Explaining the Construction Sequence of the Reverse Construction Method | 7 Checks to Avoid Failures in Underground Works

By LRTK Team (Lefixea Inc.)

All-in-One Surveying Device: LRTK Phone
text explanation of LRTK Phone

In urban underground works, conditions such as small site area, nearby buildings in close proximity, the need to shorten construction schedules, and the desire to minimize traffic restrictions often coincide, making conventional bottom-up methods difficult to apply. One representative method adopted in such sites is the reverse construction method. Its major characteristic is that it facilitates parallel progression of above-ground structural work and underground excavation, allowing construction to proceed while minimizing impacts on the surrounding environment.


However, the reverse construction method is not simply a matter of reversing the order of tasks. There are many items that must be resolved in advance—accuracy of primary columns, shoring and waterproofing plans, handling of slab openings, routes for excavated soil removal, and interfaces with underground structures—and any weakness in preparation directly leads to reduced quality or schedule delays. Proceeding with local optimizations without understanding the construction sequence often leads to defects that are difficult to undo in practice.


For practitioners researching reverse construction, what matters more than knowing the concept is grasping concretely what to check in what order and where failure factors may hide. Design, construction, temporary works, surveying, quality control, and neighbor relations must operate as an integrated whole, so risks do not become evident from the schedule alone. To organize knowledge usable on site, it is essential to capture both the construction flow and the checkpoints together.


Here, based on the basic ideas of the reverse construction method, we organize from a practical perspective the construction sequence and seven checkpoints to avoid failures in underground works. We summarize a flow that covers points often overlooked at the design stage, key management points during construction, and attention items that directly affect final quality.


Table of Contents

• Grasp the basics of the reverse construction method first

• Site conditions where the reverse construction method is likely to be adopted

• Construction step 1: Preliminary planning and organization of construction conditions

• Construction step 2: Pre-construction of retaining walls, piles, and primary columns

• Construction step 3: Pre-construction of above-ground structure and 1st-floor slab

• Construction step 4: Start of underground excavation using slab openings

• Construction step 5: Construction of underground floors and progression of the reverse sequence

• Construction step 6: Construction of base slab, pressure slab, and foundations

• Construction step 7: Closing openings, finishing, and final adjustments

• Seven checkpoints to avoid failures in underground works

• Typical troubles in the reverse construction method

• Management approach to smoothly advance the reverse construction method

• Summary


Grasp the basics of the reverse construction method first

The reverse construction method is an approach in which part of the above-ground structural frame and the 1st-floor slab are constructed first, and that slab is used like shoring while excavating downward and sequentially constructing the underground structure from top to bottom. In the general bottom-up method, excavation proceeds to the lowest level before erecting foundations and the underground structure; with the reverse method, the schedule is organized combining above-ground and underground works.


The method’s greatest characteristic is that it can more easily achieve both control of retaining wall displacements and shortening of the construction period. Each floor slab acts to support the shoring, so it is easier to reduce the amount of strutting and to start above-ground work earlier. In narrow sites or busy urban areas, it is also advantageous because it tends to limit protrusion of temporary materials and large strut arrangements.


However, judging solely by advantages leads to failure. In the reverse method, work space underground is limited, movement of heavy equipment and material delivery are constrained, and more aspects become invisible during construction. Although it may appear to offer greater flexibility than conventional methods, in reality the dependencies between stages are strong, and a single delay or precision defect can propagate across the whole project. That is why understanding procedures and managing checkpoints is essential.


Site conditions where the reverse construction method is likely to be adopted

The reverse construction method is effective especially on projects with strong demands for shortened schedules. Because above-ground structure work can start earlier, it helps ease situations where underground work would otherwise be the bottleneck of the overall schedule. It tends to be considered for station-front redevelopment, office facilities, commercial facilities, and multi-unit residential projects where handover timing is strict.


Next, it is adopted on sites where limiting displacement impacts to surrounding areas is important. Where adjacent buildings are close, the site runs along roads, many buried objects exist, or groundwater conditions are severe, management of retaining behavior becomes important. Since each floor slab in the reverse method functions as a horizontal shoring element, it can be compatible with approaches that aim to suppress retaining wall displacement.


