When they feel the power generation is low, many technicians first suspect the weather, solar irradiance, shading, dirt, or a stopped power conditioner. These factors are easy to check and are indeed common causes of reduced output. On the other hand, a frequently overlooked issue is a blown fuse. In photovoltaic systems, protective fuses may be used at the string level, in junction boxes, combiner boxes, or around the power conditioner, and if a blown fuse goes unnoticed, some circuits may not be participating in generation. As a result, the overall system may appear to be operating while daily generation is low, output lags compared with arrays of the same capacity, or it fails to reach expected values even on sunny days.


This article explains four checkpoints to avoid overlooking blown fuses for field personnel investigating the cause of "low power generation." For safety reasons, inspection of live parts and fuse replacement must be performed by qualified personnel or staff who follow facility management rules. As an on-site person, it is important to organize the flow of generation data, displays, inspection records, and visual checks to narrow down possible abnormalities before undertaking dangerous work.


Table of Contents

• Basic considerations for suspecting a blown fuse when power generation is low

• Point 1 Compare the decline in power generation on a per-string basis

• Point 2 Interpret anomalies from the combination of current and voltage values

• Point 3 Safely check the labels and appearance of junction boxes and combiner boxes

• Point 4: Investigate the causes of recurrence from replacement history and related issues

• On-site Operations to Prevent Overlooking Blown Fuses

• Summary: Assess decreases in power generation by correlating data with on-site inspections


Basic considerations for suspecting a blown fuse when power output is low

When the power output of a solar power generation system is low, the cause cannot be attributed to a single factor. On days with low solar irradiance, output naturally decreases; dirt on the panel surface, shading from weeds or buildings, snowfall, curtailment of the power conditioner (inverter) output, communication failures, or faults in measuring instruments can also make the displayed generation appear low. Therefore, when you detect a drop in generation, rather than immediately assuming a blown fuse, it is important to distinguish between the overall condition of the system and localized declines.


Characteristics of situations where a blown fuse is suspected are that the entire installation is not completely stopped, but it appears that only some circuits are not participating in power generation. For example, if there are multiple sections within the same power plant with similar azimuth, tilt, and capacity, yet only a specific combiner-box system shows low power output, or if some string currents are nearly absent even on sunny days, you should suspect a circuit-level fault. Fuses are protective components that interrupt a circuit during abnormalities such as overcurrent or short circuits; therefore, you should not treat a blown fuse merely as component degradation, but must also check why it blew.


A common oversight in the field is concluding there is no major problem simply because the power conditioner is operating. Indeed, a complete shutdown is easy to notice from alarms or displays, but if a blown fuse has disconnected only some strings, the system as a whole may continue generating power. In that case, if you look only at daily generation it is easy to judge that output is just a little low or that it might be due to the weather, and the anomaly can be left unaddressed for a long time. Especially in large-scale installations, a single blown fuse can appear to account for only a small share of total generation, so relying only on monthly comparisons or year‑over‑year comparisons can delay detection.


Also, a blown fuse should not be underestimated from a safety standpoint. If the background to a fuse blowing includes damaged wiring, loose terminals, overheating at connection points, ground faults, short circuits, incorrect wiring, or the effects of lightning or surges, simply replacing the fuse may not prevent recurrence. Furthermore, because circuits on the DC side generate voltage as long as there is sunlight, using incorrect inspection methods can create a risk of electric shock or arcing. During on-site checks, it is essential to always confirm the equipment management procedures, shutdown procedures, personal protective equipment, the ratings of measuring instruments, and the workers’ scope of qualifications, and not to make hazardous judgments unilaterally.


To correctly identify the cause of low power generation, you need to combine comparing generation data, measuring current and voltage, checking on-site displays and visual appearance, and reviewing past replacement history and any nearby incidents. By checking these items in order, it becomes easier to determine whether the reduction is an overall decline due to weather or soiling, or a circuit-level abnormality such as a blown fuse.


Point 1: Compare the decline in power generation at the string level

The first point to avoid overlooking a blown fuse is not to assess a drop in power generation only at the overall system level. A low generation state can result from the whole system falling by the same proportion, or from only some circuits dropping significantly — and the causes you should suspect differ accordingly. Cloudy skies, rain, snowfall, widespread soiling, and output curtailment tend to affect the entire system. In contrast, blown fuses, open wires, faulty terminals, shadows on specific strings, and poor connections in particular circuits are more likely to produce differences at the circuit level.


