GCP Placement and RTK: How to Use Each? 7 Tips to Avoid Mistakes on Site


In field work that handles coordinates, it’s not uncommon to be unsure whether to install GCPs thoroughly or to proceed mainly with RTK. Especially in tasks that require both speed and accuracy—such as photogrammetry, point cloud acquisition, as-built verification, and current condition assessment—making the wrong decision can lead to situations where the shooting or measurement itself is finished, but later positional or elevation offsets are discovered and require rework. Network RTK can streamline centimeter-level positioning (half-inch-level positioning) on site by using correction information, but under the public surveying approach, verification using control points and check points remains important, and in some uses RTK alone can be insufficient. In other words, rather than thinking in a binary way of GCP or RTK, it’s important to sort out where to fix, where to verify, and where to save effort, and use each method accordingly.


Contents

• Why distinguishing between GCP placement and RTK usage is important

• First clarify the different roles of GCP and RTK

• Tip 1: Decide the method by working backwards from required accuracy

• Tip 2: Treat control points and check points separately

• Tip 3: Don't be complacent with RTK fixed solutions alone

• Tip 4: Balance points visible from the air and points easy to measure on the ground

• Tip 5: Verify elevation separately

• Tip 6: Anticipate obstructions and reflective environments

• Tip 7: Establish procedures that make re-measurement easy from the start

• Summary


Why distinguishing between GCP placement and RTK usage is important

Distinguishing between GCP placement and RTK usage is important because, although they may look similar, they actually serve different functions. RTK is an excellent means to obtain coordinates quickly on site. It is well suited to workflows like walking the site to collect points, immediately confirming coordinates of shooting positions or reference points, and performing additional measurements on the same day where needed. On the other hand, GCPs play the role of reliably tying the entire deliverable to a known coordinate system, suppressing overall distortion or bias, and validating the final deliverable. In short, RTK is a tool to speed up observations, and GCPs are the foundation to ensure the consistency of the deliverables. If this difference is left vague while working on site, you can end up with extremes: coordinates are being collected yet the overall deliverable lacks sufficient reliability, or you install many GCPs that in practice were not necessary.


What requires particular attention in practice is that the term “GCP” is used too broadly in on-site conversations. In reality, points used to stabilize analysis and points used to inspect the quality of deliverables have different roles. Furthermore, whether horizontal position alone is sufficient or elevation must also be matched strictly changes the necessary measures. When dealing with broad deliverables such as photogrammetry or point cloud generation, even if local points match, a slight warp or tilt of the whole can become an issue in downstream processes. That is why the choice between GCP and RTK is not a matter of equipment preference but a decision made to define the scope of responsibility for the deliverables in advance.


First clarify the different roles of GCP and RTK

To use GCP and RTK effectively, you first need to verbalize their roles. GCPs are the benchmarks that explicitly provide ground points with correct coordinates and reflect those in shooting, processing, point cloud alignment, orthophoto creation, and so on. Especially when treating a wide area as a single deliverable, it is not enough that only some parts match; perimeter and internal restraints are needed to stabilize the whole. Even in standard public surveying thinking, perimeter arrangements, internal placements, and inspections using check points are emphasized, and it is not simply a matter of increasing the number—where they are placed is important.


One form of RTK is a system that obtains high-precision coordinates in real time at the rover while receiving correction information. If a network-based scheme that eliminates the need to place a base station on site is used, setup can be simplified and field measurement speed can be increased. For that reason, it is very effective for additional detailed observations, acquiring coordinates of aerial targets, immediate checks right after imaging, and rapid response to locations that require re-survey. However, even if coordinates obtained by RTK appear acceptable at that moment, that alone does not guarantee the quality of the entire analysis. What is truly needed in field work is not a single good positioning result but consistency that can be explained as a complete deliverable. For this reason, thinking of GCPs as the mechanism that supports deliverables and RTK as the mechanism that runs field operations makes decision-making easier.


Tip 1 Decide the method by working backwards from the required accuracy

The first tip is not to decide in the field by feel how many GCPs to place or how much to trust RTK. What must be decided first is how much accuracy is required in the final deliverable. For example, if the work is mainly for general situational awareness, progress checks, or relative comparisons, it is easier to base the approach on RTK and reduce GCPs. Conversely, for tasks such as drafting, as-built evaluation, cross-section comparisons, or overlaying with past-year results—where even small discrepancies can become problematic later—it is safer not to omit too many GCPs or validation points. Designing based solely on the notion that “RTK can save effort these days” while leaving required accuracy vague may make fieldwork easier but will leave you struggling to justify the deliverables.