Furthermore, it can be advantageous on sites with constrained plot conditions. When many struts are required, excavation and removal routes become complicated, but the reverse method can sometimes enable earlier arrangement of above-ground utilization conditions. Of course, it is not suitable for every narrow site. A comprehensive judgment is required, considering the number of underground floors, excavation depth, groundwater level, structural planning, heavy equipment plan, and cost balance.


In practice, it is important not to decide whether the reverse method is suitable solely based on excavation depth. Only by including surrounding conditions, temporary works conditions, above-ground schedule, structural type, specifications of the underground exterior wall, and waterproofing plan does appropriateness become clear. Understanding the construction sequence makes it easier to determine early whether this method is truly effective for a given project.


Construction step 1: Preliminary planning and organization of construction conditions

The success of the reverse construction method is largely determined by the accuracy of pre-construction planning. The first thing to do is to organize structural planning and temporary works planning not separately but as a single integrated construction plan. Line up the underground structure, retaining, primary columns, piles, equipment penetrations, transport-in/out plan, spoil disposal, neighbor responses, and surveying plan on a single process line and identify where interferences may occur.


Particularly important at this stage is organizing the positions and precision requirements of the primary columns. In reverse construction, columns constructed early become the reference for subsequent stages. Slight centerline offsets or tilts affect not only the above-ground structure but also connections to the underground structure, beam interfaces, and equipment routes. Assuming that these can be accommodated later is dangerous; tolerance limits and correction methods must be decided at the outset.


It is also indispensable to concretize excavation and removal methods. Whether excavators will be brought in through slab openings, whether small machines will be primarily used, whether soil will be lifted by crane, and how removal times will be restricted all change the required opening dimensions and temporary works plans. Minimizing openings too much worsens safety and constructability, whereas making openings too large affects slab stiffness and the schedule. In practice, it is important to consider heavy equipment routes and material flow separately and verify that there will be no obstruction during peak periods.


Additionally, the groundwater control policy must be finalized at this stage. Whether to rely on the retaining wall’s waterproofing performance, to combine well pumping, or how to manage inflow until base slab placement—if these remain vague, unexpected measures may be required after excavation. Because the reverse method is difficult to backtrack, interpreting ground investigation results and confirming consistency with the waterproofing plan are extremely important.


Construction step 2: Pre-construction of retaining walls, piles, and primary columns

After preliminary planning, proceed to pre-construction of retaining walls, piles, and primary columns. Retaining walls may use continuous underground walls or soil-cement column walls, selected according to soil conditions and surrounding environment. In reverse construction, the construction accuracy at this stage has a long-lasting impact on subsequent stages, so it should not be treated lightly as mere temporary works.


Primary columns are the core members in the reverse construction method. They are often installed within pre-driven piles or cast-in-place piles and support the later above-ground and underground frames while serving as construction references. It is important to manage not only plan position but also vertical accuracy, top-level elevation, connection detail, and adhesion conditions with concrete. Even if no problem is apparent during installation, misalignments may become evident when beams and slabs on the underground floors are connected.


The frequency of surveying control is also important during pre-construction of retaining walls and primary columns. It is not a one-time task; confirmations must be made at each construction step and the soundness of reference points continuously managed. In urban sites, vibrations from heavy equipment and traffic, temperature changes, and contact with temporary materials can undermine the reliability of control points. Because subsequent stages in reverse construction build upon these references, not only initial accuracy but sustained accuracy are required.


At this stage, waterproofing checks should also be advanced simultaneously. Joints in wall bodies, interfaces with pre-driven piles, planned equipment penetrations, and corner areas are prone to leakage risk. Progress should not be based on the premise that repairs can be carried out later; instead, anticipate likely leak-prone areas and incorporate auxiliary methods and repair procedures into the construction plan.


Construction step 3: Pre-construction of above-ground structure and 1st-floor slab

Once retaining walls and primary columns are in place, proceed with pre-construction of the above-ground structure and the 1st-floor slab. In the reverse construction method, this 1st-floor slab and upper slabs serve a shoring function for the retaining system, so they carry greater structural significance than usual floor construction. They should be treated not merely as floors but as members that play an intermediate role between temporary works and permanent works supporting the underground construction.