In practice, you first compare sections under the same conditions side by side. You compare strings and combiner/junction boxes with the same orientation, the same tilt, the same number of panels, the same capacity, and similar solar irradiance conditions to check whether any particular circuit is producing markedly less power. What matters here is not the simple total generation but the generation per unit of installed capacity and the ratios between circuits under the same conditions. If you directly compare sections with different capacities, differences in capacity can lead to misdiagnosing abnormalities. For example, a section with larger capacity will appear to produce more and a section with smaller capacity will appear to produce less; if you use that directly as a basis for judgment, you may miss localized faults such as blown fuses.


In systems with string monitoring or combiner-box–level monitoring, using data from clear-sky days makes differences easier to see. On cloudy days, output can fluctuate over short periods due to moving clouds, making comparisons difficult. During periods of stable irradiance on clear days, checking whether circuits under the same conditions are producing together makes it easier to narrow down suspected blown fuses. If a particular string shows no current, the output at a combiner box shows a consistent percentage drop, or the same system remains low from morning through evening, you should raise the priority of on-site inspection.


However, a difference in power generation does not immediately mean a blown fuse. Differences in shading, vegetation maintenance, uneven panel soiling, partial accumulation of snow or bird damage, or swapped measurement channels can also make only a specific circuit appear low. Therefore, it is safer to treat comparing power generation not as a task to definitively determine a blown fuse, but as a task to decide which circuits to prioritize for inspection.


When looking at how power output declines, it is important whether it dropped suddenly or gradually. In the case of a blown fuse, the output of the affected circuit may suddenly fall to zero or decrease significantly at a specific point in time. On the other hand, soiling or shadows from vegetation often worsen gradually depending on the season and maintenance conditions. Of course there are exceptions, but by tracing when the decline began in the data, it becomes easier to identify triggers for the anomaly—inspection dates, dates when lightning struck, after strong winds or heavy rain, after construction or weeding work, and so on.


It is also useful to look not only at day-to-day changes but also at variations by time of day. If output is low only in the morning or only in the afternoon, orientation or shading may be a factor. If there is almost no output throughout the day, or if output is consistently lower by a fixed proportion all day compared with other circuits under the same conditions, it becomes more likely that the circuit is not participating in power generation. A blown fuse can create this kind of “partial non-participation” in generation, so comparing by time of day helps prevent oversights.


When investigating low power generation, if you only track the total output it will be lost in the plant-wide fluctuations. To find a blown fuse, the first step is to line up circuits under the same conditions and compare them to determine whether the anomaly is localized or widespread. If you incorporate this procedure into daily inspections and monthly checks, you can narrow down the area to be checked before carrying out large-scale on-site inspections.


Point 2 Interpreting abnormalities from combinations of current and voltage readings

The second key point to avoid overlooking a blown fuse is to check current and voltage together. When power generation is low, looking only at the output figures can make it difficult to determine whether the cause is insufficient solar irradiance, a circuit fault, or a protective device trip. Check string current, open-circuit voltage, operating voltage, and the input values for each junction box, and interpret the condition of each circuit.


When a fuse blows, the current in the affected circuit may stop flowing or become almost undetectable in monitoring. How it appears depends on system configuration and measurement location, but if, under the same solar irradiance conditions, other strings are producing current while a specific string shows markedly low current, consider the possibility of a circuit interruption such as a blown fuse. Checking voltage behavior as well as low current makes it easier to distinguish between an open circuit, poor connection, shading, panel anomalies, and similar issues.


For example, if, within the same group of circuits, only one shows a current that is nearly zero, a blown fuse, a broken conductor, a loose terminal, or a faulty connector should be suspected. On the other hand, if current is present but lower than in the other circuits, partial shading, dirt, panel degradation, or increased connection resistance are also possible causes. If the voltage differs significantly, differences in the number of panels, miswiring, incorrect measurement-channel settings, or differences in circuit configuration should also be considered. In other words, it is important not to conclude “blown fuse” from current alone, but to check voltage and equipment configuration together.


