 3D Point Cloud Data On-site
By LRTK Team (Lefixea Inc.)
Embankment work at construction sites is not merely about hauling and piling soil; it is a critically important process that requires meticulous management based on precise volume calculations. Traditional surveying methods created cross-sectional diagrams from multiple measurement points and calculated volumes from those, but this approach had many challenges and limitations. The more complex the site terrain, the more subjectivity seeps into the placement of measurement points, and errors in the final volume calculation accumulate. Moreover, even when multiple surveyors perform the same task, their results can vary, which can undermine consistency in management. However, leveraging 3D point cloud data greatly improves this situation. A 3D point cloud refers to the coordinate information of millions to tens of millions of points acquired by laser scanning or drones, and by analyzing these with advanced processing techniques, more accurate and reliable volume calculations have become achievable.
In this article, we provide a detailed explanation of the methodologies for accurately calculating the volume of embankments and practical on-site approaches that utilize 3D point cloud data. In particular, we offer practical insights into which methods can resolve the specific challenges faced by practitioners and how to introduce the latest technologies. From the three perspectives of pursuing accuracy, improving efficiency, and reducing costs, we explain the value of using 3D point clouds for volume calculation.
Conventional Methods for Calculating Embankment Volume and Challenges
Conventional embankment volume calculations have mainly been carried out using a combination of two methods: the cross-section method and the longitudinal-section method. In the cross-section method, multiple sections perpendicular to the construction alignment are set, the amount of soil at each section is calculated, and the overall embankment volume is obtained from their sum. This approach is particularly effective for linear projects such as roadworks and has been adopted as a reliable method on many sites for many years. Typically, cross sections are set at intervals of 10 m (32.8 ft) to 20 m (65.6 ft), and the surface elevation at each position is estimated from multiple measurement points. However, when the site topography is complex—for example, when valley topography is intricately indented, existing structures are scattered, or rock is exposed—judgment is required to determine appropriate section locations.
At the stage of selecting cross-section locations, there is a serious problem in that the surveyor's experience and judgment can greatly influence the results. For example, if cross-sections are collected at 10 m (32.8 ft) intervals at one site but at 15 m (49.2 ft) intervals at another, calculations may differ even for the same terrain. In the worst case, calculation errors can exceed 5 percent, which in large-scale projects can amount to differences in earthwork volume of hundreds of cubic meters or more. Furthermore, fine topographic changes between cross-sections cannot be fully captured by the cross-section method. If the ground surface undulates, if there are locally deep depressions, or if embankments have been constructed to accommodate complex terrain such as alluvial fans, these features are not reflected in the calculations, resulting in systematic errors in the final volume.
The longitudinal section method also suffers from the same problems. In this approach, cross-sections are produced along the project’s centerline and volumes are calculated from terrain changes before and after construction. However, terrain changes in the direction perpendicular to the centerline are difficult for these section methods to reflect accurately. In particular, when the terrain changes abruptly near the edge of an embankment, accurately capturing those changes requires many measurement points, which in turn greatly increases the surveying workload. In addition, the terrain can change slightly over time, making it difficult to verify whether any unintended terrain changes occurred between the pre-construction and post-construction measurements.
Characteristics and Advantages of 3D Point Cloud Data
3D point cloud data has the potential to fundamentally solve the challenges of conventional cross-section methods. A 3D point cloud is a digital record of the coordinates of countless points in space, with each point containing three-dimensional information: X, Y, and Z coordinates (elevation). Such dense point cloud data can be efficiently acquired by a combination of laser scanners, cameras and IMUs (inertial measurement units) mounted on drones, and GNSS receivers. The important point is that this point cloud data captures even subtle undulations of the ground surface. Terrain changes on the order of millimeters (mm (in)) are also recorded and stored as data.
The greatest advantage of 3D point cloud data is its overwhelmingly high density of measurement points. In conventional surveying, depending on site conditions, it was common to have several dozen to several hundred measurement points per hectare. By contrast, 3D point clouds can provide tens of thousands to hundreds of thousands, and in some cases millions, of points for the same area. This dramatic difference in density means that fine variations in terrain are fully captured, enabling volumes to be calculated with higher accuracy. Additionally, once 3D point cloud data is acquired, it can be analyzed from various angles and viewpoints afterward. The high reproducibility—that different surveyors analyzing the same data will obtain the same results—is another major advantage that traditional methods could not achieve. Because the objectivity of the data is assured, if questions later arise about calculation results, the data can be easily reused to recompute them.