For the 1st-floor slab, setting the opening positions and dimensions is important. Anticipate future excavation, material and spoil removal, formwork delivery, rebar hoisting, and concrete placement, and secure necessary openings. If openings are insufficient, construction will be delayed; if overly large, slab stiffness will be insufficient and reinforcement needs will increase, worsening both schedule and costs. In practice, consider heavy equipment and material flow separately and verify that there will be no problems at the peak of operations.


Control of slab placement timing and strength development is also critical. In reverse construction, a precondition for entering the next excavation stage is that the floor slab has adequate functional performance, so simple curing age management is insufficient. Confirm when the slab will provide the required shoring performance, the state of reinforcement around openings, and the relationship with temporary loads before moving to the next stage.


When executing above-ground and underground works in parallel, adjust so that priorities of tasks above and below do not conflict. If crane plans, material storage, worker routes, and working hours overlap, the schedule advantage of reverse construction diminishes. Although stages may be parallel in the schedule, operationally they are often difficult to parallelize, so it is important not only to set the construction sequence but also to organize the operational sequence.


Construction step 4: Start of underground excavation using slab openings

After pre-constructing the 1st-floor slab, begin underground excavation using slab openings. This marks the start of the phase characteristic of the reverse method but is also a stage where construction management difficulty increases. Because above-ground areas are relatively closed while underground work proceeds, visibility, ventilation, lighting, heavy equipment routes, and safety monitoring conditions differ significantly from the conventional method.


Excavation proceeds sequentially from the opening positions, installing temporary working platforms and access routes as needed. It is essential to monitor excavation progress and retaining behavior together. Although floor slabs act as shoring, localized displacements can occur due to earth pressure, water pressure, eccentric loads, or deviations in excavation sequence. Prioritizing ease of excavation and disturbing the planned sequence can shift the stress state from what was designed and cause unexpected displacements or cracking.


Efficiency of spoil removal is also important. Reverse construction limits removal from underground, so if spoil quantities increase beyond assumptions, the schedule is quickly affected. Removal efficiency often varies with soil type and moisture content, so desk planning alone is insufficient. On site, confirm actual early-stage removal volumes and required times, and flexibly adjust vehicle numbers or time windows if necessary.


Ventilation and safety management cannot be neglected in this stage. The more enclosed the underground space becomes, the more problematic exhaust gases, dust, poor visibility, noise, and heat buildup are. In reverse construction, attention tends to focus on structural considerations, but poor working environments are a common cause of work stoppages. Rather than adding safety equipment later, establish adequate ventilation, lighting, and monitoring systems at the start of excavation.


Construction step 5: Construction of underground floors and progression of the reverse sequence

Once underground excavation reaches a certain depth, begin sequential construction from top to bottom of beams, slabs, and walls for each underground floor. This is the core stage of the reverse construction method and the part where understanding the construction sequence is most necessary. Each floor’s structure is not just a finished element but also a shoring component supporting the subsequent work, so construction quality and schedule management must be achieved simultaneously.


A key point in structural construction is the interface between the earlier-installed primary columns and newly formed beams and slabs. In practice, detailing around columns, rebar anchorage, formwork assembly, compaction during placement, and treatment of construction joints require care. In narrow underground spaces there are urges to change details for constructability, but makeshift changes can easily lead to reduced quality or leaks and should be avoided.


At the underground perimeter, management approaches differ depending on whether the retaining wall is used as the permanent outer wall or whether a separate inner structural wall is constructed. Whether walls are treated integrally or as a double-wall arrangement affects waterproofing, insulation, equipment space, and maintainability. Decisions should consider not only construction convenience but also post-completion performance.


Also important during underground floor work is the timing of reducing and closing openings. From an efficiency perspective, one may want to leave openings longer, but regarding structural integrity, waterproofing, seismic performance, and temporary works planning, there are times when early closure is preferable. Mistakes in balancing these factors will create difficulties in subsequent stages. In reverse construction, one must proceed while considering how openings will affect future stages, not optimizing only a single stage.


Construction step 6: Construction of base slab, pressure slab, and foundations

When excavation reaches the lowest level, proceed to construction of the base slab, pressure slab, and foundations. This stage greatly influences the quality and durability of the underground works. In reverse construction, the lowest-level work is carried out while the upper structure is already in place, meaning construction space is limited and material delivery and placement conditions are constrained. Therefore, placement planning and waterproofing planning are more important here than in conventional methods.


