top of page

In field work using a total station, there are situations where "re-setting"—moving the instrument from its installed position to another instrument point—is unavoidable. When measuring areas where line of sight cannot be maintained, when the construction area is large, or when changing observation positions to follow obstacles or heavy machinery, re-setting occurs routinely. However, if the handling of the instrument point, back-sight point, coordinate system, height, and observation conditions shifts slightly each time re-setting occurs, it can affect the positions of measured points and as-built verification. This article organizes practical procedures to make it easier to prevent coordinate drift during total station re-setting, presented in a workflow that site personnel can easily follow.


Table of Contents

Why coordinate shifts commonly occur when relocating a total station

Step 1 Record the current instrument point and backsight before repositioning.

Step 2 Confirm the reference point and coordinate system to be used for the next instrument station

Step 3: After installation, reconfirm centering, leveling, and instrument height.

Step 4 Align direction by backsight observation and known-point checks

Step 5 Detect coordinate shift during the first measurement after reinstallation

Standardize the repositioning of total stations to prevent recurrence

Summary


Reasons Why Coordinate Shifts Are Likely to Occur When Relocating a Total Station

A total station is a surveying instrument that measures angles and distances and determines the positions of survey points based on conditions such as the instrument station and the backsight.


On site it is sometimes called "kōha," and it is used in a wide range of situations: checking construction positions, batter-board staking, as-built measurements, verifying positions near boundaries, and laying out positions for land development and exterior construction. It is a convenient instrument, but measurement results are not determined solely by the instrument's performance. Only when the preconditions — which point the instrument was set over, which direction was used as the reference, which coordinate system was used, and how elevation was handled — are all satisfied will you obtain coordinates that are practical for use on site.


A major reason coordinate shifts occur when relocating the instrument is that, although the working conditions before and after the move appear continuous, the instrument is actually reassembled. When you move the instrument to another location, the tripod position, instrument center, leveling, sighting direction, choice of back-sight point, entered instrument height and mirror height, and the order of observed survey points all change. Even if measurements at the previous instrument station were correct, if you cannot correctly connect to the same coordinate system at the next instrument station, the entire set of survey points may be translated, rotated, or displaced in elevation.


One thing to be particularly careful about is that equipment relocation on site tends to be carried out hurriedly. When circumstances such as wanting to expand the work area, not wanting to stop the movement of heavy machinery, or not wanting to keep the next crew waiting coincide, recording and verification are often put off. As a result, small mistakes can occur, such as misreading the backsight, leaving the instrument height at the previous value, using an old version of coordinate data, or mixing up local coordinates and design coordinates. These are hard to notice immediately after measurement and may only become apparent later as a sense of inconsistency when preparing reports or performing construction verification.


Also, coordinate shifts after relocating the instrument cannot always be treated as a simple single-point error. If multiple survey points observed from the new instrument station are displaced in the same direction, judgments about construction positions will be affected. If the handling of elevations is inconsistent, as-built evaluations and gradient checks will show inconsistencies. If orientation is off, it will affect straight sections, alignment/grid lines, areas near boundaries, and position checks of structures. Therefore, instrument relocation should not be regarded as a mere move but as work to reconstruct the connectivity of coordinates.


To prevent coordinate shifts, it is important to consider the checks before, during, and after reinstallation separately. Before reinstallation, ensure that the current observation conditions are reliably preserved. During reinstallation, confirm the reference and coordinate system to be used next. After reinstallation, correctly set up the total station and reconcile with backsight and known-point checks. Then detect any anomalies in the initial measurement, and if there are problems, isolate the cause on the spot. If this sequence can be performed on site every time, it will be easier to reduce coordinate shifts caused by reinstallation.


Step 1 Record the current instrument station and backsight point before repositioning

The first step to prevent coordinate shifts when re-setting the instrument is to properly record the state before moving. After packing up the total station, trying to remember “which point was used as the backsight,” “what the instrument station name was,” or “which job was being used” may not allow accurate reconstruction if the site is busy. Especially when multiple crews are working, or when there are reference points with similar names at the same site, relying on memory makes it easier to mix them up.


The items you should record before relocating the instrument are: instrument point name, coordinates of the instrument point, backsight point name, coordinates of the backsight point, observed direction, instrument height, mirror height, edition of the coordinate data used, time of operation, and work area. You do not need to record all of these in long sentences, but it is important to leave enough information so that a third party can follow the situation later. Standardizing a method that is easy to use on site—such as field notes, observation logs, the comment field of electronic data, or in-house record templates—can reduce omissions during checks.