One important point to note is that the values displayed on the remote monitoring screen do not necessarily present the actual on-site circuitry in a straightforward way. How an anomaly appears depends on whether the measurement point is at the junction-box level, the string level, or the power conditioner input level. If multiple strings are measured together, a blown fuse on a single string may only make the displayed total current appear slightly lower. Conversely, due to measurement settings or communication faults, values may be missing on the display even though generation is actually occurring. When generation is low, do not draw conclusions based solely on the monitoring-screen values; verify the measurement granularity and cross-check against the equipment drawings.


When measuring current or voltage on site, safety procedures are the top priority. The direct-current circuits of photovoltaic installations generate voltage as long as sunlight is present. Carelessly opening fuse holders, junction boxes, terminal blocks, or similar components can create a risk of electric shock or arcing. You must verify that the instrument ratings match the circuit voltage and current, that the measurement range is appropriate, whether insulated protective equipment is required, whether the equipment should be shut down, and whether the operator’s qualifications and company procedures are met. Even if operational staff detect an anomaly from generation data, detailed inspection of live parts or fuse replacement must always be handed over to an appropriately qualified person.


Having reference values is also important when checking current and voltage. If you do not record how much current each string and junction box produces under normal sunny conditions, it becomes difficult to judge something as “low” during an abnormal condition. Because panel capacity, orientation, tilt, circuit configuration, and seasonal conditions differ for each power plant, you cannot judge based on generic figures alone. Keeping records of normal trends during routine inspections allows you to detect localized abnormalities, such as blown fuses, more quickly.


Also, it is more effective to look at changes in current and voltage readings than at single-point measurements. If a circuit that was functioning normally until yesterday suddenly shows current near zero today, the likelihood of a blown fuse or a break in the wiring increases. If the values have been gradually decreasing over several weeks, possible causes include dirt, shading, or deterioration of the connections. Rather than relying only on the result of low power generation, tracing when and how the electrical values changed makes it easier to pinpoint the cause.


When checking a blown fuse, you need to consider "why that fuse blew" before replacing it. If you replace it without confirming whether an overcurrent occurred, whether there is a suspected short circuit or ground fault in the circuit, whether the fuse's rating and specifications match the equipment, or whether a poor connection caused heating, it may blow again. Reading current and voltage values not only helps locate the abnormal circuit but also serves as the starting point for preventing recurrence.


Point 3: Safely check the labeling and appearance of junction boxes and combiner boxes

The third point is to check the displays/indicators, internal condition, and external appearance of junction boxes and combiner boxes. When power output is low, monitoring data alone may not be enough to pinpoint the location of a fault. On site, checking the indicators and condition of junction boxes and combiner boxes can sometimes uncover clues that lead to reduced power output, such as blown fuses, tripped circuit breakers, alarm indications, malfunctioning indicator lights, discoloration at terminals, enclosure damage, or signs of water ingress.


However, the most important thing here is to stay within the range that can be checked safely. Inside junction boxes and collector boxes there are parts involving high DC voltages and large currents. Actions such as opening doors, removing covers, touching fuse holders, or placing measuring instruments on terminals must be performed in accordance with the facility manager’s procedures and within the worker’s scope of qualifications. During the site inspection stage, the basic approach is to start with items that can be checked without contact, such as external appearance, indicator windows, warning labels, abnormal noises, unusual smells, burn marks, signs of rainwater ingress, deformation of doors, and locking status.


As a clue to a blown fuse, a junction box may have an indicator that shows the fuse status. Display methods differ depending on the equipment, so before inspection you need to check drawings, manuals, and on-site labels so you can tell normal from abnormal indications. Even if there are indicator lights or alarms, they may not display correctly depending on communication or power conditions. Therefore, a normal indication does not guarantee that there is no blown fuse, nor is it appropriate to immediately conclude a blown fuse just because the indication is abnormal. Treat the indication only as one piece of evidence.