The most critical concerns in base slab work are inflow of groundwater and construction joints. The base slab resists groundwater pressure and is a critical element; even minor leakage paths can lead to post-completion problems. Disturbance of the excavation bottom, deficiencies in blinding concrete, poor installation of waterproofing materials, and inadequate handling of inflows during placement can combine to cause prolonged post-construction repairs. It is important not to omit steps in the areas that are hard to see during construction.


Furthermore, detailing at interfaces—between base slab and primary columns, base slab and perimeter walls, and foundation beams—tends to be complex, and rebar congestion and formwork difficulties often appear. If ad hoc rebar changes or on-site decisions continue here, cover deficiencies or poor filling are likely. Even if details work on drawings, confirm pre-construction whether assembly is possible in the actual construction space, whether compaction is feasible, and whether placement sequences are realistic.


After base slab placement, transition from temporary to permanent load transfer with the upper structure should be organized. If this transition is ambiguous, it becomes unclear which elements function as permanent parts when and which temporary supports can be removed. In reverse construction, the boundary between temporary and permanent is less visible, so understanding the flow of forces according to the sequence is important.


Construction step 7: Closing openings, finishing, and final adjustments

When the lowest-level structure is completed and the main underground structures are near completion, proceed to close remaining openings, finish, coordinate with equipment, and perform final adjustments. Although the schedule appears to be in its final stages, this period is where defects commonly become apparent in practice. This is because dimensional tolerances and weak points in waterproofing that were tolerated temporarily tend to surface as the structure approaches its final form.


When closing openings, integration with existing structures is important. Proper handling of rebar connections, treatment of concrete joint surfaces, placement of waterproofing materials, and prevention of inadequate compaction during placement must be carried out carefully to avoid later cracking or leakage. Areas around openings are particularly vulnerable because heavy equipment and materials concentrate there during construction, and temporary members are repeatedly fixed and removed, causing more local damage than expected.


Coordination with equipment installation also needs checking. With reverse construction, structural work often takes priority and routing of equipment piping and ducts tends to be deferred, making clearances in ceilings and adjacent to walls tight. Even slight misalignment of equipment openings or sleeve positions can greatly expand the scope of remedial work, so surveying confirmation and drawing verification become increasingly important toward the end.


Finally, do not forget final checks after releasing the retaining system and confirming surrounding settlement. Even if no major problems occurred during construction, additional displacements may manifest due to changes in load conditions or groundwater. Although reverse construction focuses attention on stability during construction, continuing measurements and confirmations until just before handover is key to ensuring quality.


Seven checkpoints to avoid failures in underground works

After understanding the construction sequence of the reverse method, there are seven checkpoints practitioners should particularly cover. First is construction accuracy of primary columns and pre-driven piles. If these are misaligned, all subsequent connections to the structure will be problematic. In addition to initial surveying, confirmations should be repeated at installation, after concrete placement, and before structural connections at each stage.


Second is verification of retaining and waterproofing performance. Even if design is valid, construction joints, corners, and penetrations remain risky. It is too late to respond after groundwater emerges; anticipate likely leak points in advance and secure repair routes. Because it is difficult to access work spaces later in reverse construction, proactive management is required.


Third is planning of slab openings. Bigger is not always better, nor is smaller always safer. Determine required dimensions considering excavation, spoil removal, lifting, evacuation, and safety monitoring. Because required conditions change as the schedule progresses, avoid fixed thinking and treat openings as phase-managed assets.


Fourth is management of the working environment underground. Poor ventilation, lighting, dust control, exhaust handling, noise, and heat conditions degrade both quality and safety. Even if reverse construction is structurally rational, neglecting the work environment makes site operations untenable. Equipment and safety systems should be integrated into the early-stage construction plan, not added later.


Fifth is quality control of construction joints and interfaces. Areas prone to defects include opening closures, base slab connections, column surrounds, and wall interfaces. In confined spaces, execution often leans on contractor experience, so standardized check items, thorough photographic records, and witnessed confirmations help prevent rework.


Sixth is consistency of excavation sequence and load conditions. In practice, ease of work tempts teams to change excavation sequence. However, reverse construction is premised on which slabs support at which time, so sequence changes alter stress states. Always check that design and construction assumptions remain valid and do not proceed unilaterally.


