• Initial considerations to check when PVSyst indicates low energy production

• Review Point 1: Meteorological data and site conditions

• Review Point 2: Azimuth and tilt angle inputs

• Review Point 3: Balance between array capacity and PCS capacity

• Review Point 4: Near shading and racking spacing settings

• Review Point 5: Temperature losses and installation method conditions

• Review Point 6: Wiring losses, mismatch losses, and soiling losses

• Review Point 7: System control, self-consumption, and output limit conditions

• Practical diagnostic steps to isolate causes of low energy production

• Importance of correlating PVSyst results with on-site conditions

• Summary: Aligning settings and on-site information reveals the validity of the energy yield


First things to check when PVSyst shows low energy production

When PVSyst shows low energy production, the first important thing is to consider separately at which stage the production is falling. If you only look at the final annual energy yield, you cannot tell whether the cause is weather conditions, the layout, the electrical design, or the loss settings. In photovoltaic simulations, losses occur at each stage: the stage where solar irradiance reaches the module surface, the stage where the module produces DC power, the stage where the PCS converts it to AC, and the stage where it is supplied to the grid or load.


For example, even with the same installed capacity, energy production can vary greatly depending on the amount of solar irradiance in the installation area. Moreover, even within the same area, if the azimuth or tilt angles are misaligned, the irradiance incident on the module surface will change. Even when irradiance is sufficient, large shadows from racking rows or nearby buildings will reduce the system's overall output. If there are problems in the electrical configuration, generation opportunities can be lost due to the PCS's operating range or output limits. Under severe temperature conditions, output decreases because of rising module temperatures.


Thus, PVSyst results are not determined by a single setting. Just because generation is low, it is risky to immediately decide to increase installed capacity, change PCS capacity, or lower loss rates. First, check the loss diagrams and the energy balance in the report to identify which items are experiencing a significant decline.


In practice, we first line up and check annual energy production, specific yield, PR, system losses, shading losses, temperature losses, wiring losses, PCS losses, clipping losses, and so on. If the specific yield is extremely low, there may be major problems with irradiance conditions, shading, or design parameters. If PR is low, the loss assumptions for the power generation equipment may be too strict, or there may be impracticalities in the layout or electrical design. Rather than judging by annual energy production alone, distinguishing which indicator is low is the first step in identifying the cause.


Review Point 1: Meteorological Data and Installation Site Conditions

When PVSyst shows low energy production, the first things to check are the meteorological data and the site conditions. In solar power generation simulations, solar irradiance is the starting point for the inputs. No matter how appropriate the equipment design is, if the solar irradiance data entered is low, the resulting energy production will also be low.


A common problem is that meteorological data chosen because it seemed close to the installation site does not actually reflect conditions such as elevation, coastal versus inland locations, or mountainous terrain. Even nearby points can show different solar radiation due to factors like cloudiness, snowfall, fog, sea breezes, and mountain shadows. In particular, in mountainous areas, coastal zones, basins, and snow-prone regions, the outlook for power generation can vary greatly even within the same prefecture.


Also, be careful if the latitude, longitude, or elevation of the site selected in PVSyst differ from those of the actual planned site. Even if they appear close on the map, if the simulation point has worse solar irradiation conditions than the real site, the annual energy production will be underestimated. Conversely, if you use data that are more favorable than the actual site, the production will be overestimated, so you need to watch out not only for low results but also for results that are too high.


When reviewing meteorological data, first check the annual horizontal plane solar irradiance and the monthly irradiance. If months with low power generation are concentrated in a particular season, the solar irradiance data for that season may be set conservatively. For example, if power generation is extremely low in winter, separately verify whether the irradiance itself is low, whether tilt angle or shading effects are responsible, or whether conditions such as snow cover or soiling have been included.


Temperature data also affects power generation. In general, solar modules produce less output as temperature rises, so regions with higher ambient temperatures experience greater temperature losses. If summer generation falls short of expectations, stronger solar irradiance does not necessarily mean higher output; the shortfall may reflect output reduction due to high temperatures.


