top of page

Table of Contents

Roles to understand before using PVSyst in professional work

Use Case 1: Estimate approximate energy generation during initial assessments

Use Case 2: Compare differences in energy generation due to tilt and azimuth angles

Use Case 3: Validate array configuration and string design

Use Case 4: Quantify shading impacts and reflect them in layout planning

Use Case 5: Organize loss conditions and clarify the basis for energy production estimates

Use Case 6: Examine the balance between oversizing ratio and output limits

Use Case 7: Use for modeling that includes self-consumption and batteries

Use Case 8: Make it easier to explain design decisions by comparing multiple proposals

Use Case 9: Create materials usable for internal sharing and client presentations

Use Case 10: Improve design accuracy by combining with on-site survey data

Points to note when using PVSyst in practice

Conclusion: PVSyst is a practical tool for visualizing design decisions


Roles You Should Understand Before Using PVSyst for Professional Work

One key point to grasp when using PVSyst professionally is that PVSyst is not a tool that automatically provides the "correct answer," but a tool that performs power generation simulations based on the design conditions you input. The calculation results are very useful, but their quality is heavily dependent on the accuracy of the input conditions. If meteorological data, system capacity, module layout, racking conditions, shading settings, loss factors, electrical design parameters, etc., differ from reality, the resulting estimated energy production will also diverge from the actual performance.


Therefore, when learning how to use PVSyst, it is important not just to follow the on‑screen operations, but to understand which input fields relate to which design decisions. For example, if the annual energy production is lower than expected, you need to determine whether this is due to problems with the meteorological data, the azimuth or tilt angles, shading effects, or the settings for temperature losses and wiring losses. PVSyst provides the information needed to make that distinction.


In practice, design is not completed based solely on PVSyst results; decisions are made by combining them with on-site surveys, topographical information, equipment specifications, construction conditions, maintenance conditions, electricity consumption, contract terms, and other factors. Among these, PVSyst plays a central role in numerically organizing the relationship between energy production and losses. In particular, when you want to compare multiple design proposals or explain the basis for projected energy production to internal or external stakeholders, a major advantage is the ability to compare under consistent conditions.


In addition, PVSyst also helps compensate for differences in experience among practitioners. Judgments that experienced designers can sense intuitively—“this orientation will slightly reduce energy production,” “this shading will likely be effective in winter,” “this level of overloading will probably increase output curtailment”—can be visualized as simulation results. This makes it easier for junior staff to participate in discussions with a solid basis.


However, it is dangerous to place too much trust in PVSyst's outputs. Because the figures are displayed in detail, they can appear to be highly precise forecasts, but actual power generation is affected by weather, soiling, faults, output curtailment, maintenance status, changes in the surrounding environment, and other factors. PVSyst does not fully guarantee future actual generation; it should be treated as providing a reasonable estimate based on the design conditions.


Use Case 1: Estimating approximate power generation in a preliminary assessment

One typical use of PVSyst is to obtain a rough estimate of power generation in the early stages of a project. When evaluating a solar power installation, the first step is to roughly determine how much capacity can be installed on the site or roof and how much it would generate annually in that configuration. Because detailed equipment selection and the final wiring design are often not yet finalized at this stage, the goal is to create a model under standard conditions to assess project feasibility and the overall direction of the design approach.


During preliminary assessments, input the installation location, orientation, tilt, assumed capacity, and basic system configuration, and check the annual and monthly power generation. The important point here is not to over-specify detailed values from the outset. Since there are many uncertainties at the initial stage, it is more practical in actual work to set up a condition where multiple scenarios can be quickly compared rather than to strictly define detailed loss coefficients.


For example, even on the same site you can consider several options: a plan that slightly limits installed capacity, a plan that arranges equipment to the maximum extent, a plan that avoids the effects of shading, and a plan that prioritizes constructability. Using PVSyst, you can compare the annual energy production and loss trends for each option. In the initial study phase you may discover observations such as “increasing capacity does not increase generation as much as expected because of shading and output limits” or “simply changing the layout slightly improves winter generation.”