Seventh is continuous surveying and as-built confirmation. Because the reverse method advances in unseen areas, as-built understanding tends to lag. Small deviations can cause major rework later, so continuously verify column centers, floor levels, opening positions, equipment sleeves, and wall locations to enable early detection of abnormalities. To keep to schedule, do not treat surveying control as an expendable effort.


Typical troubles in the reverse construction method

One common trouble with reverse construction is detailing issues at primary columns and beam connections. Errors that appeared acceptable at the start of construction can become unmanageable as underground floors increase, leading to forced rebar arrangements, formwork rearrangements, and equipment clashes. Causes often include not just surveying mistakes but misreading of initial accuracy, overlooking temporary displacement, and insufficient information sharing.


Another frequent issue is water leakage. There are multiple points at risk of leakage in reverse construction—retaining wall joints, construction joints, penetrations, and base slab interfaces. Because underground spaces are narrow, repairs are difficult and the cost of addressing leaks increases in later stages. Leakage may look like a local problem, but it tends to cascade into finishing, equipment, and handover inspections, so early containment is important.


Delays in spoil removal and lifting of materials are also common causes of schedule slips. While desk planning may show the advantages of parallel work, on-site productivity can decline due to constraints at the removal entrance, crane usage times, and interference with above-ground operations. Always revisit whether scheduled parallels match actual site operations.


From a safety perspective, poor visibility and cramped working spaces raise the risk of contact accidents. When underground excavation, structural work, and material delivery overlap, workers and machines tend to be close and temporary access routes become complex. Reverse construction does not automatically make a site safer; a safety plan tailored to the unique enclosed-space risks is necessary.


Management approach to smoothly advance the reverse construction method

Successful sites using the reverse construction method do not treat schedule control as mere date adjustments. Structural, temporary works, surveying, safety, transport-in/out, and equipment teams manage by sharing the same construction cross-section. In other words, rather than one person seeing the whole, everyone is kept in a state where they can see the whole—that is the major difference.


Particularly effective is clarifying the conditions for switching between stages. Rather than simply “after floor concrete is placed, proceed,” visualize the conditions for starting the next stage—required strength, opening reinforcement, displacement confirmation, secured removal routes, and ventilation equipment operation—to reduce inconsistent decisions. Reverse construction is a chain of preparations, so unclear start and completion conditions quickly lead to confusion.


On-site, the quality of records pays off more in later stages. Organizing survey results, as-built photos, conditions during placements, inflow locations, and repair histories makes cause tracking easier when problems arise later. Because reverse construction hides many parts, leaving thorough records while things are still visible is extremely important.


From the viewpoint of improving efficiency, a major theme is how to reduce the burden of layout and as-built confirmation. Underground works are demanding and even small checks consume time and effort. Therefore, rather than cutting inspections, build systems that allow confirmations to be done quickly and accurately. If mismanaged, the cost of rework due to insufficient checking outweighs any saved effort.


Summary

The reverse construction method’s sequence can be organized as preliminary planning; pre-construction of retaining and primary columns; pre-construction of the 1st-floor slab; underground excavation using slab openings; construction of underground floors; base slab construction; and closing openings and final adjustments. However, in practice, understanding the order alone is not enough. Because each stage becomes a condition for the next, construction accuracy, waterproofing, opening planning, work environment, joint quality, excavation sequence, and surveying management must be considered in an integrated manner.


To avoid failures in underground works, inspect the seven checkpoints at each stage and prevent problems from being carried into subsequent stages. When properly executed, the reverse construction method can effectively shorten schedules and reduce surrounding impacts, but poor preparation turns it into a method prone to large rework. That is why understanding the construction sequence and precise site operations determine outcomes.


In recent years, even for such complex underground works, greater emphasis has been placed on measures to more efficiently perform layout, as-built confirmation, and progress tracking. For operational efficiency, building systems that reduce surveying and measurement effort while ensuring necessary accuracy is indispensable. One option worth considering is using high-precision positioning devices that attach to smartphones, such as LRTK, to enable rapid on-site confirmation tasks. On sites with many stage interferences like reverse construction, making checks faster, more accurate, and easier to share leads to both quality and productivity improvements.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

​

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page