In visual inspections, pay attention to signs such as a burnt odor, discoloration of resin parts, heat-induced deformation around terminals, damage to cable jackets, evidence of insect or small animal intrusion, traces of rainwater or condensation, and accumulation of sand and dust. A blown fuse can occur on its own, but it may also be related to nearby poor connections, overheating, insulation failure, or the effects of moisture. For example, a loose terminal can increase contact resistance and lead to heating. If moisture has entered, the risk of insulation failure or ground faults increases. Replacing only the fuse without checking these surrounding conditions will leave the root cause unresolved.


When inspecting junction boxes or combiner boxes, it is also important not to mistake which box corresponds to which circuit. If the circuit that shows an anomaly in the power generation data does not match the on-site junction box number, the circuit number on the drawings, and the channel number on the monitoring screen, there is a risk of inspecting a normal box and concluding there is no abnormality. This is especially true at sites that have undergone additions or modifications, where the drawings and on-site markings may be outdated. When tracing the cause of low power generation, you need to proceed while verifying the correspondence among on-site labels, drawings, the monitoring screen, and inspection records.


If an abnormality is suspected during an on-site inspection, photographic records can also be useful. Recording the door exterior, display panel, labels, surrounding environment, and the positional relationship of the abnormality makes it easier to share the information later with electrical or maintenance personnel. However, you must avoid approaching hazardous areas or removing covers for the sake of taking photos. While maintaining a safe distance and following proper work procedures, it is important to record the location of the abnormality, the time it was discovered, the weather, and its relation to power generation data.


Also, the surrounding environment of junction boxes and combiner boxes is an inspection point that is easy to overlook. Conditions such as vegetation covering the area around the boxes, poor drainage causing retained moisture, accumulated sediment, severe direct sunlight or high-temperature environments, and cables being pulled can place long-term strain on equipment and connections. When a circuit has experienced a blown fuse, checking whether any of these environmental factors are present nearby makes it easier to consider measures to prevent recurrence.


Checking junction boxes and combiner boxes is the task of linking anomalies seen in power generation data to actual conditions in the field. Even if you find a low value on the monitoring screen, unless you check the on-site display and the unit’s exterior, it remains unclear whether it’s a blown fuse, a measurement fault, or a shadow or soiling. By carefully inspecting displays, appearance, labels, and the surrounding environment while staying within what can be safely inspected, you can reduce oversights.


Point 4: Investigate Causes of Recurrence from Replacement History and Related Issues

The fourth point is not to treat a blown fuse as a one-off component failure, but to verify it in connection with the replacement history and any nearby troubles. When a blown fuse is found as the cause of reduced power output, there is a tendency to want to restore service quickly and end the response by simply replacing the fuse. However, a fuse is a component that protects the circuit, and there may be electrical, environmental, or installation-related factors behind the failure. If the investigation of the cause is insufficient, the same circuit may suffer a recurrence and the reduction in power output may be repeated.


The first thing to check is whether fuses have blown on the same circuit in the past. Review inspection records, maintenance records, replacement records, abnormality notifications, site photos, and work reports to see whether the same junction box, the same string, or the same input circuit has experienced repeated occurrences. If multiple incidents have occurred at the same location, it may not be a merely incidental fuse blow but could indicate remaining problems with the wiring, connection points, panel, connectors, terminals, or environmental conditions. If low power generation keeps occurring and each time is resolved only by replacing parts, identification of the root cause will be delayed.


Next, correlate the timing of the blown fuse with external factors. Check whether any events that could have triggered an anomaly occurred, such as days with lightning strikes, after strong winds or heavy rain, after snowfall or thawing, after nearby construction, after mowing or weeding, or after equipment replacement. For example, if cable damage occurred after mowing, or if cables were pulled during strong winds causing stress at connection points, there may be other faults hidden in addition to the blown fuse. Linking the start date of the decline in power generation data with on-site events makes it easier to narrow down the cause.


Checking fuse specifications is also important. If a fuse is replaced without verifying that its ratings, type, and operating conditions are appropriate for the equipment, the protective function may not operate correctly. On-site personnel should avoid unilaterally selecting substitutes. There are elements to check for fuses such as voltage, current, interrupting capacity, suitability for DC applications, and the conditions at the installation location. Even if appearance and dimensions are similar, using one that is not suited to the application is dangerous. Replacement work must be determined by the appropriate personnel in accordance with equipment drawings, design conditions, and maintenance standards.