Estimated power generation can also be used for internal project decision-making. Because sales staff, design staff, and business planning staff can discuss while looking at the same figures, it becomes easier to determine the project's direction. Rather than using PVSyst results directly in the final proposal, it is practical to use them at the initial stage as material to judge whether "there appear to be no major issues under these conditions" and "it is worth proceeding to a detailed study."


The model created during the initial study becomes the foundation for subsequent detailed design. Update the model each time conditions are finalized, and by refining weather data, equipment configuration, loss parameters, and shading conditions, it will also serve as a record of the design review history. Rather than treating the initial model carelessly, it is important to manage the project name, conditions, and versions clearly so it can be easily reviewed later.


Use Case 2: Comparing Power Generation Differences from Tilt Angle and Azimuth Angle

PVSyst is also well suited for comparing differences in energy production caused by variations in module tilt and azimuth angles. In solar power generation, the direction panels face and the angle at which they are installed affect annual energy output and seasonal generation trends. The optimal angle varies depending on installation conditions, such as ground-mounted, roof-mounted, wall-mounted, carport-type, and agrivoltaic installations.


In practice, you cannot always install equipment perfectly south-facing or at the optimal tilt. Constraints on orientation and angle can arise from roof shape, site boundaries, mounting-height limits, wind loads, constructability, maintenance access, surrounding shading, and aesthetic/landscape considerations. In such cases, comparing multiple tilt angles and azimuths in PVSyst makes it easier to determine which option is realistic within those constraints.


For example, by comparing an option that is nearly south-facing with one rotated slightly to the east or west, you can check not only annual power generation but also generation trends in the morning and evening and seasonal differences. In self-consumption projects, an option that more closely aligns generation with demand hours can be more advantageous than the option that maximizes annual generation. Rather than simply pursuing annual generation alone, it is important to consider how electricity is used together with generation patterns.


Also, increasing the tilt angle makes it easier to receive solar radiation in winter, but it can affect inter-row shading, wind loads, racking height, and construction costs. Decreasing the tilt angle makes it easier to increase installation density, but soiling is more likely to remain and generation may not increase as much depending on the season. PVSyst allows you to compare these design trade-offs in terms of energy yield.


When evaluating azimuth and tilt angles, it's important not to look at the results just once but to line up and review multiple scenarios under different conditions. If the difference in power generation is small, prioritizing ease of construction and maintenance can lead to a better overall decision. On the other hand, even a slight difference in angle can cause a large difference in annual energy production for large-scale projects, so it's worth comparing options from the early stages.


Use Case 3: Verifying the Validity of Array Configuration and String Design

PVSyst is also useful for verifying the validity of array configurations and string designs. In photovoltaic systems, the overall efficiency and safety depend on how many modules are connected in series, how many in parallel, and which capacity of power conversion equipment they are paired with. If design conditions are inappropriate, this can lead to mismatched voltage ranges, increased output clipping, insufficient equipment capacity, and generation losses during operation.


In string design, what is particularly important is voltage variation caused by temperature conditions. In cold periods the open-circuit voltage becomes higher, and in hot periods the operating voltage becomes lower. Therefore, instead of deciding the number of modules in series solely by looking at the voltage under standard conditions, you need to consider the expected minimum and maximum temperatures and verify that the equipment’s input range is not exceeded. PVSyst allows you to evaluate the system configuration taking these conditions into account.


Also, even with the same installed capacity, the way strings are configured can change how shading effects and mismatch losses manifest. In particular, when a roof is divided into multiple surfaces or when combining surfaces with different orientations or tilts, you must carefully decide whether they can be grouped under the same input or should be treated as separate systems. Organizing the configuration in PVSyst makes it easier to spot design infeasibilities and inconsistencies.


In practice, when deciding on an array configuration we also take into account the number of modules that can be installed, equipment input specifications, cable routes, the location of the electrical panel, maintainability, and provisions for future replacements. PVSyst is primarily a tool for validating configurations from the standpoint of power-generation simulation, but its results also influence electrical design and construction planning. Even if a design is valid in simulation, it must be revised if on-site wiring would become too complex, inspections would be difficult, or per-system management would be hard.


