Six Construction Process Management Items to Review During Rainy Weather for Solar Power Plant Construction
By LRTK Team (Lefixea Inc.)
Table of Contents
• Why rain preparedness is important in solar power plant construction
• Problems that occur when schedule management for rainy conditions is lax
• Item 1 Clarify criteria for stopping work and decision-making authority
• Item 2 Reevaluate on-site traffic flow and heavy equipment operations with rain as the assumption
• Item 3 Reorder installation sequence for piles, racking, and foundations
• Item 4 Strictly control quality conditions for wiring, connections, and electrical work
• Item 5 Design material storage and delivery plans to include rain countermeasures
• Item 6 Standardize restart procedures and checklist items after rain
• How to embed rain-specific schedule management practices on site
• To further stabilize solar power plant construction
Why rain preparedness is important in solar power plant construction
Because solar power plant construction is outdoor work, it is strongly affected by the weather. In particular, rain broadly impacts not only work efficiency but also safety, quality, scheduling, recordkeeping, and handover, so it should not be judged simply by whether work stops. If you proceed with the schedule using the same assumptions as for sunny conditions, the moment it rains the entire site workflow can easily be disrupted. For that reason, in solar power plant construction it is important to treat rain not as an exceptional event but as a site condition to be incorporated from the outset.
A solar power plant site may at first glance look like the same work repeated. Driving piles into the prepared ground, erecting the racking, installing modules, wiring, mounting junction boxes and PCS, and moving on to testing — that sequence is repeated in a similar way for each section. However, in reality, the ground conditions, drainage patterns, heavy-equipment access routes, the condition of temporary roads, and the interfaces with existing structures differ from section to section. When rain is added, the way the site is affected also varies from place to place within the same site. Work may proceed without problem in one section, while in another section the continuation of work can become hazardous due to mud or puddles.
Also, because construction of photovoltaic power plants is a long, interconnected process, a rainy day does not necessarily affect only that day’s work. For example, if temporary access routes are left in poor condition because of rain, it will affect heavy equipment mobilization and material transport the next day. If pile installation is forced ahead in the rain, the racking installation is more likely to show alignment or height discrepancies. If wiring work is pushed through in wet weather, it may appear to be finished at the time but later tests and insulation checks can reveal inconsistencies. In other words, rain response should not be a day-by-day decision but considered as process management that looks ahead to subsequent work stages.
Furthermore, schedule management during rainy weather is directly linked to safety management. Problems such as slippery ground, heavy equipment sinking more easily, reduced visibility, materials getting wet and becoming harder to handle, and changes to working conditions for electrical work affect safety before they affect work speed. On-site, a small shortcut or overreach can lead to major accidents or equipment damage. Therefore, when considering schedule management in rainy weather, the perspective needed is not on securing progress but on how to reorganize the entire schedule while protecting safety and quality.
Readers searching for "solar power plant construction" are likely not just looking to finish the work, but have practical concerns about keeping progress stable. In particular, during rainy weather differences in site management translate directly into differences in the schedule. Between sites where preparations collapse every time it rains and sites that can minimize damage and move on to the next phase even when it rains, the overall burden at the end differs greatly. In this article, we organize the process-management review points that create those differences into six categories.
Problems Caused by Lax Schedule Management During Rainy Weather
If schedule management during rainy weather is lax, the first thing to appear is a simple delay. However, what is truly serious on site is not the delay itself but that, in trying to recover lost time, forced construction and insufficient checks tend to occur. It is not uncommon for sites to feel that overall progress has slowed even though work stopped for only half a day due to rain. This is because rework and rechecks that occur after the rain burden the schedule more than the time directly taken by the rain.
One common problem is the deterioration of temporary roads and circulation routes within work sections. When it rains, mud, puddles, surface runoff, and instability near slope shoulders are likely to occur. If these are left as they are and work resumes the next day, movement of heavy machinery slows, the order of material deliveries is disrupted, and progress differences between sections widen. What may appear to be a minor issue on site, disruption of circulation routes affects the entire process. It is very common for schedule delays to be caused not by the construction work itself but by poor site circulation.
The next common issue is the impact on the accuracy of piles and support structures. During rainy weather, the ground tends to soften, changing the conditions for pile installation and around foundations. If construction is forced under these conditions, progress may be made on site, but later inconsistencies in alignment and elevation can be discovered, requiring adjustments during support construction and module installation. Prioritizing temporary progress in rainy weather can result in losing much more time in later stages.