Peripheral troubles include loose terminals, overheating, damage to cable sheathing, poor connector connections, panel damage, reduced insulation resistance, moisture ingress, and the effects of insects or small animals. These not only directly cause reduced power generation but can also be underlying causes of blown fuses. For example, increased resistance at connection points can lead to heating and, over the long term, affect components and surrounding materials. Moisture and dirt can degrade the insulation condition. Ingress by small animals or damage to cables can also increase the risk of short circuits or ground faults.


When investigating the cause of recurrence, it is also effective to compare the circuit where the anomaly occurred with a normal circuit. Consider why only that circuit experienced a blown fuse within the same power plant. Check whether the cable route is different, whether it runs close to the ground, whether it is in a location where water tends to accumulate, whether it is susceptible to vegetation, whether the junction box is exposed to harsh installation conditions, and whether it has been retrofitted in the past. By identifying differences from the normal circuit, you can make candidate causes more concrete.


Also, the longer a blown fuse goes undetected, the longer the period of generation loss. When restoring service, record the date the anomaly occurred, the date it was detected, the date of replacement, and the date restoration was confirmed; knowing which period had reduced generation makes it easier to review monitoring criteria for next time. For example, this can lead to operational improvements such as notifying when a similar drop continues for several days, performing on-site verification if the generation difference per combiner box exceeds a certain threshold, and conducting circuit-by-circuit comparisons on a weekly rather than just a monthly basis.


After replacing a fuse, it is essential to verify that power output has returned to normal. Don’t rely only on the momentary recovery immediately after replacement; examine the generation curve on sunny days, compare with circuits under the same conditions, and monitor the stability of current and voltage. If power output remains low after replacement, other causes besides a blown fuse may still be present. Conversely, even if values return to normal after replacement, it is important not to skip checking related causes to prevent recurrence.


A blown fuse can appear as a "result" of decreased power generation, or as a "sign" indicating another abnormality within the equipment. By organizing replacement history and surrounding trouble records, you can make judgments that lead not only to temporary recovery but also to stable operation.


On-site operational practices to avoid overlooking blown fuses

To avoid missing a blown fuse, it is important not to wait until you feel the power generation is low and then hurriedly check, but to incorporate mechanisms into routine monitoring and inspections that make detection easier. In particular, when the installation is large or there are multiple sections, multiple junction boxes, or multiple power conditioners, partial anomalies can be difficult to see from overall power generation alone. Even if the total generation does not appear to have dropped significantly, if a particular circuit has been inactive for a long time, the accumulated losses cannot be ignored.


In field operations, first clarify the unit of comparison. Determine how far you can observe — the entire facility, per power conditioner, per combiner box, or per string — and record the normal generation trends for each. Even in facilities where the monitoring system cannot display such fine-grained units, if you retain circuit-level measurements during monthly inspections or regular maintenance, it becomes easier to confirm abnormal trends later. Without records from normal operation, when generation is low it is difficult to determine whether that is an abnormal condition or an inherent characteristic of the equipment.


Next, it is important not to make the inspection criteria ambiguous. Relying only on impressions such as "somewhat low" or "seems worse than usual" delays the discovery of blown fuses. You need practical on-site decision criteria, such as differences from circuits under the same conditions, differences in output on sunny days, trends up to the previous day, and deviations from past normal values. Because criteria differ for each piece of equipment, do not apply generic values as-is; adjust them to the characteristics of the power plant.


How inspection records are written also affects the prevention of oversights. If you discover a blown fuse, record the circuit number, junction box number, date and time of discovery, weather, status of the power generation data, display readouts, whether it was replaced, the results of the post-replacement checks, and measures taken to prevent recurrence. Simply writing "fuse replaced" makes it impossible to trace the cause or recurrence trends later. By documenting which circuit, what symptoms occurred, what checks were performed, and what state it returned to, subsequent decisions will be faster.


It is also necessary to clarify the division of responsibilities between on-site staff and electrical personnel. On-site staff often handle checking power generation data, visual inspections, record keeping, and initial reporting of abnormalities, whereas inspection of live parts, fuse replacement, insulation testing, and root-cause investigations are areas that require specialized knowledge and qualifications. If this boundary is unclear, dangerous work may be carried out unnecessarily, or necessary checks may go unrequested and be left undone. Establishing in advance the contact criteria, shutdown decision-making, urgency levels, how to take photos, and reporting destinations when power generation is low will stabilize the response.