Particular attention should be paid to requirements in the vertical direction. Horizontal positions seldom look obviously wrong and can feel correct on site, whereas vertical information tends to reveal differences in later processes such as cross-sections, volume calculations, drainage planning, and settlement comparisons. Demonstrations have also confirmed cases where RTK-derived positioning alone produced vertical residuals that exceeded allowable limits, and results were shown to change depending on the number of reference points and imaging conditions. In other words, judging that things are fine because the horizontal positions are roughly correct is risky. A safer order for deciding the on-site method is: first determine the intended use, next the allowable error, and then decide the ratio of GCPs to RTK.


Tip 2 Treat reference points and validation points separately

The second tip is not to treat all GCPs as a single category. In practice, you need to distinguish between points used to provide coordinates for processing and adjustment and points intentionally excluded from processing to check deliverable deviations. The former are, in effect, points used to create the deliverable, and the latter are points used to inspect it. If you confuse these two, the analysis may look clean at first glance but you won’t be able to judge whether it is truly valid externally. Even in public surveying practice, the placement and management of validation points are treated independently, and evaluations are not closed using only reference points. A common field mistake is to feel reassured after spending time installing GCPs and then fail to secure enough points for validation. This leaves you unable to tell whether the results are “a product of fitting” or “actually correct.”


In photogrammetry, the standard approach is to place points that control the outer perimeter, points that stabilize the interior, and points that check accuracy at locations distant from the reference points. It is not necessary to apply this rigidly to every private-sector job, but the concept itself is very useful. Even if you cluster only the points used in processing, you can easily miss edge distortion or local tilts. Conversely, if validation points are appropriately dispersed, you can see where weaknesses occur. If you want to reduce GCP installation, first cut indiscriminate additions; do not cut the mechanisms for verification. Adopting this mindset makes it easier to incorporate RTK-based labor savings without degrading quality.


Tip 3 Don’t be reassured by RTK fixed solutions alone

The third tip is not to mistake the RTK display state for a guarantee of deliverable quality. When RTK appears stable on site, there is a tendency to think, “Conditions are good today, so we can reduce GCPs.” However, what matters with RTK is not only that the coordinates at that moment are a fixed solution. Communication conditions, satellite geometry, sky visibility, nearby reflections, observation time, and antenna orientation all affect the results, and these can manifest as different types of bias in post-processing or overall analysis. Especially for large-extent deliverables, individual points may look acceptable while the whole product is slightly twisted or tilted.


Verifications by the Geospatial Information Authority of Japan have shown cases in GNSS-based analyses where vertical differences exceeded limits under certain conditions, and a tendency for validation point differences to decrease as the number of reference points increased. What this indicates is that RTK is extremely useful but not always sufficient on its own. The correct approach in the field is to use RTK to obtain coordinates efficiently while verifying with another mechanism that the results are truly correct. In other words, RTK can be placed at the center of labor-saving measures, but it must not be made the last line of quality assurance. A fixed solution is a start condition, not a guarantee of the finish.


Tip 4 Balance points that are visible from the air with points that are easy to measure on the ground

The fourth tip is not to select GCP candidate points by coordinates alone. Points used for photogrammetry, orthophoto production, and point cloud reconstruction must be not only easy to measure on the ground but also clearly identifiable from the air. Public surveying practice requires that aerial targets be designed so they can be identified on enlarged photos, taking into account shape, dimensions, color, and contrast with the surroundings. In other words, a good point must satisfy both the ground crew’s ease of measurement and the image-processing side’s recognizability. In the field these two perspectives are often split: a point may be placed where it is easy to measure but is hard to see in images, or it may be highly visible but located where access is poor and re-measurement is difficult.


Also, even if aerial markers are not clear, it may be possible to substitute structures that have a clear tonal contrast with their surroundings. This can reduce the labor of installation work, but not everything can be substituted. Under conditions such as rounded corners, cast shadows, an appearance that changes over time, or blending into surrounding patterns, they become unstable as recognition points. What really works on site is for the surveyor and the photographer to look at the same drawings in advance and narrow down points that simultaneously satisfy "this point is easy to obtain coordinates for," "this point is easy to pick up in the images," and "this point is easy to re-measure." Rather than needlessly increasing the number of GCPs, improving the quality of visibility and measurability makes even a smaller number of points more likely to be stable.


Tip 5 Treat height as a separate category

The fifth tip is: do not treat height as an afterthought to the planar measurements. Discussions about GCP placement and RTK tend to converge on the question of “do the coordinates match,” but in practice failures manifest differently in the horizontal plane and in height. Planar offsets are relatively easy to notice from visual inconsistencies or by overlaying existing maps, whereas height offsets may only become apparent when you section the deliverables, calculate volumes, or compare with previous results. Moreover, validation of RTK usage has shown that residuals in the vertical direction tend to be problematic. Therefore, sites where you want to reduce GCPs should treat height as a separate management item.


