top of page

When estimating solar power generation with PVSyst, the first thing people are likely to stumble over is not detailed loss settings or report creation, but organizing the initial settings. If you proceed with unclear assumptions about the site, meteorological data, system conditions, azimuth, tilt, equipment capacity, and loss conditions, it will become difficult to explain the basis for the results later. This article explains, for practitioners researching how to use PVSyst, the seven initial-setting steps you should confirm before starting a solar power estimate.


Table of Contents

Key considerations to clarify first in PVSyst initial setup

Step 1: Define the purpose of the calculation and the assumptions

Step 2: Set the project location and meteorological data

Step 3: Determine the PV system type and basic capacity

Step 4: Set the azimuth and tilt angles

Step 5: Enter the conditions for PV modules and power conversion equipment

Step 6: Realistically organize loss factors and operational conditions

Step 7: Identify items to check on the results screen and in the report

Common mistakes in PVSyst initial setup and how to prevent them

How to proceed to apply PVSyst simulations in practice

Summary


Key concepts to clarify first in PVSyst initial setup

PVSyst is software used for design studies, capacity assessments, energy production simulations, and data analysis of solar power generation systems. In practice, it is consulted in various situations such as preliminary estimates before design, comparison of equipment capacities, energy production forecasting, feasibility studies, checking conditions before construction, and comparing actual generation after operation.


However, using PVSyst does not automatically produce reasonable estimates. The results depend on the input conditions. In particular, during the initial setup, how you configure the site, meteorological data, system capacity, azimuth, tilt, equipment configuration, and loss rates will affect the reported annual generation, monthly generation, performance ratio, and loss breakdown.


When using PVSyst for the first time, it's easy to focus only on filling in the input fields on the screen in order. However, what matters in practice is to clearly define which conditions are treated as fixed values and which are treated as assumed values. For example, even if the planned installation site is fixed, if the module capacity or tilt angle are undecided, the results will be estimates that include assumed conditions. Conversely, even if the equipment specifications are fixed, if the choice of meteorological data or the handling of shading is coarse, the explanatory power of the results will be reduced.


In the initial setup of PVSyst, it is important not only to ensure accuracy but also to make the assumptions traceable when reviewed later. The level of detail required varies depending on the purpose for which the calculation results will be used, such as internal review, customer presentations, feasibility reports, construction planning, and maintenance planning. You don't need to over-detail everything from the start, but estimates that do not record at least the basic assumptions will be difficult to use in later stages.


This article explains the initial settings for estimating solar power generation in PVSyst, divided into seven steps that are easy to verify in practice. Exact screen names and menu layouts may vary depending on the version or display settings, but the basic concepts — location, weather, capacity, tilt/angle, equipment, losses, and result review — are common.


Step 1: Decide the purpose and assumptions of the estimate

The first thing to do is not the operations in PVSyst, but to clarify the purpose of the estimate. There are various objectives for solar power estimations: when you want to grasp an approximate generation amount, when you want to compare multiple layouts, when you want to consider system capacity, when you want to see the effects of shading, when you want to create a benchmark to compare with post-construction performance, and so on.


If you begin setting things up with an unclear objective, you are likely to spend time on unnecessarily detailed items or, conversely, omit important conditions. For example, in an early feasibility assessment it is a priority to grasp the overall trend in annual power generation. Conversely, at more advanced stages of design it becomes necessary to model orientation, tilt, equipment capacity, loss conditions, and shading impacts more realistically.


When determining the purpose of an estimate, clarify whether you will look only at power output, also assess the appropriateness of the equipment configuration, or verify the breakdown of losses. PVSyst lets you set many parameters, but it is not always correct to configure every parameter in detail from the outset. It is important to distinguish, according to the study phase, between parameters that can be provisionally assumed and those that should be checked carefully.


As preconditions, clarify the installation location, installation method, expected system capacity, the type of photovoltaic modules to be used, the capacities of conversion equipment such as inverters and PCS, grid connection conditions, the commissioning date, and the number of options to be compared. If any items are still undecided, rather than proceeding with them left undefined, explicitly state them as assumed values so they can be more easily revised later.


In practice, multiple estimate files may be created for the same project. Initial proposal, revised version, for client presentation, after reflecting design changes, after adding shading conditions, etc.—the more files there are, the harder they become to manage. Therefore, it is useful to include information in the project or case name that indicates the site name, capacity, orientation, tilt, date created, and stage of review.