The combination of the instrument point and the backsight point is especially important. Even for the same instrument point, the items to check for orientation change depending on which point is used as the backsight. If the backsight is mistaken, the angular direction can be off, producing inconsistencies that may appear as if the entire set of survey points has rotated. On sites with multiple backsight points, it is safer to record supplementary information to distinguish them in the field—such as the stake position, nearby structures, and the condition of markings—not just the point names. When point names are similar, do not omit parts of the name; record them using the same notation as in the coordinate list.


Instrument height and mirror height are items you should also check before re-setting the instrument. If the height input values are mistaken between before and after moving the instrument, the horizontal position may appear to match while discrepancies can show up when verifying elevations. For earthworks, paving, foundations, and exterior works—tasks where elevation directly affects construction quality—the handling of instrument height and mirror height cannot be taken lightly. Even if the previous input values remain stored in the instrument, they are not necessarily usable as-is after re-setting, so you need to record the values before re-setting and after re-setting separately.


Also, before relocating the reference points, leave a record of the results for the last-measured known points and check points, as this makes later troubleshooting easier. This makes it easier to determine whether there were no problems with the control point checks prior to the move or whether discrepancies had already appeared. If a misalignment is found after the relocation, and the pre-move state was not recorded, it becomes difficult to separate whether the cause lies in the relocation work or in the original control points or coordinate data.


Records made before relocating are not intended to slow down work. Rather, they are a short safeguard to prevent later re-measurements and rechecks of construction. Simply developing the habit of pausing once to record the current conditions before moving the total station makes it easier to reduce instability after relocation. Instead of thinking on site “I can check after moving,” adopting the mindset of “close the current position before moving” is the first step in preventing coordinate shifts.


Step 2 Confirm the reference points and coordinate system to be used at the next instrument station

Once you've recorded the measurements taken before relocation, the next thing to check is which reference points to use at the new instrument station and which coordinate system to connect to. When relocating a total station, it is more important to verify that the new location is within the correct coordinate system than merely to set up the instrument at the new site. At a site, design coordinates, local coordinates created for construction, temporary reference points, and auxiliary points added later may coexist. If you relocate without sorting these out, the measurements may look reasonable but still disagree because they reference different standards.


First, you need to confirm whether the next instrument point is a known point, a point to be determined by resection (back intersection) or similar methods, or a temporary auxiliary point to be used on site. If it is to be treated as a known point, check that its coordinates match the latest coordinate list. If you use an auxiliary point, you must record how the auxiliary point was installed and which reference it was derived from. If the status of a point remains ambiguous during work, it will be difficult later to distinguish between measurements that can be used as formal survey results and those that should be treated only as guidance for construction verification.


Next, it is necessary to perform checks to prevent mix-ups of coordinate systems. The concept of which coordinates to use varies by site: public coordinate systems, arbitrary coordinates for construction, coordinates aligned to a building’s or structure’s gridlines, coordinates provided by the client or the main contractor, and so on. Even if the coordinate list imported into the total station is correct, it is meaningless if the work and the coordinate system do not match. For example, if coordinates from design drawings and coordinates converted for construction are mixed, values can differ for the same point name. Do not judge by the point name alone; it is important to check the coordinate values, the revision, the creation date, and the intended use.


Confirm the height reference at the same time. Even if the planar coordinates match, differences in how elevation or temporary benchmarks are handled can cause discrepancies in judgments of as-built conditions and gradients. On sites that use temporary benchmarks, confirm which height is being used as the reference, how differences from the design height are treated, and whether the same height reference as the previous survey is being used. When handling heights with a total station, instrument height, prism height, the elevation of control points, and the calculation of the elevations of measured points are involved, so a single differing input or assumption can change the results.


The reference points at the relocation site must also be physically verified on site. Even if a point is correct on the coordinate list, it can be dangerous to use as-is if the on-site stake has shifted, the marking is fading, there is a similar nearby point, or the surrounding area has been excavated by construction. Check whether there are any disturbances around the point, whether the stakes or nails are securely in place, and whether recent work might have moved it. If in doubt, verify from another known point or consult the site supervisor to determine whether it can be used as a reference point.


In this procedure, the focus is on organizing site information rather than on operating the total station. If you can set up on the correct point, choose the correct coordinate system, and connect to the correct height datum, observations after changing stations will tend to be more stable. Conversely, if these checks remain ambiguous before proceeding to the next task, no matter how carefully you sight, the premises underlying the measurement results will be shifted. A station change is not simply the act of moving to a location with a better line of sight; it should be regarded as the task of transferring the coordinate reference to the next work area.