Although handling elevations based on GNSS has been improving in recent years, official materials organize GNSS-based elevation determination as a technique to be used selectively according to purpose, and note that traditional methods can be advantageous over short distances. In other words, having RTK does not mean elevation checks can be uniformly simplified. In the field, it is effective to first identify places where elevation has a large impact—areas with significant relief changes, around structures, slope shoulders, locations related to drainage, and places with reference comparisons—and place the necessary checkpoints there. Proceeding with RTK as the main method for horizontal positioning while treating elevation more thoroughly as a supplementary matter is a perfectly valid division of labor. The important thing is not to assume that horizontal and vertical measurements are equally straightforward.


Tip 6 Anticipate obstructions and reflective environments

The sixth tip is to read the site conditions “before measuring.” Although RTK is highly convenient, satellite signals are affected by buildings, trees, slopes, metal surfaces, water surfaces, vehicles, temporary structures, and so on. Materials from the Geospatial Information Authority of Japan also show that, especially in urban areas, narrow passages, or environments with nearby structures, signal blockages and reflections causing multipath are likely and positioning accuracy tends to degrade. What matters here is not to enter the site and then worry about reception conditions, but to pre-classify areas into “places where RTK will be reliable” and “places where GCPs should be retained.” In wide open areas with a clear sky view, RTK can be the primary method; at forest edges, alongside buildings, in narrow sections, and around metal objects it is safer to leave verification points and auxiliary points.


If this assessment is too optimistic, even if the overall policy of relying on RTK is fine, quality can be undermined by just a few local trouble spots. What makes it worse is that those local offsets reduce the reliability of the entire deliverable. Therefore, in practice, risk-based differentiation by location is more important than uniform rules applied across the board. In open areas, proceed briskly with RTK and supplement only the difficult sections with GCPs or checkpoints. Thinking of the site in zones like this avoids adding more GCPs than necessary and maximizes RTK efficiency. It’s easier to understand if you consider selective use not as a matter of equipment choice but as a design that adjusts the intensity of quality assurance to the risk of each location.


Tip 7: Establish procedures from the start that make re-measurement easy

The seventh tip is to set up operations from the start that make rechecking easy, rather than aiming for perfection on the first attempt. In the field, after reviewing images you may notice things like “this point is hard to read,” “this edge lacks enough reference points,” or “I want to re-record only this elevation.” If the workflow requires large-scale reinstallation or re-surveying each time, an approach intended to save labor can become inefficient.


Decide from the outset on things like naming conventions for points that are easy to locate on revisit, how to preserve record photos, standardization of the measurement point ledger, whether markers should be left in place, and the priority order for re-survey candidates; doing so reduces potential losses if something goes wrong. The fact that precision control sheets and inspection procedures are prepared separately also reflects the need to manage data in a form that can be verified later, rather than simply finishing the measurements and stopping there.


Especially when introducing RTK, because the speed of taking points in the field increases, if operational rules are ambiguous the quality of records cannot keep up. Which points are for analysis, and which are for validation? Which points are mandatory, and which are backups? Under what conditions should you switch to re-surveying? Deciding these rules before going to the field prevents decisions from depending on individuals. The sites that are truly strong in the use of GCP and RTK are not those with special equipment, but those where operations — including re-surveys and accountability — are well organized. As a result, such sites are more resilient even if they reduce GCPs, and can consistently realize the benefits of RTK.


Summary

To avoid failure when choosing between GCP placement and RTK use, it is important not to focus on which to adopt but to clearly define what each will be responsible for. RTK increases on-site speed and makes additional observations and immediate checks easier. GCPs support the overall consistency of deliverables and create a state in which the required accuracy can be explained. Work backwards from the required accuracy, separate control points and check points, do not overtrust fixed solutions, balance visibility and ease of measurement, treat elevation separately, anticipate the effects of obstructions, and establish operations that make re-measurement easy. If you keep these seven points in mind, you can avoid both making GCPs excessively numerous and inefficient and relying so heavily on RTK that quality becomes unstable.


What is truly needed in the field is not theoretically high precision but an operational approach that can reproduce the required accuracy without undue effort. The goal is not to reduce GCPs to zero, nor is it to adopt RTK for its own sake. The biggest practical difference comes from being able to design where to streamline and where to be thorough within limited personnel and time. If you want to keep tasks such as coordinate checks on site, linking photos and point clouds, additional observations, and record sharing as lightweight as possible, it is also effective to consider means that make it easy to integrate RTK operations into everyday workflows—such as LRTK, an iPhone-mounted GNSS high-precision positioning device. Keep GCPs where they should remain, and reliably eliminate the tasks that can be saved by RTK. That pragmatic allocation of roles is the approach best suited to future fieldwork.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

​

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.