When learning to use PVSyst, knowing the operational procedures is important. However, if you proceed with the operations without clarifying the purpose of the calculations, it becomes difficult to judge the validity of the results. The starting point for the initial setup is to first decide "what you will use the calculation results for."


Step 2: Set the project location and meteorological data

Next, set the project location and the meteorological data. The power generation of a photovoltaic system varies depending on solar irradiance, ambient temperature, the installation site's latitude and longitude, and the surrounding environment. Therefore, when estimating solar power generation in PVSyst, the location settings must be handled carefully.


When setting the site location, choose a position close to the planned installation and verify that latitude, longitude, elevation, time zone, and other parameters are not significantly different. For large-scale solar power plants, conditions can vary even within the same municipality—mountainous areas, coastal zones, flatlands, and snow-prone regions can all present different conditions. Even for residential or small-scale installations, differences in local solar irradiance and temperature conditions affect power generation.


Meteorological data such as solar irradiance, air temperature, and wind speed are used to calculate power generation. There are several types of meteorological data available, and results can vary depending on the data source, the period covered, the temporal resolution, the interpolation method, and so on. In PVSyst, you select or create meteorological data corresponding to the site for use in simulations, but you need to verify that the chosen data closely reflects the actual conditions of the planned installation site.


What you should be particularly careful about is not treating meteorological data values as unconditionally correct. If there are nearby measured data or if the values can be compared with past power generation results, check whether the estimated values are excessively high or low. In the initial stages you may not be able to verify that level of detail, but at a minimum you should record the name of the meteorological data selected, the period covered, and the reason for selecting it.


In solar power generation, not only solar irradiance but also ambient temperature is important. In general, photovoltaic modules tend to lose output as temperature rises. Therefore, even with the same irradiance, different temperature conditions will change the resulting energy production. The impact of temperature varies with site conditions, such as cold regions, warm regions, rooftops that tend to become hot, and well-ventilated ground-mounted installations.


Also, if there are region-specific conditions such as snowfall, fog, coastal salt-damage environments, dust, or mountain shadowing, it is useful to leave them as notes during the initial setup stage because they will be helpful in later stages. Even if you cannot quantify everything from the start, organizing the conditions that are likely to affect power generation will make it easier to explain the estimation results.


In PVSyst's initial setup, once the location and meteorological data are set, the foundation of the calculation is essentially determined. Even if you fine-tune the system capacity and azimuth, if the meteorological data differ significantly from actual site conditions, the overall reliability declines. These are items you should take time to verify even at the initial stage.


Step 3: Determine the System Type and Basic Capacity of the Solar Power Generation System

After setting the site and meteorological data, next determine the system type and basic capacity of the photovoltaic installation. Here, organize the basic conditions such as whether it will be ground-mounted or roof-mounted, whether it will consist of a single orientation or multiple orientations and tilts, and whether it will be fixed or tracked.


Many initial estimates typically assume a fixed installation. For fixed installations, the tilt angle and azimuth of the solar modules are determined and the annual energy production is calculated. For rooftop installations, they are often aligned with the roof’s pitch and orientation, while for ground-mounted installations the settings are decided based on site conditions, racking conditions, row spacing, constructability, and maintainability.


When determining system capacity, it is necessary to distinguish between the DC-side photovoltaic module capacity and the AC-side power conversion equipment capacity. In solar power generation, the total capacity of the photovoltaic modules does not necessarily equal the capacity of the conversion equipment. The DC side may be designed larger than the AC side, but under certain conditions the amount of time during which the conversion equipment limits output may increase.


In PVSyst you check the overall system consistency while setting the number of PV modules, the string configuration, the number of power conversion units, input ranges, and so on. In the initial stages, precise equipment selection may not yet be complete. In such cases, it is realistic to assume an expected capacity range, perform a preliminary estimate, and later replace it with the finalized specifications.


What you should be careful about here is not to simply assume that “increasing installed capacity is always better.” Because there are constraints such as site area, shading effects, row spacing, maintenance aisles, electrical equipment, grid-connection conditions, and constructability, increasing capacity alone may not be the practical optimal solution. PVSyst estimates are useful for comparing capacities, but confirming on-site conditions is essential for design decisions.