Because array configuration and string design affect not only power generation but also safety and maintainability, it is important to cross-check the verification results from PVSyst with the design drawings and equipment specifications. PVSyst is effective when used as a checking tool to detect design inconsistencies early.


Use Case 4: Quantify Shadow Impacts and Incorporate Them into Layout Planning

One factor that is easy to overlook in solar PV system design but that has a major impact on energy production is shading. Shadows are cast at different times of day and in different seasons by nearby buildings, trees, utility poles, fences, adjacent racking, equipment, rooftop protrusions, and other objects. Because the effects of shading are difficult to judge intuitively, it is effective to quantify them using PVSyst.


In PVSyst, by configuring near shading you can reflect losses due to shading in the energy production calculations. Rather than simply determining whether shading exists or not, you can check during which periods, at what times of day, and to what extent shading occurs. Especially in winter, when the sun’s elevation is lower, obstacles that are not problematic in summer can cast long shadows. By looking not only at annual energy production but also at monthly shading losses, you can understand the impact of shading more concretely.


On ground-mounted installations, considering inter-row shading is important. If you reduce the spacing between rows to increase installed capacity, the capacity per unit area will increase, but shading losses in the mornings, evenings, and during winter may increase. Conversely, if you widen the row spacing, shading losses decrease, but the installed capacity may decrease. By comparing multiple layout options in PVSyst, you can evaluate whether to prioritize capacity or reduce shading losses and what balance is optimal.


On rooftop installations, shadows from rooftop equipment, parapets, and adjacent buildings can be problematic. Even obstacles that look small on site can, depending on the season and time of day, cast shadows on specific strings and affect power generation. Using PVSyst’s shading analysis allows you to identify which areas are prone to shading and to inform a review of module placement and stringing/system grouping.


When using shadow analysis in professional practice, understanding site conditions is indispensable. If the locations and heights of obstacles, the site's elevation differences, or the conditions of adjacent land are not accurate, the shadow simulation will deviate from reality. Therefore, when handling shadows in PVSyst, it is important to reflect field survey data and surveying data as accurately as possible.


Use Case 5: Organize loss factors to clarify the basis for electricity generation

One of the major advantages of using PVSyst in professional practice is that it allows you to organize the losses that affect energy production by category. The energy output of a solar power system is not determined solely by solar irradiance and installed capacity. Temperature losses, wiring losses, mismatch losses, soiling losses, shading losses, conversion losses, degradation, downtime, and many other factors accumulate to determine the final energy production.


In practice, simply presenting the power generation numbers is not persuasive unless you can explain why those figures were obtained. In PVSyst, you can use loss diagrams and various reports to see which losses are affecting the output and to what extent. This allows you to analyze the causes of low power generation and to identify opportunities to improve design conditions.


For example, if temperature losses are large, there may be room to review the mounting structure type, ventilation conditions, and the environment of the installation surface. If wiring losses are large, it is necessary to reconsider cable length, cross-sectional area, equipment layout, and current collection method. If mismatch losses are a concern, check whether surfaces with different orientations or tilts are grouped in the same system and whether shading is unevenly distributed. For soiling losses, you need to set a reasonable value based on the installation region, tilt angle, rainfall conditions, and maintenance plan.


When setting loss conditions, entering overly optimistic values can make the projected energy production appear higher and later fail to match actual results. Conversely, entering overly conservative values can underestimate the project's viability more than necessary. Because PVSyst divides loss items into detailed categories, it is important to enter each value while checking whether it is realistic.


Also, loss conditions vary by project. Ground-mounted and rooftop installations, snowy regions and coastal regions, steeply tilted systems and low-tilt systems, and systems with cleaning plans versus those without should not use the same values. Even if your company has standard values, you need to adjust them according to project characteristics. PVSyst is useful for visualizing the validity of these loss conditions and for organizing the design rationale.


Use Case 6: Consider the Balance Between Overload Rate and Output Limits

In solar PV systems, how to set the ratio between module capacity and converter capacity is an important consideration. Designing module capacity to be larger than converter capacity tends to increase generation in mornings, evenings, and cloudy conditions, but when peak output on clear sunny days exceeds the converter capacity the output may be limited. Using PVSyst allows you to quantitatively verify this balance.