In practice, the important thing is not to make a judgment based on a single meteorological dataset. When necessary, compare multiple meteorological datasets to confirm how much the predicted energy output differs. When using data to assess the finances of a generation project or to determine equipment sizing, it is important to choose data that reflect the planned site’s conditions as much as possible rather than overly optimistic data. Even when you feel the energy yield in PVSyst is low, first check whether the "input solar irradiance conditions are truly reasonable"—this makes it easier to distinguish whether the issue is a design problem or simply due to the underlying meteorological conditions.


Review Point 2: Entering Azimuth and Tilt Angles

Next, what I want to check are the azimuth and tilt angle settings. Solar panels receive different amounts of solar irradiance depending on which direction they face and at what angle they are installed. If the energy yield in PVSyst is shown as low, input errors in the azimuth or tilt angle, or settings that differ from the actual design intent, can be the cause.


One common mistake with azimuth angles is misunderstanding the reference direction. Terms like south-facing, east-facing, and west-facing are used intuitively on-site, but in software they must be entered as angles. If the sign or reference is mixed up during input, what was intended as a south-facing setting can end up swung largely to the east or west, reducing energy production. This is especially important when dealing with multi-orientation roofs or east-west racking; you should carefully verify that each array’s azimuth settings are correctly reflected.


Regarding tilt angle, there are cases where the actual racking angle does not match the input value. For ground-mounted systems, consider the racking angle; for roof-mounted systems, consider the roof pitch; and for folded-plate metal roofs, consider the correction angle introduced by brackets or racking. If the tilt angle is too small, winter solar gain decreases, and it can be disadvantageous in terms of soiling and drainage. If the tilt angle is too large, it affects summer generation and the capacity per unit area of installation. Which is better depends on the region and the purpose, so if generation is low you should look at monthly as well as annual generation to determine in which season the decline occurs.


Azimuth and tilt angles are also related to shading effects. For example, increasing the tilt angle can make the height difference between the front and rear rows larger, which may increase shading between racking rows. Changing the azimuth alters morning and evening shadows and the timing of the generation peak. Therefore, azimuth and tilt angles should not be optimized in isolation but must be considered together with rack spacing, site layout, PCS capacity, power sale conditions, and self-consumption patterns.


When PVSyst shows low results, a practical approach is to first create a simple model with azimuth and tilt close to the ideal and check the baseline generation. From there, add the actual azimuth angle, tilt angle, shading conditions, and loss conditions one by one so it becomes clear which setting caused the drop in generation. If you only look at a complex model from the start, the causes become buried, so it is practical to compare the angle conditions between the baseline case and the real project case.


Review Point 3: Balancing Array Capacity and PCS Capacity

If the energy production predicted by PVSyst is low, the balance between array capacity and PCS capacity is also an important item to check. In a solar power generation system, the ratio between the DC capacity on the module side and the AC capacity on the PCS side affects the annual energy yield and peak-time output limits. In designs that use the so-called oversizing, the operating rate is increased during mornings, evenings, and cloudy periods, while during times of strong sunlight some of the power may be curtailed by the PCS output limit.


One reason generation may appear low is clipping losses caused by this output cap. If you increase module capacity but annual generation doesn’t rise as much as expected, the PCS capacity may be the bottleneck. However, the presence of clipping does not automatically mean the design is poor. With oversizing, there is an approach of accepting a certain amount of clipping while increasing overall annual generation and equipment utilization. What’s important is to determine whether the losses are within the intended range or excessive losses due to a configuration error.


You should also verify the PCS input voltage range and maximum input current. If the combination of number of strings, modules in series, and modules in parallel is inappropriate, electrical constraints can arise — for example, the open-circuit voltage at low temperatures may exceed the upper limit, or the operating voltage at high temperatures may fall below the lower limit. Check PVSyst for any warnings or inconsistencies, and review whether the array configuration falls within the PCS specification range.


Also, in configurations with multiple arrays or multiple orientations, the way they are assigned to the PCS can affect energy yield. When combining east- and west-facing arrays, peak generation times are dispersed, which can allow more efficient use of PCS capacity. Conversely, configurations where peaks coincide tend to increase clipping. If energy yield is low, it is important not to look only at the DC/AC ratio but to check the hourly output profile and the breakdown of PCS losses.