Procedure 3 Reconfirm centering, leveling, and instrument height after installation

Once the next instrument point has been established, properly set up the total station. Coordinate discrepancies when relocating the instrument can arise not only from incorrect coordinate data or mixing up backsight points, but also from poor tripod setup, inadequate centering, insufficient leveling, or misreading the instrument height. Especially when work is rushed, the tripod may appear stable when placed, yet the legs can sink or the instrument can tilt slightly due to vibration during measurements. Because a total station is a precision surveying instrument, it is important not to omit the basics of installation.


First, place the tripod on stable ground. Soft soil, crushed stone, the edge of pavement, areas near drainage covers, and ground immediately after excavation are places where the legs are likely to sink or move. If you must set up on unstable ground, make sure the legs are firmly planted and take care to prevent vibrations or contact from the surroundings during work. Where heavy machinery or vehicle traffic is nearby, vibrations can be transmitted to the tripod during measurements. Even if the total station's display appears stable, a slight movement of the tripod itself can affect the observation direction and position.


During centering, adjust the instrument so that its center is directly above the instrument point. If the centering is off, observations will be made with the instrument point itself displaced. Even a misalignment that appears small in short-distance work can affect the position of the measured point depending on direction and distance. If the mark on the instrument point is hard to see or the center of the stake is difficult to determine, do not force the work; clarify the center position before setting up. If it remains unclear where the point’s center is taken, it will be difficult to determine the cause later when checking the results.


During leveling, check that the instrument is horizontal. Insufficient leveling can affect angle observations and height measurements. Even with instruments that have automatic compensation, you should avoid exceeding the compensation range or relying too heavily on compensation. Rather than just confirming level on the display, it is reassuring to recheck the condition immediately after setup, after setting the backsight, and again after measuring for a while. Especially on soft ground in summer, at sites after rain, or at sites with vibration, the tripod’s condition can change during work.


Checking instrument height is also important. Instrument height is treated as the height from the instrument point to the instrument’s reference position, and it affects elevation calculations. When the person taking measurements changes, it can become unclear where the height was read from, what unit was entered, or whether the previous value was used as-is. Instrument height is not something you measure once and forget; verify that the entered value matches the recorded value. When reading, be careful of slack in the tape, reading at an angle, unit mix-ups, and decimal point placement errors.


Similarly, check the mirror height to match the work conditions after repositioning. In measurements that use a mirror, if the entered mirror height differs from the actual height, it will affect the height results. Even if the mirror height used in the previous job remains stored in the instrument, it does not necessarily apply to the next job. If the person in charge changed the mirror’s extension, used a different pole, or adjusted the height to suit the measurement target, always update the input value. If you continue measurements without confirming the height, it will be difficult later to determine which measurement points were taken under the correct conditions.


Checks after installation are a basic part of the work, yet they tend to be omitted on busier sites. However, many of the coordinate shifts that occur when relocating a total station can be prevented by consistently performing these basic checks. Confirm centering, leveling, instrument height, and prism height one by one, and, where necessary, keep records; this increases the reliability of subsequent backsight observations and known-point checks. Stabilizing the instrument’s condition before starting measurements provides the foundation for correctly linking coordinates after relocation.


Step 4 Align orientation using backsight observations and known-point checks

After setting up the total station, align its direction by performing a backsight observation. This procedure is extremely important for preventing coordinate shifts after relocating the instrument. By correctly sighting the backsight point and ensuring the instrument properly recognizes the relationship between the instrument station and the backsight point, the coordinates measured from the new instrument station will be tied into the site’s coordinate system. If the backsight point is chosen incorrectly, the sighting is sloppy, or the coordinate values are wrong at this stage, the points measured afterwards may all shift together.


In backsight observations, first perform a physical verification of the backsight point. Confirm that the point names on the coordinate list match the stakes or survey pins being sighted on site. At a site, multiple points can be located very close to one another. If old control points, temporary points, construction offset points, or points from other construction sections are nearby, judging only by point names or markings can lead to errors. Before sighting, check the point's position, the surrounding conditions, the record photos, and consistency with the coordinate values; if anything feels off, stop work.


When sighting a backsight, pay attention to the mirror’s position and how it is mounted. If the mirror is offset from the point center, it will affect the backsight direction as well. Make clear signals with the person holding the mirror, and confirm that they are standing correctly over the point center, that the pole is not leaning, and that the mirror height is set correctly. When distances are long or visibility is reduced by heat shimmer, rain, backlight, or obstacles, avoid forcing the task to be completed in a single sighting; it is advisable to improve the line of sight or perform check observations.