Increasing the overloading ratio tends to raise annual energy production, but beyond a certain point losses from output limiting (clipping losses) increase, and the incremental energy yield relative to the added module capacity can become small. In other words, increasing capacity does not always lead to proportionally efficient gains in generation. By comparing multiple overloading ratios in PVSyst, you can assess the increases in energy production alongside the increases in clipping losses and consider an appropriate design point.


In this analysis, it is important to examine not only the annual power generation but also the output trends by month and by time of day. If restrictions are concentrated in specific seasons or times of day, how to assess their impact will depend on the project's objectives. The optimal decision varies depending on whether the primary goal is selling electricity, self-consumption, or dealing with grid constraints.


Also, when considering oversizing, it is necessary to verify the equipment’s input specifications and temperature conditions as well. Even if the simulated power generation looks favorable, it cannot be adopted unless it is safely feasible from an electrical-design standpoint. PVSyst results should be treated together with electrical-design verification.


In practice, several oversizing ratio scenarios are developed and compared comprehensively in terms of energy generation, curtailment losses, installed capacity, constructability, and maintainability. PVSyst plays the role of quantifying the energy generation and losses among these. In design meetings, it becomes easier to explain statements such as "this option has a larger capacity but also increases curtailment losses" and "this option generates slightly less energy but has a simpler configuration and is easier to maintain."


Use Case 7: For examining models that include self-consumption and battery storage

In recent years, there has been a growing trend not only to export generated electricity externally but also to study self-consumption solar power systems that use electricity within facilities and designs that combine them with battery storage. PVSyst can also be used to analyze these kinds of models. For self-consumption systems, it is important not only to consider the amount of generation itself but also to assess how much of the generated power can be consumed within the facility.


When evaluating self-consumption, the handling of demand data becomes a key point. Whether a facility’s electricity use is higher during the daytime or at night, whether there is a difference between weekdays and holidays, and whether seasonal variations are large will affect its compatibility with solar power generation. Even if annual generation is large, if generation is concentrated in periods of low demand, surplus may increase. Using PVSyst allows you to organize the relationship between generation and demand and check self-consumption rates and surplus trends.


When evaluating scenarios that include battery storage, charging and discharging conditions, capacity, power output, and operational strategy are important. Adding a battery does not automatically provide a benefit; if the capacity does not match demand and generation patterns, it may not be used effectively. When modeling in PVSyst, you need to review the results with awareness not only of the battery capacity but also of which time periods are used for charging and which for discharging.


When evaluating self-consumption and battery storage, it can be difficult to make decisions based solely on monthly results. It is important to examine power flows by time of day to see how much generation overlaps with demand and how effectively the battery is being used. PVSyst is an effective tool for organizing these energy flows.


However, if the demand data are of low accuracy, projections for the self-consumption rate and the battery’s effect will also be uncertain. Rather than using only a single representative day, it is desirable to prepare actual data covering as much of the year as possible and demand patterns that match the intended usage. When using PVSyst, you need to treat not only the generation-side inputs but also the demand-side conditions as factors that influence design quality.


Use Case 8: Make it easier to explain design decisions by comparing multiple options

PVSyst is particularly powerful when comparing multiple design proposals. In design practice, it is rare to decide on a single proposal from the outset; rather, one typically advances by comparing multiple options—proposals to increase capacity, avoid shading, prioritize constructability, reduce costs, or provide wider maintenance access, among others.


When comparing multiple options, it is important to keep the conditions consistent. If weather data, equipment conditions, loss settings, degradation conditions, etc. vary between options, you cannot tell whether differences in energy yield are due to design differences or to differences in input conditions. In PVSyst, you can duplicate the original model and change only some of the conditions, making comparisons easier.


For example, by creating a scenario that changes only the tilt angle, one that changes only the azimuth angle, one that changes only the row spacing, and one that changes only the overloading ratio, it becomes easier to understand how each factor affects power generation. This allows you to determine which changes are effective and which have only a small effect. Because the rationale for design decisions becomes clear, it also enhances persuasiveness in internal reviews and when explaining to the client.