Also, when there are multiple installation surfaces, consider whether they can be grouped as the same system or should be treated as separate surfaces. For example, when using east- and west-facing roofs simultaneously, their orientations and power-generation peak times differ. Even for south-facing ground-mounted installations, if slope or shading conditions vary within the site, treating them simply as a single surface may result in discrepancies from the actual situation.


In the initial setup, it is important to organize the approach to system configuration and capacity, and to separate cases so they can be compared later. When comparing different capacities, tilts, orientations, or equipment configurations, clearly stating the assumptions for each case makes it easier to explain which conditions caused differences in power generation.


Step 4: Set the azimuth and tilt angles

When estimating photovoltaic power generation in PVSyst, the azimuth and tilt angle settings are parameters that directly determine the amount of power generated. The azimuth indicates which direction the photovoltaic modules face, and the tilt angle indicates how much they are inclined relative to the horizontal plane.


Generally, in the Northern Hemisphere, the closer an installation's orientation is to south, the higher its annual energy production tends to be. However, at actual sites it is not always possible to install in the ideal orientation. Azimuth is constrained by factors such as roof orientation, site shape, relationships with roads and neighboring properties, racking layout, avoidance of shading, maintenance access routes, and landscape conditions.


Similarly, the tilt angle should not be determined solely by annual energy production. Increasing the tilt changes how generation is distributed seasonally and also affects wind loads, rack height, and row spacing. Reducing the tilt can make it easier to increase installation density, but it requires checking issues such as soiling, drainage, snow accumulation, reflection, and maintainability.


In PVSyst, by entering the azimuth and tilt angles you can check changes in monthly and annual energy production. In preliminary assessments, it is advisable to compare multiple angle conditions and evaluate not only energy production but also constructability and land-use efficiency. For example, even if a setting produces slightly higher annual generation, it may not be the practical optimum if mounting conditions, construction difficulty, shading effects, or maintainability worsen.


When entering the azimuth angle, pay attention to the reference direction and the sign convention. In PVSyst for the Northern Hemisphere, the basic convention is to set south to 0 degrees, treat west as positive and east as negative. Because general maps and CAD often use north as 0 degrees, entering the orientation from drawings as-is may lead to swapping east/west or north/south. After input, it is important to check the orientation and the power generation trend shown on the screen to ensure they match the intended conditions.


On roof installations, the measured roof pitch or the angle shown on the drawings is often used. For ground-mounted installations, the tilt angle is determined by the racking specifications and site conditions. On developed sites, sloping terrain, or sites with level differences, care must be taken not to confuse the slope of the terrain itself with the inclination of the module surface.


Also, in installations where multiple orientations and tilts coexist, summarizing them using only representative values will make the results coarse. For east–west roofs, folded-plate roofs, multiple buildings, or staggered ground-mounted installations, it is closer to actual conditions to separate the settings by surface. However, because initial studies may aim only to capture overall trends, adjust the level of detail in the settings according to the required accuracy.


Azimuth and tilt angle can be easily adjusted later, but because they have a significant impact on the estimated results, it is important to clearly state the basis for their input at the initial stage.


Step 5: Enter the Conditions for Photovoltaic Modules and Conversion Equipment

Next, input the conditions for the photovoltaic modules and the power conversion equipment. In PVSyst, the total system energy production is calculated from the modules' rated output, electrical characteristics, temperature characteristics, number of modules, connection configuration, and the conversion equipment's input range, rated capacity, and efficiency characteristics.


One of the first practical matters to confirm is at what stage the solar photovoltaic module’s model/type and capacity are treated as information. In the early design phase, specific models may not yet be decided. In such cases, make provisional settings based on the assumed output range and conditions close to typical specifications, then replace them later with the official specifications. If conditions that are not yet finalized are treated as if they were final specifications, misunderstandings among stakeholders are likely to arise later.


When entering the number of PV modules, check not only the total capacity but also the string configuration. Basic consistency is required: for example, confirm that the number of modules in series fits the input voltage range of the power conversion equipment, that the open-circuit voltage does not rise excessively at low temperatures, and that the operating voltage does not fall too low at high temperatures. If warnings or cautions appear in PVSyst, do not simply aim to clear them—verify why they are being displayed.


For power conversion equipment, factors such as rated capacity, number of inputs, input voltage range, maximum input current, and conversion efficiency are relevant. If the balance between DC-side capacity and AC-side capacity is inappropriate, constraints may increase during generation peaks and the utilization efficiency of the installation may decline. Because PVSyst results allow you to confirm the impacts of losses and limitations on the converter side, it is advisable to pay attention to these from the initial configuration stage.