In practice, we compare cases with slight changes in array capacity, cases with changes in PCS capacity, and cases with changes in string configuration to determine which modifications affect annual energy production. If the cause of low energy production is the PCS capacity, simply increasing the number of modules may not improve it. Conversely, even if PCS capacity is increased, the effect will be limited if irradiance conditions or shading losses are the primary causes. When reviewing PVSyst results, be sure not to judge low energy production solely by system capacity; always check how much limitation is occurring during the DC-to-AC conversion process.


Review Point 4: Proximity Shading and Mount Spacing Settings

One of the major factors that can reduce energy yield in PVSyst is the near shading settings. In photovoltaic power generation, surrounding buildings, trees, utility poles, substation/transformer equipment, fences, slopes, and adjacent racking rows cast shadows that reduce the solar irradiance reaching the modules. In particular, for ground-mounted systems, shading between racking rows has a large effect on annual energy production.


When the spacing between racking rows is narrow, shadows from the front rows are more likely to fall on the rear rows during periods of low solar altitude in winter. If shading occurs over a wide area not only at dawn and dusk but also during winter mornings and afternoons, annual energy production can drop significantly. If you cram panels too closely to make efficient use of land, installed capacity may increase, but the energy generated per panel and the PR will decrease. When PVSyst shows low energy yield, instead of looking only at array capacity and thinking "we've installed this much but it's not generating," you need to check for losses due to shading.


In near-shadow settings, entering the dimensions of the 3D scene is important. If the rack height, tilt angle, inter-row spacing, module layout, ground elevation differences, and the positions and heights of surrounding obstacles are not accurate, the shadow loss results will also be inaccurate. For example, mistakes such as entering the rack height too high, entering the inter-row spacing too narrow, or entering obstacle heights larger than they actually are will cause the estimated energy production to be lower than it should be. Conversely, if obstacles are not entered, the estimated energy production will be overestimated.


Also, the impact of shading is not just a simple reduction in solar irradiance. If part of a module is shaded, electrical mismatches and output reductions at the string level may occur. In PVSyst, results change depending on the shading calculation method and how electrical effects are handled. It is important to confirm whether you are looking only at simple shading losses or also at shading impacts that take string configuration into account.


Even on rooftop installations, parapets, air-conditioning equipment, lightning protection equipment, adjacent buildings, signage, rooftop piping, and similar elements can cause shading. Because it is difficult to accurately determine heights and distances from site photos alone, we map out the relative positions of obstacles using on-site surveys, drawings, and point cloud data when possible. If simulations are run with ambiguous shadow settings, you cannot determine whether a low power output is caused by the design or by the input values.


When power generation is low, comparing a case with proximity shading temporarily disabled to a case with shading enabled makes it easier to isolate the cause. If generation is reasonable without shading but drops significantly with shading, the layout or obstacle conditions are the primary causes. In that case, consider measures such as increasing the spacing between mounts, reducing the number of rows, changing the arrangement, moving panels away from obstacles, or reviewing the string configuration.


Review Point 5: Conditions for Temperature Loss and Installation Method

Solar panels tend to generate more electricity the stronger the solar irradiance, but their output decreases as module temperature rises. Therefore, when the energy production in PVSyst is low, you should also check the temperature loss settings. In particular, if summer generation is lower than expected or the annual energy production is low relative to the irradiance, temperature conditions may be having an impact.


Temperature losses vary depending on ambient temperature, wind speed, mounting method, rear ventilation, distance to the roof, racking shape, and so on. The way module temperature rises differs between ground-mounted installations with sufficient rear ventilation and installations mounted close to the roof. If rooftop conditions are set to poor ventilation, temperature losses increase and energy output tends to be lower. Conversely, if conditions are set as having good ventilation while ventilation is actually poor, you may overestimate the energy output.


In PVSyst, you enter coefficients that describe thermal behavior and the conditions of the mounting method. What beginners often overlook is proceeding with the default settings, which may not match the actual installation method. For example, if you create a model intending a ground-mounted system but the conditions are set close to a roof‑flush configuration, temperature losses can be shown as larger. Conversely, if you use ventilation conditions similar to a ground-mounted installation for a rooftop project, the energy production may appear higher.