Furthermore, 3D point cloud data makes time-series comparison extremely easy. By acquiring data at multiple points in time—such as the early, middle, and completion stages of embankment construction—and overlaying them, it becomes possible to precisely determine which parts of the embankment have progressed and by how much, or whether uneven construction is occurring. Such time-series analysis enables improved construction quality and early detection of unexpected problems. Moreover, if a construction quality issue is found, tracing its cause also becomes straightforward. For example, if it is discovered that the embankment height at a certain location is below the planned value, data analysis can help infer whether the reason is machine malfunction, worker error, or ground subsidence.
On-site Methods for Acquiring 3D Point Cloud Data
There are several options for efficiently acquiring 3D point cloud data at an embankment site. The first is using drones equipped with laser scanners. This approach has the major advantage of being able to survey large areas in a short time. Because drones can be flight-controlled without manual labor, they can safely perform surveys on hazardous slopes and in areas that are difficult to access. Typically, they are flown up to an altitude of about 100 m (328.1 ft) above ground and pass over the construction area multiple times to collect survey data. Drone surveying can cover several hectares in a single day, making it particularly time-efficient for large construction areas. However, drone surveying has the drawback of being highly susceptible to weather conditions. Flights become difficult on rainy or windy days, and because the sun's position differs significantly between morning and afternoon, shadow patterns change, which can affect the quality of the point cloud data.
The second option is to use a terrestrial laser scanner. With this method, the scanner is mounted on a tripod and measurements are taken sequentially from multiple positions on site. Terrestrial scanners have the advantage of higher accuracy than drones. Typically, errors are kept to a few centimeters or less (a few inches or less), and measurement accuracy at short range is particularly good. They can also acquire relatively accurate data around complex terrain and existing structures. However, because the area that can be covered in a single scan is limited, many scan positions are required for large construction areas, which in turn increases the time required for surveying work. In addition, it is necessary to register the multiple scans obtained from different positions into a unified coordinate system, and this registration process requires technical effort.
The third option is to use photogrammetry. By processing high-resolution images taken from multiple angles, it generates a 3D point cloud. This approach has the major advantage of being low-cost to implement, and with a drone equipped with a high-performance camera it can achieve sufficient accuracy. However, on soil surfaces with a uniform texture, extracting feature points can become difficult, posing a risk of reduced measurement accuracy. In particular, freshly placed soil often has a uniform surface, and photogrammetry algorithms may be unable to find feature points, so caution is required. The choice of the optimal method should be made by comprehensively considering multiple factors such as project scale, on-site topography, accuracy requirements, budget allocation, and weather conditions.
Process for Calculating Volume from 3D Point Cloud Data
Once 3D point cloud data has been acquired, the subsequent data processing stage becomes extremely important. First, the acquired point cloud data contains noise, and this noise must be removed. Noise refers to points generated by measurement errors rather than the actual ground surface. For example, points captured during periods when the drone was vibrating, points returned from low-reflectivity objects, points representing dust or other particles in the atmosphere, or points where parts of existing structures were mistakenly recorded all count as noise. Properly removing these significantly improves the accuracy of subsequent processing. Statistical methods that automatically detect outliers are often used for noise removal.
Next, it is necessary to distinguish between embankment areas and non-embankment areas. This is called classification processing, in which a computer automatically extracts embankment regions from terrain features or an operator manually specifies the regions. Automatic classification is fast, but because its accuracy may not be perfect, verification is essential. Manual specification takes time but yields more reliable results. In practice, a hybrid approach—checking the results of automatic processing and adjusting them as needed—is the most efficient. For example, workers visually confirm the boundary lines of embankment areas and correct any discrepancies with the automatic classification results.
When the fill area is determined, compare the two point cloud datasets of the pre-construction ground surface and the post-construction ground surface, and calculate the volume difference. This calculation is performed by aligning both point clouds in a unified coordinate system, computing the elevation difference at each point, and aggregating those differences into a grid. The calculation results can be obtained not only as the total volume of the fill area but also as volumes for each smaller subarea. This makes it possible to grasp construction progress in detail. For example, by dividing the construction area into a grid of 5 m (16.4 ft) squares and calculating the volume within each grid, it becomes immediately clear which parts are behind schedule.
Steps for practical use in the workplace
When actually using 3D point cloud data at an embankment site, a phased approach is effective. As the first phase, record the pre-construction conditions in detail. The measurement accuracy at this stage becomes the baseline for all subsequent comparative calculations, so careful attention is required. It is also important to carry out multiple measurements and verify the consistency of the data. Recording all conditions—measurement time, weather conditions, drone flight parameters, and so on—will be useful when conducting quality evaluations later.
In the second stage, after construction begins, data are collected regularly. Generally, measurements are taken when the volume of fill reaches a predetermined reference amount, or when it reaches benchmark quantities indicating construction progress (for example, 30 percent, 60 percent, 90 percent of the plan). These regular measurements allow verification of whether construction is progressing according to plan. If deviations from the plan are found, the causes can be identified and the construction plan adjusted. For example, if it is found that embankment progress in a particular area is significantly below the plan, an investigation can determine whether the cause is an issue with the placement of heavy equipment or an unexpected change in soil properties, and appropriate countermeasures can be taken.