After finishing the backsight setup, measure another known point and check it whenever possible. If you align the direction using only the instrument point and the backsight point, you may not notice immediately if that pairing is wrong. By observing another known point and confirming that the coordinate and elevation differences fall within tolerances acceptable on site, you can inspect the connection condition after repositioning. Acceptable tolerances vary depending on the work, internal standards, and the client's criteria, so make your judgment according to each site's rules.


When selecting known points to check, it's effective to choose not only points near the work area but, if possible, points with different directions and distances. Directional errors that are hard to notice with only nearby points can become clear with more distant points. Also, for work involving elevation, it's reassuring to include points whose elevations are known among the checkpoints. If you verify only horizontal positions and overlook elevation discrepancies, problems may arise later when checking as-built conditions or slopes.


When a discrepancy is found in the known-point check, it is important not to continue working as is. Even if the difference seems small, proceeding without understanding the cause may force you to review measurement results over a wide area later. First, check in order for a mix-up of the instrument station, a mix-up of the backsight, a different version of the coordinate list, input errors for instrument height or mirror height, poor centering or leveling, the way the mirror is set up, and misidentification of the sighting target. By isolating causes one by one, you will more easily find what needs to be corrected.


Backsight observations and checks against known points are gatekeepers for making the coordinates after re-setting the instrument trustworthy. The more familiar someone is with operating a total station, the more likely they are to treat the backsight setup as a routine task, but special care is required when re-setting. Are you correctly sighting the backsight point, is the direction aligned, and can it be confirmed from a different point? By checking these three things each time, the reliability of the coordinates measured after re-setting is more likely to be improved.


Step 5 Detect coordinate shift in the first measurement after repositioning

After backsight observations and checks of known points are completed, you begin measuring the actual survey points. However, for the first measurement after relocating the instrument, it is important not to proceed directly to the main measurement but to perform a check to detect any coordinate shifts. Immediately after relocation, the instrument settings, coordinate system, backsight direction, and height inputs have all just been switched. If an anomaly is missed here, it will spread to all subsequently measured data.


For the initial measurement, it is effective to first measure points that have already been measured or points whose design positions are clearly defined as check points. If points measured from the previous instrument station can be re-observed from the new instrument station, compare the coordinate values. If the differences in horizontal position or elevation are larger than normal, there may be a problem somewhere in the repositioning. Performing this check in the overlapping area of the work range makes it easier to understand and also serves to link the before-and-after observation results.


When measuring check points, it is desirable not to make a judgment based on a single point. With only one point, it can be difficult to distinguish between a coincidental difference caused by how the mirror was set up or by selecting the wrong measurement point, and an overall shift caused by relocation. If possible, measure multiple points with different directions and distances, and observe how the differences appear. By seeing whether the entire setup is shifted in the same direction, whether only one point differs significantly, or whether only the elevation is shifted, it becomes easier to identify the cause.


Care must be taken in how discrepancies are viewed. Planimetric position discrepancies, directional discrepancies, and height discrepancies may each have different causes. If the entire plane is shifted uniformly, confusion of the instrument point or the coordinate system is suspected. If differences widen depending on direction, there may be a problem with the backsight direction or collimation. If only the height does not match, check the instrument height, mirror height, reference elevation, and the handling of the temporary benchmark. It is important to look not only at the magnitude of the differences but also at how they manifest.


Even if there were no problems in the initial measurement, recording the results will be useful for downstream processes. If you record the points checked after relocation, the measurement time, and the results of the discrepancy checks, it will be easier to explain when preparing reports later or when questions arise about the measurement results. On site, leaving not only the fact that it was "checked" but also which points were measured and by how much they differed helps build trust.


If a discrepancy is found in the initial measurement, stop measuring and return to the previous procedure. Recheck the backsight, instrument point, coordinate data, instrument height, prism height, centering, and leveling, and, if necessary, redo the setup from the beginning. If you try to force corrections or make repeated adjustments and judgments here, you will increase the data without identifying the cause. When relocating a total station, stopping anomalies at an early stage will ultimately reduce rework.


The initial measurement after relocating the instrument is not merely the start of work but a process to confirm that the previous coordinate system and the new observation area are correctly connected. Making this check a habit makes it easier to detect coordinate shifts early and helps prevent re-measurement and incorrect judgments about construction positions. The more rushed the measurements are, the more important it is to spend time on the first few points.


Standardize Repositioning of Total Stations to Prevent Recurrence

To reliably prevent coordinate shifts during repositioning, a system that does not rely solely on individual experience or attentiveness is necessary. Even checks that experienced operators perform instinctively can be missed when the personnel change. The busier the site, the worse the weather, the more crews working simultaneously, or the tighter the schedule, the more likely checks will be overlooked. Therefore, it is effective to organize total station repositioning work as site-specific standard procedures.