When checking temperature losses, look at the loss chart in the report to see how much reduction is caused by temperature. In general, temperature loss is not negligible, but if it is extremely large you need to review the configuration settings. Viewed by month, temperature losses tend to be larger in summer. If solar irradiance is sufficient in summer but power generation does not increase, check whether temperature losses and PCS output limitation are occurring simultaneously.


Also, a module's temperature coefficient affects power output. If the specifications of the module data being used are not registered correctly, the output reduction due to temperature rise will differ from the actual result. When selecting equipment data, check not only the capacity but also that the temperature coefficient, voltage, current, operating range, etc., match the equipment you will actually use.


If the cause of reduced power generation is temperature losses, design countermeasures to consider include ensuring ventilation, reviewing the clearance from the roof surface, using components appropriate to the mounting method, and selecting modules with good temperature characteristics. However, you should avoid relaxing the assumptions in PVSyst to make losses appear smaller. Simulations are intended to reproduce conditions close to reality, so it is important to configure settings that match the on-site mounting method.


Review Point 6: Wiring Losses, Mismatch Losses, and Soiling Losses

When PVSyst shows low energy production, individual loss settings may be stacking up. Wiring losses, mismatch losses, soiling losses, degradation, auxiliary consumption, and so on may each appear to be below a few percent on their own, but when added together they can have a large impact on annual energy production. If the energy production is lower than expected, check whether these loss rates are set too high and whether they reflect the actual conditions.


Wiring losses are determined by factors such as the DC wiring from the modules to the PCS, the AC wiring from the PCS to the power reception and transformation equipment, cable length, cable cross-sectional area, and current values. If the cable length is entered too long, the cross-sectional area is too small, or the settings do not match the voltage conditions, wiring losses will increase. In large-scale ground-mounted installations, wiring distances can vary greatly depending on the placement of the PCS and collection equipment, so these should be checked together with the layout design.


Mismatch losses arise from differences in output between modules, differences between strings, shading, orientation differences, uneven soiling, and similar factors. Because not all modules operate under exactly the same conditions, some degree of mismatch is unavoidable. However, mixing modules with multiple orientations on the same system or grouping together strings that receive very different shading patterns tends to increase losses. If mismatch losses are large in PVSyst, it is important to check the relationship with string configuration and shading conditions, not just the entered loss percentage.


Soiling loss is a commonly overlooked factor. Sand and dust, pollen, bird droppings, fallen leaves, salt damage, dirt after snowfall, and other contaminants affect performance differently depending on the installation environment. If you assume a large soiling loss, annual energy production will naturally decrease. If you set higher soiling losses for specific months, monthly energy production will also be affected. For example, in regions where dirt accumulates easily during dry seasons or for installations with a low tilt that rain does not wash clean, soiling losses may not be negligible.


On the other hand, setting losses lower is not always better. For submission-ready generation forecasts and business plans, if realistic losses are not reflected, the gap with actual generation can become large later. The problem is inadvertently double-counting loss rates without a sound basis. For example, if shading losses are calculated in detail using near-field shading yet an additional contingency loss for shading is added under a different item, the projected generation may end up being lower than necessary. The same applies to soiling and mismatch—verify whether the settings reflect the actual situation and whether you have been overly conservative to the point of double counting.


In practice, it is useful to list the loss items and manage them separately as initial settings, company standard values, and project-specific values. If the PVSyst result is low, creating comparison cases that reset each loss rate to the standard value one by one will reveal which losses are affecting the energy yield. Especially when multiple people are working, settings copied from previous projects can remain, so it is important to make a habit of checking the loss conditions for each project.


Review Point 7: Conditions for System Control, Self-Consumption, and Output Limitations

System control, self-consumption, and output-limiting settings are also important causes when energy production appears low. In PVSyst, models are sometimes created that consider not only a simple grid connection but also self-consumption, batteries, output control, and load patterns. In such cases, the amount of energy the modules can generate and the amount that can ultimately be used or sold differ, so it is necessary to clarify which figure you are looking at when judging that the generation is “low.”