The combination of photovoltaic modules and power conversion equipment affects not only power generation but also constructability and maintainability. If the number of strings increases, the wiring and junction box configurations change, and the number of items to manage during inspections also increases. Conversely, if units are grouped too large, a single fault can have a large impact on power generation. It is important not to make the final decision based solely on PVSyst estimates, but to verify them together with the electrical design and construction conditions.


Also, when using equipment data, confirm that the specifications you entered match the source documents being referenced. Rated output, temperature coefficient, efficiency, input range, allowable current, and so on can differ even among devices with similar names. Do not judge by name alone; it is important to check the capacity and specification values and ensure they are consistent.


In initial estimates, work can proceed even if detailed equipment selection has not been finalized. However, when preparing formal comparison documents or materials for external explanations, it is necessary to clarify the basis for the equipment conditions. As for using PVSyst, it is practical to first observe the major trends with provisional conditions, then update the equipment specifications as the design progresses and reconfirm the results.


Step 6: Realistically organize loss conditions and operational conditions

When using PVSyst's simulation results in practice, setting the loss conditions is important. In photovoltaic power generation, even when solar irradiance strikes the PV modules, not all of it can be used as electricity. Power generation is reduced by various factors such as temperature-related losses, wiring losses, soiling losses, shading losses, conversion losses, equipment variability, degradation over time, and downtime.


A common mistake in initial setup is using the loss conditions at their default values and failing to verify consistency with site conditions. Default values are convenient, but they are not necessarily suitable for every project. For example, in areas with a lot of sand and dust, locations where bird damage is expected, snowy regions, coastal sites, low-slope roofs, or equipment with limited cleaning frequency, the effects of soiling and accumulation need to be considered carefully.


Temperature losses are also important. Photovoltaic modules tend to lose output as temperature rises. In installation conditions where heat can accumulate, such as on roofs, module temperatures may be higher than for ground-mounted installations. It is desirable to consider factors such as airflow, mounting height, roofing material, and ambient temperature, and to set parameters under conditions close to those at the site.


Wiring losses depend on the wiring lengths on the DC and AC sides, cable sizes, and connection configuration. In the initial stages they may be set as approximate values, but as the design progresses they are reviewed and adjusted to match the actual wiring routes and panel layout. If wiring losses are underestimated, the calculated power generation is likely to be overestimated.


The effect of shading is an important factor to consider when estimating solar power generation. Shadows cast by surrounding buildings, trees, utility poles, rows of mounting racks, terrain, or rooftop equipment can affect generation output. In preliminary assessments shading may be treated simply, but on sites with significant shading it is better to reflect shading conditions as much as possible to approach actual performance. Because shadows tend to be longer in the morning, evening, and during winter, check not only the annual generation but also monthly declines.


Operational conditions to consider include availability (operating rate), downtime, maintenance and inspections, output control, and cleaning frequency. It is difficult to predict everything precisely, but it is important to organize the conditions that can be anticipated. For example, if there are stoppages for scheduled inspections, stoppages during equipment replacement, or restrictions due to grid interconnection conditions, reflect them in the estimates as needed.


When setting loss conditions, it becomes easier to make decisions if you compare not only optimistic values but also standard and conservative cases. In particular, in project feasibility studies, even a slight change in power generation can affect the financial outcome. Because PVSyst makes it easy to compare cases with different conditions, checking loss conditions across multiple patterns is effective.


What's important is not to make the losses appear unduly small. Set conditions that are close to reality and be able to explain why you used those values. Estimated results are the cumulative outcome of the input conditions. The more carefully you organize the loss assumptions, the greater the reliability and explanatory power of the results.


Step 7: Key Items to Check on the Results Screen and in Reports

After finishing the initial setup and running the calculation, check the results screen and the report. The important thing here is not to stop at just looking at the annual energy production. In PVSyst, in addition to energy production, you can review monthly energy production, the performance ratio, a breakdown of losses, limitations on the power conversion equipment side, temperature effects, shading effects, and an overview of the system configuration.


The first item to look at is the annual power generation. This is the central figure of the estimate, but it is dangerous to judge it in isolation. Even with the same annual generation, the assessment changes if monthly variability, the breakdown of losses, or generation efficiency relative to installed capacity differ. Whether the annual generation is higher or lower than expected, confirm why that result occurred.