Furthermore, wiring and electrical work are prone to problems affecting both quality and safety. If work on cables, terminals, connection points, and around equipment is carried out without sufficiently checking the conditions, insulation or connection issues may arise during the testing phase. Because this can appear to be finished on the day, the burden when discovered later is significant. If rework or retesting becomes necessary, the process becomes even more burdensome.
Furthermore, the flow of record-keeping and corrective actions is easily disrupted during rainy weather. On sites that do not proceed as planned, people tend to postpone checks and simplify photo sorting and the sharing of corrective-action details. However, those makeshift responses will inevitably come back to affect the site later. If it becomes unclear which sections were stopped, what the conditions for resuming are, and which checks should be redone, the whole site will begin the next day's work in a state of uncertainty. In other words, if schedule management during rainy weather is handled too leniently, not only time but the very criteria for making decisions become ambiguous.
Item 1 Clarify work stoppage criteria and decision-making authority
The first item to review for rainy weather is to clarify the criteria for stopping work and the decision-making authority. The main reason responses to rain tend to be ambiguous from site to site is that it is not decided who will stop work under which conditions. On site, judgments like “let’s wait a bit” or “let’s push on a little longer” tend to accumulate, and that places a burden on both safety and quality. That is precisely why, in rainy weather, you need to share upfront the criteria for stopping and the conditions under which work may continue.
For example, suspension criteria vary by process: when ground muddiness exceeds a certain level, when heavy equipment cannot safely enter the designated position, when materials become slippery making hand tasks hazardous, or when continuing electrical work raises quality concerns. The important thing is not to leave those decisions to the atmosphere on site or to individual judgment. For pile installation, racking installation, module installation, wiring, and equipment installation, you should clarify which conditions require stopping and which allow conditional continuation.
Decision-making authority must also be clearly defined. If it is unclear who issues a stop decision for the entire site, who decides to halt work by section, and who confirms whether work can resume, on-site decisions will be delayed. As a result, one team may stop while another continues, creating inconsistencies that are difficult to reconcile later. If you want to streamline process management, you need to separate the decision-making line for the entire site from the decision-making line for individual sections.
Furthermore, work-stoppage criteria should not be decided once and for all; it is important that they be formulated in a way that is easy to implement according to the actual on-site conditions on the day. If the criteria are too detailed and cumbersome, decisions will ultimately revert to ad hoc judgments. Conversely, if the criteria are too vague, their interpretation will diverge. In practice, it is most effective to have concise, easy-to-apply criteria that fit the realities of the site. In schedule management during rain, the presence or absence of these criteria greatly influences how calmly the site operates.
Item 2: Review on-site traffic flow and heavy equipment operations assuming rainy weather
The second item is to review on-site traffic flow and heavy-equipment operations on the assumption of rainy conditions. In solar power plant construction, heavy equipment, material transport vehicles, and workers move simultaneously across a large site, so even a slight deterioration of temporary roads or internal circulation within sections can disrupt the flow of the entire site. Even if there is no problem in fair weather, when rain causes mud and slipperiness, heavy-equipment mobility efficiency drops dramatically, which in turn affects the whole process. For that reason, circulation should be designed not to fair-weather standards but on the assumption of rain.
The first thing to check is which access routes are vulnerable to rain. On the site there are places where water tends to collect, places where heavy equipment can easily churn up the ground, places near slopes that are prone to instability, and narrow places where passing is difficult. If you identify these in advance, you can see which temporary roads should be prioritized for reinforcement during rain and which sections should be closed to traffic. Conversely, if you assume the entire site is under the same conditions, you won't know where to take action when rain has an impact.
It is also necessary to reorganize the use of heavy equipment with rainy conditions in mind. Concentrating heavy equipment in the same locations and at the same times as on clear days can worsen the mud and even block access routes for other operations. By assigning heavy equipment roles by task and deciding in advance which machines to prioritize in wet weather and which sections should not be forced ahead, the site will become much more stable. Not only the performance of the equipment but also the judgment of where and when to use it is important.
Furthermore, reviewing site traffic flow directly affects safety. Transporting materials on unstable or slippery ground, intersections between heavy machinery and people in narrow passages, and turning when visibility is impaired can all lead to accidents from even a small overreach. Rather than forcing heavy equipment to operate to meet the schedule, clearly separating routes that are allowed from routes that should be closed will ultimately reduce losses at the site. This judgment is especially important for schedule management during rainy conditions.
Revising on-site traffic flows and heavy equipment operations with rainy conditions in mind is not only about preventing schedule delays. It is also about ensuring site safety and reducing the effort required for later recovery. Compared with sites that change traffic routes ad hoc every time it rains, sites that adopt a rain-ready approach from the outset experience fewer disruptions to their schedule.