In a self-consumption model, the temporal pattern of demand loads has a major impact on the results. In facilities with low daytime loads, the amount that can be self-consumed is limited even when solar generation is producing. How surplus power is handled depends on whether the system is configured to sell excess electricity or to restrict reverse power flow. If reverse flow is not permitted, generation that exceeds demand will be curtailed, so the reported utilized energy may appear low. This is less a case of the equipment being unable to generate than a situation where system control causes generated power to be unusable.


Be sure to check the output limit settings as well. If grid-side constraints, contractual caps, the PCS's output limit, the plant's total interconnection capacity, or similar limits have been entered, output may be curtailed even during periods when generation is possible. If you find that generation seems low, check how much loss is being caused by output limits. In particular, for oversized designs, check whether clipping due to PCS capacity and grid-side output limits overlap.


In models that include batteries, charge/discharge efficiency, capacity, available charging time, discharge control, SOC range, and other factors influence the results. The presence of a battery does not necessarily increase power generation. Batteries can help utilize surplus power and shift peaks, but charging/discharging losses occur. Also, if load patterns and control conditions are not appropriate, the battery may not be used sufficiently and the expected benefits may not be realized.


When reviewing a PVSyst report, it is important to distinguish between the DC energy generated, the AC energy after the PCS, the energy exported to the grid, the energy used by loads, and the energy discarded as losses. Even if the final amount of energy sold is low, the modules may still be generating sufficiently. In that case, the cause lies not in the generation conditions but in control or demand conditions. Conversely, if generation is low from the DC stage, prioritize checking irradiance, angle, shading, temperature, and module conditions.


Operational staff should pay attention to indicators that match their objectives. For power sales businesses, the amount of electricity sent to the grid is important. For self-consumption projects, in addition to generated electricity, check self-consumed electricity, the self-consumption rate, the reduction in purchased electricity, and surplus electricity. If the expression “low generation” remains ambiguous about which electricity metric it refers to, the countermeasures will also be misdirected.


Practical diagnostic procedures to isolate the causes of low power generation

When investigating the causes of low power generation in PVSyst, it is more efficient to decide on an order and check items systematically rather than making ad hoc changes as they occur to you. The recommended approach is to first create a simple baseline model and then add project-specific conditions one by one.


First, create a simple case using the installation site, meteorological data, standard azimuth and tilt angles, no shading, and standard loss settings. If energy production is low at this stage, it is more likely that the cause lies in the meteorological data or basic equipment settings. If the energy production of the reference model is reasonable, next reflect the actual azimuth, tilt, array capacity, and PCS capacity. If energy production decreases here, the effects of layout and electrical design become apparent.


Then add proximity shading. If power generation falls sharply when shading is added, rack spacing or obstructions are the main cause. By comparing the case without shading to the case with shading, you can quantitatively understand the impact of shading losses. Next, add wiring losses, mismatch losses, soiling losses, temperature conditions, output limits, and self-consumption conditions in sequence. If you record how much power generation and PR change at each stage, the results will also be easy to use as presentation materials.


If you change multiple items at the same time, you won't be able to tell which setting is responsible. For example, if you change the rack spacing while also altering PCS capacity and loss rates, you won't be able to explain why generation increases or decreases. In comparative simulations, the basic rule is to change as few conditions at once as possible. In practice, because time is limited, it may be difficult to examine everything in detail, but at minimum you should check the five items—meteorological data, tilt angle, shading, PCS capacity, and major losses—separately.


Also, to determine whether the power generation is low, you need a point of comparison. By comparing it with past projects in the same area, the company's standard model, rough calculations, or actual performance data, you can see whether the current result is truly low or within a reasonable range. If you judge it to be low based solely on intuition, it may in fact be a correct result reflecting solar radiation and installation conditions.


When you are not yet familiar with using PVSyst, be sure to check whether any errors or warnings have appeared. If there are problems with equipment combinations, voltage ranges, string configurations, missing inputs, or similar issues, the results can turn out in unintended ways. Ignoring warnings and proceeding with calculations may cause you to overlook the reasons for low energy production. A completed calculation is not necessarily correct; you need to cross-check the input conditions against the report contents.