Comparing multiple options also helps reduce the designer's own assumptions. From experience, a proposal that seemed good can, when actually compared, show only a small difference in energy yield, or conversely reveal a large, previously overlooked loss. By quantifying with PVSyst, you can make decisions that do not rely solely on intuition.


When summarizing comparison results, it is important not simply to rank by the size of annual energy production, but to be able to explain why the differences occurred. Whether shading losses decreased, temperature losses changed, curtailment increased, or installed capacity changed, the implications for design decisions are different. Interpreting PVSyst results and linking them to the design intent is what leads to proficient practical use.


Use Case 9: Create materials for internal sharing and client presentations

The results from PVSyst can also be used to prepare materials for internal sharing and for client briefings. In photovoltaic system design, it is necessary to communicate clearly to non-designers the expected energy production, the breakdown of losses, the design conditions, and the differences between alternative proposals. Using PVSyst reports and graphs makes it easier to organize the numerical basis.


However, simply providing the raw PVSyst outputs is not enough. Because the report contains many technical items, some readers may find it difficult to know what they should check. For internal sharing and client briefings, it is important to organize the key points to match what the audience wants to know.


For example, for sales representatives, it is easier to understand if you concisely present the annual generation, monthly generation, main loss factors, and differences between design proposals. For technical reviews, make it possible to examine in detail the equipment configuration, string conditions, shading losses, temperature losses, wiring losses, output limitations, and so on. For owners, it is important to carefully explain not only the expected generation but also what assumptions were used in the calculations and what factors can cause actual generation to vary.


When using PVSyst results in explanatory materials, it is essential to specify the input conditions. If installed capacity, azimuth, tilt, meteorological conditions, loss settings, and the scope of shading consideration are not shown, the results can be taken out of context. If conditions are changed later, it is reassuring to keep track of the project name, creation date, and the version of the study so you can tell which model’s results were used as the reference.


Also, if multiple people in your company use PVSyst, it’s a good idea to standardize the rules for model creation to some extent. If file naming, approaches to loss settings, how comparison scenarios are created, and methods for saving reports differ by person, it can easily lead to confusion when reviewing later. It’s important to treat PVSyst not only as an individual work tool but as a foundation for sharing design information within the organization.


Use Case 10: Improve Design Accuracy by Combining On-site Survey Data

To improve the accuracy of PVSyst simulations, integration with on-site survey data is essential. In the design of photovoltaic installations, there is much information that cannot be determined from drawings and maps alone. Site elevation differences, heights of obstructions, locations of surrounding buildings, layout of rooftop equipment, condition of trees, existing installations, access routes, fences, and the condition of adjacent land are all items that are difficult to accurately assess without field verification.


In PVSyst you can set shading and layout conditions, but if the underlying on-site information is inaccurate, the simulation results will also be inaccurate. In particular, in shading analysis, errors in obstacle positions and heights affect the results. By organizing obstacles and terrain conditions based on on-site position data, point clouds, photos, and survey results and then incorporating them into PVSyst, you can perform an analysis that is closer to reality.


On rooftop projects, even if the drawings appear to allow ample room, in reality equipment, inspection spaces, changes in elevation, guardrails, lightning protection, piping, and other items can limit the area available for placement. For ground-mounted projects, site slope, drainage, slopes (cut/fill), access roads, and ground conditions affect the layout plan. If you create a model in PVSyst without incorporating the results of an on-site survey, you may obtain generation estimates but end up with a proposal that cannot actually be constructed.


Also, organizing site photos and location information will be useful for internal reviews and client explanations. It becomes easier to explain why you chose not to place something at a particular position, why you treated a certain obstacle as a source of shading, and why you widened the row spacing. By combining PVSyst’s numerical results with on-site information, you can present it not merely as simulation output but as a design decision based on the field.


To link on-site surveys with PVSyst, it is important to consciously record "information that will be used later for simulation" from the survey stage. Organizing the positions, azimuths, heights, distances of obstacles, photographing directions, site boundaries, roof dimensions, and candidate installation areas will reduce rework when creating the model. If you forget to collect necessary information on site, a re-survey may be required later, so standardizing the survey items is also effective.