In the third stage, the final volume is measured after construction completion and compared with the design value. This comparison provides the basis for evaluating construction accuracy and for deciding, if necessary, on additional work or corrections. Typically, embankment construction requires accuracy within ±5 percent of the design value, but by utilizing 3D point cloud data this accuracy requirement can be reliably met. In addition, this data can be used to improve accuracy in similar future projects. By analyzing accumulated data to understand construction difficulty under specific terrain conditions, personnel allocation and project scheduling for future projects can be made more rational.
Practical Tips for Improving Accuracy
There are several practical tips for improving the processing accuracy of 3D point cloud data. The first is the installation of ground control points (GCPs). This involves placing multiple points with known coordinates on site and linking them to the measurement data to improve overall coordinate accuracy. Especially in large construction areas, the number and placement of these ground control points greatly affect data accuracy. It is generally recommended to place them at the four corners and the center of the construction area. Ground control points should be made of highly reflective materials and be clearly identifiable during measurement. In aerial surveying with drones, particularly over large areas, it has been reported that using multiple ground control points can improve accuracy by more than five times.
The second is consideration of environmental conditions during measurement. Measuring at the same time of day standardizes the direction of sunlight and minimizes the effects of shadows. You should also avoid measuring on rainy days or days with high humidity. Under those conditions, lasers and cameras can operate unreliably, posing a risk of reduced data quality. In addition, the ambient temperature at the time of measurement also has an impact. In extremely cold environments, drone battery performance declines and flight time is shortened. When planning measurement schedules, it is important to fully take weather conditions into account and select the optimal measurement day.
The third is the selection of data processing software and its proper configuration. There are various point cloud processing software products, each employing different algorithms. By choosing the software that best fits your site conditions and appropriately tuning its parameters, higher accuracy can be achieved. Comparing and evaluating results processed with multiple software products is also an effective quality-assurance method. For example, processing the same point cloud data with several software products and checking the differences in the computed results can reveal that a particular software is not suitable for the characteristics of the site.
The Path to Streamlining Embankment Volume Management
By utilizing 3D point cloud data, the entire process of managing embankment volumes can be greatly streamlined. With traditional methods, surveying through volume calculation could take days to weeks. In contrast, using 3D point clouds can significantly shorten the time from measurement to report preparation. Furthermore, because the data are managed digitally, multiple stakeholders can share the same information, greatly improving transparency in construction management. Project owners, designers, contractors, and supervisors can all access the same data and understand construction progress in real time.
The benefits of this kind of digitization extend beyond merely saving time. By enabling decision-making based on accurate, detailed data, it leads to optimized construction planning and the early detection of problems. In addition, accumulated data can be used as benchmark information for future similar projects, contributing to overall improvements in work quality. For example, if data on the settlement amounts and compaction characteristics of embankments under specific terrain conditions are accumulated, predictive accuracy for new projects will improve.
Currently, many construction companies are adopting embankment management systems that utilize 3D point cloud data. These companies are achieving significant cost reductions and quality improvements through automation of measurements, streamlining of data processing, and standardization of reporting processes. By introducing such cutting-edge technology at your site, you can also expect substantial benefits.
The Potential for High-Precision Measurement Using Smartphones
In recent years, devices that add high-precision positioning capabilities to smartphones have emerged, and these are poised to revolutionize embankment measurement. Traditional drones and scanners were very expensive and complex to maintain, but smartphone-based solutions significantly lower the barrier to adoption. By leveraging equipment such as iPhone-mounted GNSS high-precision positioning devices, field workers can carry a compact device while obtaining positioning information with centimeter-level accuracy (half-inch accuracy). These mobile devices require a relatively low initial investment, making it economically feasible to deploy multiple units.
By using such mobile devices at multiple measurement points and collecting their coordinate information, an information density comparable to that of point cloud data can be achieved. Furthermore, workflows are possible in which data are sent to the cloud in real time and processing results can be checked while on site. By leveraging smartphones, on-site staff without special training can participate in surveying tasks, resulting in a significant increase in site flexibility. In addition to improved operational efficiency, worker safety is also enhanced. Traditional surveying with conventional instruments required carrying heavy equipment and working on hazardous slopes, but using mobile devices enables lightweight and safer measurements. Going forward, such mobile-based high-precision measurement systems are expected to become mainstream for embankment volume management.
Next Steps:
Explore LRTK Products & Workflows
LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.
LRTK supercharges field accuracy and efficiency
The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.