Next, check the monthly power generation. In solar power generation, because solar irradiance and temperature change with the seasons, generation also fluctuates month by month. If output drops significantly in winter, solar irradiance conditions, snow cover, shading, or tilt angle may be influencing it. If output struggles to grow in summer, losses from rising temperatures or limitations of the power conversion equipment may be involved.


The performance ratio is also an important metric. The performance ratio is used as an indicator of how efficiently an installation is generating electricity relative to solar irradiance conditions. However, you cannot judge the quality of an installation by the performance ratio alone. Even with a high performance ratio, total electricity generation is limited if the system capacity is small, and a low performance ratio may be reasonable when considering installation conditions or shading. When evaluating results, consider energy production, system capacity, and loss conditions together.


Also check the loss diagram and the loss breakdown. Here you can see at which stages and to what extent losses occur. Depending on whether temperature losses are large, wiring losses are large, shading effects are significant, or limitations in the conversion equipment are prominent, the improvement measures will differ. Rather than simply accepting the results, interpreting the causes of loss is what gives PVSyst its value.


Restrictions on the conversion-equipment side must not be overlooked. If the DC-side capacity is set large, constraints can occur on the AC side during generation peaks. If these constraints are small they may be acceptable in the design, but if they are too large it may be necessary to review the equipment capacity and the string configuration.


When preparing a report, organize it so that the input conditions are clear. If the site, meteorological data, system capacity, azimuth, tilt, module conditions, converter specifications, loss assumptions, and so on cannot be confirmed, it becomes difficult to evaluate from generation output alone. For materials shared internally and externally, it is important to present the assumptions together with the estimated results, not just the calculation outputs.


Also, be careful not to confuse initial estimates with final estimates. Early-stage PVSyst results are merely analyses that include provisional assumptions. As the design progresses and equipment specifications, layout, shading conditions, and wiring conditions are finalized, the estimates must be updated. Sharing reports that still reflect old assumptions can lead to incorrect decisions.


When verifying results, it's important not only to look at the magnitude of the figures but also to examine how the input conditions relate to the outcomes. PVSyst can be used not merely as a tool for producing energy output figures, but as a tool to verify the design conditions of photovoltaic systems.


Common Mistakes During Initial PVSyst Setup and How to Prevent Them

One common mistake when using PVSyst is failing to record the justification for input values. Even if you remember immediately after running a calculation, when you look back weeks or months later you may not recall why you chose that meteorological data, why you set that loss rate, or which drawings you used to determine the angle. In practice, being able to explain your choices afterward is more important than the results themselves.


The next most common issue is confusing provisional assumptions with confirmed conditions. In the early stages of design, it is not uncommon for equipment capacity, device specifications, layouts, wiring routes, shading conditions, and so on to be undecided. Performing estimates based on provisional assumptions is not a problem in itself, but if you do not explicitly state that they are provisional, stakeholders may treat them as finalized results.


Be careful about input mistakes for azimuth and tilt angles. They can be set to unintended orientations because of factors such as the east–west sign convention, the reference used for angles, roof pitch conversions, and differences between the direction shown on drawings and the actual azimuth. After inputting values, check the on-screen orientation and the power generation trend to confirm they match the on-site impression.


Mistakes in selecting meteorological data can also significantly affect the results. Using data from locations far from the installation site, or data that does not reflect regional characteristics, can cause estimated power generation to deviate from actual output. Even if there is no perfectly matching data, documenting the reasons for your selection will provide a basis for later review.


Neglecting loss conditions can also lead to failure. If you proceed with the initial values unchanged, the effects of soiling, temperature, wiring, shading, downtime, and so on may not be adequately reflected. In particular, when using power generation figures for external reporting or business decisions, you need to carefully verify the validity of the loss conditions.


Also, there are cases where anomalies go unnoticed if you look only at the numbers in the report. If annual energy production is extremely high, monthly production variations are unnatural, the performance ratio deviates significantly from expectations, constraints from power conversion equipment are large, or shading losses differ from assumptions, review the input conditions. PVSyst’s results are produced by calculation, but it is the user who must judge whether those results are reasonable.


To avoid mistakes, it's effective to decide the order of checks in advance. If you verify in the order of location, meteorological data, capacity, azimuth, tilt, equipment configuration, loss conditions, and results, you can reduce omissions. When multiple people are checking, separating the person who entered the data and the reviewer makes it easier to find errors caused by assumptions.