The basis of standardization is fixing the checklist items for before, during, and after instrument relocation. Before relocation, record the current instrument station, backsight point, instrument height, mirror height, version of the coordinate data, and the final check point. During relocation, confirm the next instrument station, the coordinate system to be used, the condition of reference points, and the height datum. After relocation, perform centering, leveling, instrument height, backsight, known-point checks, and verification against the initial measurements. If you carry out this sequence in the same order each time, you can reduce omissions and redundancies in the checks.


It is important to keep record forms as simple as possible. Forms that are too complex will stop being used in the field. Ideally, necessary items can be recorded quickly and the situation is understandable when reviewed later. Paper records or electronic records are both acceptable, but ensure that point name, time, operator, coordinate data, and the results of check points are retained. When using photographs, take them so that the locations of reference points and instrument points, the surrounding conditions, and any markings are visible, which makes later verification easier.


On sites where multiple crews work, it is important to standardize the management of point names and coordinate data. If the same control point is called by different names by each crew or if an old coordinate list is used, mistakes during re-establishment increase. Decide where the latest coordinate list will be managed, who will update it when changes occur, and how to identify which data are authorized for use on site. If version control of coordinate data is unclear, situations can arise where, even though the total station is operated correctly, the results do not match.


Communication among workers can also be standardized. Simply incorporating short checks into the work—announcing the instrument point, announcing the backsight, mutually verifying instrument height and mirror height, and sharing any discrepancies found at the initial check—reduces mistakes. Especially when the worker holding the mirror and the worker operating the equipment are different people, make the point name, measurement point location, mirror height, and the signal to start measurement clear. When communicating by radio or phone, the habit of repeating information back is also effective to prevent mishearing.


Deciding in advance on rules for how to respond when a deviation occurs after repositioning helps stabilize on-site decision-making. Clarify beforehand how large a difference warrants rechecking, which points should be rechecked, and who has the authority to decide to stop work. Because allowable tolerances vary depending on the task, you may not be able to set a uniform standard, but at minimum you need a rule to "not continue measuring while something feels off." If you expand the measurement range while carrying unexplained discrepancies, the scope of later corrections will grow.


The purpose of standardizing the repositioning of total stations is not to increase work as a mere formality. It is to ensure that whoever is in charge can perform checks to the same standard and can trace the cause when a problem occurs. If work records are kept, not only surveyors but also construction managers, as-built management personnel, and staff in subsequent processes can more easily understand the situation. As a result, rework and the burden of verification caused by coordinate discrepancies can be reduced.


Summary

To prevent coordinate shifts when relocating a total station, it is important to start checks before moving the instrument. Before relocation, record the current instrument point, backsight point, instrument height, prism height, and the version of the coordinate data, and at the new location confirm the reference points and coordinate system to be used. After setup, recheck centering, leveling, and instrument height, and align the orientation with backsight observations and checks of known points. Finally, during the first measurements after relocation verify known points and overlapping survey points, and detect anomalies early from the way the differences appear.


Shifts caused by repositioning are not solely due to issues with the total station itself. They occur from a combination of small on-site oversights—such as mixing up point names, using different versions of coordinate data, confusing height datums, an unstable tripod, mis-aiming the backsight, and insufficient recordkeeping. Therefore, countermeasures should not rely on a single action but be considered across the entire workflow before, during, and after repositioning.


What’s important on site is to follow the same procedure every time and keep records. Relying only on a veteran’s intuition leads to missed checks when personnel change or during busy periods. Record the instrument station and backsight, verify the coordinate system and height datum, review centering and leveling, cross-check against known points, and confirm any differences in the initial measurement. Standardizing these basics makes it easier to prevent coordinate shifts after reinstallation.


On sites using a total station, quality involves not only the speed of measurement but also keeping measurement results in a state that can be explained later. When records and cross-checks are in place, as-built verification, determination of construction positions, and handovers to subsequent work proceed smoothly. Maintaining awareness of correctly tying coordinates each time the instrument is re-set up makes it easier to improve overall surveying accuracy and work efficiency on site.


Additionally, if you want to streamline on-site position checks and record-keeping, it is effective to set up a system to digitally retain daily site inspections together with observations from an optical total station. Making the positions of survey points, photos, notes, and work history easy to manage will make post-repositioning verification and sharing with stakeholders easier. Do not limit yourself to specific product names; choose a recording method that fits your field operations and ensure that surveying results and site records can be cross-checked.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page