Points to keep in mind when using PVSyst in professional practice

When using PVSyst in practice, the most important thing to be aware of is to always keep in mind the relationship between input conditions and output results. Simulation results are the calculated outcomes based on the input assumptions. In other words, if the assumptions change, the results will change as well. If, during the design process, the system capacity, equipment, layout, shading conditions, or loss settings change, you should not use past results as-is; you need to update the model and recheck.


Also, the required accuracy and the items to be checked differ among initial study, basic design, detailed design, and final proposal. The purpose of the initial study is to confirm the general direction, but in detailed design it is important to ensure consistency with equipment specifications and electrical conditions. If you do not clarify at which stage you intend to use PVSyst, you may spend too much time performing unnecessarily detailed analyses or, conversely, omit important checks.


Managing models is also important. In PVSyst you can create multiple variations, so as the study progresses the number of files and proposals increases. If you lose track of which proposal is the latest, which proposal was presented to the client, or which conditions were changed, you will not be able to explain it later. It is important to clearly manage the project name, date, study contents, and changes, and to avoid confusing old proposals with the latest ones.


Furthermore, having standard input rules within the company is also effective. Loss coefficients, fouling conditions, temperature conditions, degradation conditions, unavailability rates, and similar items tend to vary depending on the judgment of the person in charge. You should not use the same values for every project, but without a standard approach, results can differ greatly from one person to another. Separating the concept of standard values from project-specific adjustments makes review easier.


When reviewing PVSyst results, check not only the annual energy production but also the breakdown of losses, monthly generation, output clipping, shading losses, system efficiency, and so on. Even if the annual energy production is high, be cautious if a particular loss is extremely large or if the design conditions are unrealistic. Conversely, even if the annual energy production is slightly lower, considering constructability, maintainability, shading risk, and ease of explanation may make it a more appropriate option.


Finally, PVSyst is not a substitute for on-site verification. Simulations support design decisions, but they do not automatically judge site constraints, construction conditions, future changes in shading, maintenance access routes, or safety. By using the results obtained from PVSyst in conjunction with on-site information, design drawings, and construction plans, you can move closer to a design that will withstand practical implementation.


Summary: PVSyst is a practical tool for visualizing design decisions

PVSyst is not just software for calculating the energy output of solar power systems; it is a practical tool for visualizing design decisions. In initial assessments it lets you grasp estimated generation, compare tilt and azimuth angles, verify array configurations and string designs, quantify shading and losses, and evaluate conditions for oversizing, self-consumption, and battery storage, thereby organizing the rationale behind the design.


To become proficient in PVSyst for professional work, it is important not only to memorize the operating procedures but also to understand how input conditions influence the results. Instead of looking only at the annual energy production figure, interpreting the breakdown of losses, the impact of shading, monthly trends, and differences between comparative scenarios allows for more practical decision-making. Also, when sharing internally or explaining to the client, it is important not to present PVSyst results as-is but to explain them together with the underlying assumptions and the design intent.


In projects where site conditions are particularly complex, the accuracy of PVSyst is influenced by the quality of on-site information. If the positions and heights of obstacles, elevation differences across the site, rooftop equipment, and the surrounding environment can be accurately identified, the reliability of shading analysis and layout planning increases. Conversely, if a model is created while site information remains ambiguous, a neat report may be produced but the design could end up not matching reality.


Therefore, when using PVSyst in practical design work, it is important to consider improving both the efficiency and the accuracy of on-site surveys. By utilizing LRTK, a high-precision GNSS positioning device that can be attached to an iPhone, it becomes easier to link on-site-acquired location information, photos, and point clouds to design studies. By conducting more accurate layout studies of photovoltaic systems, obstacle checks, on-site records, and pre- and post-construction inspections, you can bring PVSyst simulations closer to actual site conditions. By visualizing power generation and losses in PVSyst and accurately capturing site conditions with LRTK, it becomes easier to carry out photovoltaic system designs that are more practical and bridge desk studies with field surveys.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page