PVSyst is a versatile software, but if the quality of the initial settings is poor, no matter how detailed the reports are, their reliability will not improve. Carefully verifying the basic items leads to estimates that can be used in practical work.


How to Use PVSyst Estimates in Practical Work

Once you have completed the initial setup of PVSyst, you also need to consider how to apply its results in practical work. Estimates for solar power generation are used not only to calculate generation output but also as a basis for design decisions, business feasibility studies, construction planning, maintenance planning, and explanations to customers.


A practical way to proceed in practice is to first create an initial estimate using approximate conditions, and then update the estimate each time the design conditions are finalized. Rather than aiming for perfect inputs from the outset, it is more efficient to increase accuracy according to the stage of review. In the initial phase, focus on capturing the major trends—site, capacity, azimuth, and tilt—and in the detailed design phase, refine the equipment configuration, shading, wiring, and loss conditions.


When comparing multiple proposals, it is important to organize the conditions you change one by one. If you change capacity, azimuth, tilt, and loss assumptions all at once, it becomes difficult to tell which factor is responsible for differences in power generation. For example, if you want to compare tilt angles, perform calculations with the other conditions made as similar as possible. Likewise, when comparing equipment capacities, aligning the azimuth and meteorological data makes evaluation easier.


When sharing internally, include a document summarizing the assumptions as well as the results so that everyone has a common understanding. If you share only the power generation figures, the results may take on a life of their own even when the underlying assumptions change. In particular, estimates that include provisional assumptions, rough or preliminary estimates, and estimates prepared for external submission should have their handling clearly specified.


When explaining to customers, it's important not to simply list technical terms, but to clearly show which conditions affect power output. For example, organizing and communicating factors such as solar irradiance, installation angle, shading, temperature, soiling, equipment conversion, and wiring losses will deepen understanding of the power generation figures.


Also, the PVSyst estimates become more valuable when verified together with on-site surveys and design drawings. Site elevation differences, nearby obstructions, sources of shading, maintenance access routes, cable routing, and racking layout can be overlooked if you rely only on software settings. It is important to iterate between the simulation and the actual site conditions to improve accuracy.


After the start of operations, it can also be used to compare with actual power generation. If the actual values are significantly lower than the estimated values, check for differences in weather, downtime, soiling, shading, equipment malfunction, output curtailment, measurement conditions, and so on. However, a simple comparison between a single year's actual performance and a long-term average estimate can lead to misunderstandings. When comparing estimates and actuals, it is necessary to align the period, weather, downtime history, and measurement methods.


To use PVSyst effectively in professional practice, you need not only software operation skills but also an understanding of the design, construction, and operation of solar power systems. By carefully performing the initial setup and being able to explain the background behind the results, estimates become more than mere numbers—they become materials suitable for decision-making.


Summary

When estimating solar power generation with PVSyst, the quality of the initial settings greatly affects the reliability of the results. First, determine the purpose of the estimate, set the location and meteorological data, and organize the system configuration and capacity. Then enter the azimuth and tilt angles, the conditions of the photovoltaic modules and conversion equipment, the loss conditions, and the operational conditions, and verify the validity on the results screen and in the reports.


What's important is not filling in the fields on the screen, but being able to explain the relationship between the assumptions you entered and the simulation results. Rather than just whether the energy production is high or low, interpreting why that result occurred, which losses are significant, and which conditions can be changed to improve it will increase the value of using PVSyst.


At the initial stage, it is important not to force uncertain conditions to be treated as definitive but to record them as assumed values. As the design progresses, equipment specifications, layout, shading conditions, wiring conditions, and loss conditions should be updated, and the calculation results should be reviewed. Judging power generation based on outdated conditions can lead to discrepancies in design and business decisions.


Practitioners learning how to use PVSyst can make the estimation workflow more stable by first mastering seven steps. Organizing inputs in the order of site, meteorological data, capacity, tilt, equipment, losses, and results verification helps reduce missing inputs and inadequate checks.


Estimating the power output of a solar PV system is relevant to design, construction, maintenance, and business feasibility. To evaluate conditions closer to the actual site, it is important not to rely solely on PVSyst simulation results but to verify them against on-site surveys, survey data, design drawings, construction conditions, and operational performance. Updating estimates while retaining the rationale for the initial settings leads to power output assessments that are easier to explain to stakeholders.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page