A system that links monitoring data with on-site inspections is also important. Even if remote monitoring detects a drop in power generation, it will take time to verify if you don’t know which junction box on site to check. Standardizing drawings, field labels, and the names used on the monitoring screen, and maintaining a correspondence table of circuit numbers will speed up reaching the affected location. In particular, after equipment expansions or renovations, you should check whether labels or drawings have been left outdated.


From the perspective of preventing blown fuses, environmental management of junction boxes and combiner boxes is also essential. Regularly check door seals, drainage, vegetation contact, cable fastening, measures against ingress by insects and small animals, and the presence of corrosion or dirt. Rather than responding only after a period of low power generation occurs, you can reduce the risk of recurrence by first addressing environmental conditions that are likely to lead to abnormalities. Of course, not all blown fuses can be completely prevented, but improving the quality of inspections leads to earlier detection and safer responses.


Furthermore, when investigating decreases in power generation, weather and solar irradiance data are managed together. To avoid confusing reductions caused by a blown fuse with those caused by weather, it is effective to examine not only comparisons within the same plant but also solar irradiance trends, surrounding weather conditions, and time-of-day output variations. If solar irradiance is stable yet only a specific circuit shows low output, the likelihood of an electrical anomaly increases. Conversely, if the entire system is similarly low, the effects of weather or output curtailment should also be considered.


The purpose of on-site operations is not merely to locate blown fuses. It is to quickly narrow down the causes of low power output and accurately hand the situation over to the appropriate personnel while avoiding hazardous work. By streamlining data checks, on-site inspections, record-keeping, reporting, and recovery verification into a single workflow, responses to drops in power output become much more stable.


Summary: Assess declines in power generation by linking data with on-site inspections

A blown fuse that reduces power output is not necessarily an obvious fault that stops the entire system. If only some strings or combiner boxes are not contributing to generation, the power conditioner may continue operating and the total output can still appear to be at a reasonable level. Therefore, if you only look at the daily total generation, you may be slow to notice a blown fuse.


To avoid overlooking issues, first compare the drop in power output at the string level or combiner-box level. Compare circuits under the same conditions to determine whether only a particular system is underperforming or the entire facility is. Next, check current and voltage values together to see whether a circuit is participating in generation and whether there are any signs of tripping or disconnection. Also, safely inspect the indicators, appearance, and surrounding environment of combiner boxes and collection boxes to gather clues of visible abnormalities on site. Finally, organize fuse replacement history and nearby troubles so you can address causes and prevent recurrence rather than merely achieving a temporary restoration.


When power generation is low, you may be tempted to quickly pin it on a single cause. However, in photovoltaic power systems multiple factors can overlap, such as weather, shading, dirt, curtailment, communication faults, equipment failures, and wiring defects. A blown fuse is one of these possibilities and must be judged carefully based on both data and on-site inspection. In particular, inspecting DC circuits and replacing fuses involves danger, so it is essential to follow the defined scope of work and safety procedures and, when necessary, hand the task over to a qualified specialist.


To strengthen your ability to respond to declines in power generation, the quickest way is to routinely record normal generation trends so you have something to compare during anomalies. If you document which circuit corresponds to which junction box, verify that the names on the monitoring screens match the on-site labels, and record which circuits have experienced blown fuses in the past, you'll be able to make faster decisions when problems occur. By tracking not only the fact that generation is low but also when, where, and how the decline happened, you can reduce oversights.


If you want to continuously monitor a power plant’s condition and detect signs of anomalies early, it is important to manage daily generation data, on-site photos, and inspection records together. Partial anomalies, such as a blown fuse, are also easier to detect if there is a system for recording and comparing data. To streamline cause identification for declines in power output and on-site management of solar power plants, it is essential to retain inspection items, photos, measurements, and response histories in a form that can be reviewed later, and to establish operations that allow them to be shared among stakeholders. By having a system that links data review with safe on-site checks, you can reduce missed drops in generation and make it easier to prevent recurrence.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

​

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page