The Importance of Comparing PVSyst Results with On-site Conditions

To correctly determine the causes of low energy output in PVSyst, it is essential to cross-check not only the settings in the software but also the on-site conditions.


The accuracy of solar power simulations depends on how accurately the site can be modeled. Even if drawings appear to show few shadows, in reality neighboring buildings, trees, slopes, utility poles, signs, existing equipment, and so on may cast shadows. There may also be discrepancies between assumed and actual ground level variations and the actual height of the mounting structures.


When results show particularly low power generation, it is necessary to determine whether the site truly has harsh conditions or whether the inputs are overly conservative. Check site photos, layout plans, land development drawings, survey maps, information on the heights of surrounding obstacles, roof plans, single-line wiring diagrams, and so on, and review whether they match the model in PVSyst. When dealing with the effects of nearby shading, even differences in obstacle position and height of just tens of centimeters (tens of inches) to several meters (several ft) can change how shadows appear in winter.


Local terrain and elevation differences also affect mounting-structure design. If a site is entered as flat but is actually sloped, inter-row shading and installation heights will change. Conversely, if the model is set to excessively unfavorable conditions even though the actual site has steps or terraces, the estimated power generation may be too low. To improve the reliability of simulation results, it is important to ascertain the site's three-dimensional information as accurately as possible.


In recent years there has been a growing trend to use position information and point cloud data acquired on site to more accurately verify obstacles and terrain. In solar power system design, subtle elevation differences, surrounding structures, racking positions, and constraints near boundaries that cannot be discerned from a desktop layout affect energy output. When reviewing PVSyst settings, having measurements taken on site also makes it easier to justify the validity of shading and placement conditions.


When power generation is low, the important thing is not to artificially inflate the results. If they reflect the actual conditions, low generation is still an important factor in decision-making. Conversely, if the low values are caused by input errors or overly conservative maintenance settings, the conditions need to be corrected. By accurately assessing site conditions and reflecting them in PVSyst settings, you can determine whether the low generation is a design issue or a reasonable result of the site conditions.


Summary: Aligning configuration settings with on-site information reveals the validity of the power output

When PVSyst indicates low energy production, it is important not to judge based solely on the annual generation figure, but to check, in order, the weather data, azimuth, tilt angle, array capacity, PCS capacity, nearby shading, temperature losses, wiring losses, mismatch losses, soiling losses, output limitations, and self-consumption conditions. The cause of low generation is not necessarily a single factor; often multiple settings accumulate to produce the result.


One particular pitfall for beginners is using the initial settings or settings from past projects as they are. Small mistakes—such as meteorological data not matching the planned site, using the wrong reference for the azimuth angle, rack spacing differing from reality, entering overly conservative shading conditions, double-counting loss rates, or overlooking limitations due to PCS capacity—can lead to reduced energy production. When using PVSyst, it is essential not only to follow operational procedures but also to understand the meaning of the input values.


To diagnose the causes of low power generation, creating a baseline model and adding conditions one by one for comparison is effective. By comparing no shading versus shading, standard losses versus project-specific losses, no output limits versus output limits, and different PCS capacities, it becomes easier to explain which factors are affecting power generation. This is also useful for internal sharing, customer explanations, and design reviews.


To make PVSyst results closer to reality, the accuracy of on-site information is critical. In solar PV design, panel layout, racking height, row spacing, surrounding obstacles, ground elevation differences, and boundary locations all affect energy production. If these are entered ambiguously, it becomes difficult to explain why the energy yield is low or high.


If you want to obtain accurate location and terrain information on site, using LRTK, a high-precision GNSS positioning device that attaches to an iPhone, allows you to easily record the coordinate data required for solar power plant planning and construction sites. If you keep high-precision on-site records of racking locations, boundaries, obstacles, ground elevation differences, and the location information of current-condition photos, it will also make it easier to verify shading and layout conditions in PVSyst. To improve simulation accuracy, it is important not only to review settings in the software but also to measure the site correctly and reflect those measurements in the design conditions.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

​

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page