Item 3 Reorder the construction sequence around piles, mounting frames, and foundations
The third item is to rearrange the installation sequence for piles, racking, and foundation works. Because ground conditions change during rainy weather, proceeding in the same order as in fine weather can create infeasibility in terms of accuracy and constructability. In particular, pile installation and foundation works are strongly affected by soil conditions and access/working-platform conditions, so these should be treated with the utmost caution in schedule management during rain. If forced ahead here, noticeable discrepancies in alignment and level are likely to occur during subsequent racking and module installation.
The first thing to consider is the order in which to advance each section. In sections that are prone to becoming muddy or where access for heavy equipment is difficult, it may be better to avoid working immediately after rainfall. Conversely, in areas with good drainage or where foundational conditions are already in place and the load on heavy equipment is low, it may be easier to move parts of the schedule forward. Rather than uniformly stopping or proceeding across all sections, reorganizing the construction sequence on a section-by-section basis is effective.
Also, it is important to clearly define the verification break between pile installation and racking installation. Especially in rainy conditions, if you proceed to racking installation without thoroughly confirming pile positions and levels, later adjustments will be substantial. After pile installation is finished, verify that they match the reference, check distances to existing structures, and confirm whether they are in a condition to be handed over to the next process, and adopt the approach of advancing to racking installation only for the sections that meet those conditions. This reduces the likelihood of carrying unverified inconsistencies into subsequent processes.
Furthermore, the assembly order of the racking components should be reviewed. In rainy conditions, the longer the components are left temporarily on the ground, the more likely their management will become disorganized, and in slippery environments manual work also becomes unstable. Therefore, rather than assembling a wide area at once, narrowing the work sections and completing them in small, self-contained units will ultimately stabilize quality. In solar power plant construction, there is a tendency to want to cover a wide area at once, but under rainy conditions, tighter, more localized control is more effective.
Reordering the construction sequence of piles, racks, and work around the foundations does not mean disrupting the schedule. Rather, it means having the ability to rebuild the work plan in response to changes in the weather. For site management, being able to switch to an order that causes less backtracking in rainy conditions is more valuable than strictly following the ideal sequence for fair weather.
Item 4 Strictly manage the quality conditions of wiring, connections, and electrical work
The fourth item is to strictly manage the quality conditions for wiring, connections, and electrical work. One of the processes most likely to be pushed too hard during rainy weather is anything related to electrical work. When visible civil works and racking/mounting work stop, attention tends to shift to wiring and connections as tasks that can be advanced even a little. However, electrical work may seem problem-free on the day, yet inconsistencies often appear during later testing or operation, so the more you relax the conditions and proceed, the greater the impact of any rework.
Wiring work requires attention not only to the routing of the cables themselves but also to terminations, connection points, cable entry into equipment, and the condition of identification markings. If you force work to proceed in rain or high-humidity conditions, even if the installation appears complete at the time, problems can later emerge as compromised insulation, faulty connections, or disrupted labeling. In other words, the decision to proceed or stop should be based not on whether the work can be done, but on whether it can be completed in a condition that ensures quality.
Also, during rainy weather it is important to check wiring routes. A route that is fine under normal conditions may later require reassessment of cable protection or support methods if it is in a place where water tends to flow, where mud is severe, or where it overlaps the traffic routes of other operations. Prioritizing work in sections where route conditions are suitable, rather than advancing the wiring itself everywhere, will ultimately make it easier to reduce rework. In schedule management during rainy weather, it can be effective to select only the locations with good conditions instead of stopping all wiring or pushing ahead with all of it.
Furthermore, for connection work, it is important to clarify what will be checked and considered finished on that day. If it is unclear whether you will only finish the wiring, complete the connections, or close out the day including the displays, when you resume the next day you will have to start over by reassessing the site. Leaving more work in an unfinished state is especially dangerous in rainy weather. Break the work into small segments and finish each segment in a way that meets the quality conditions.
Strictly controlling the quality conditions for wiring, connections, and electrical work may seem overly cautious. However, in solar power plants, rework in the later stages is especially burdensome. Therefore, during rainy weather it is more important to clearly define the conditions under which work may proceed than to try to find tasks that can still be advanced. Reorganizing the workflow so work is performed only within the range where quality conditions can be maintained is ultimately the most efficient approach.
Item 5 Design the material storage and delivery plan including rain countermeasures
The fifth item is to design material storage and delivery plans that include rain countermeasures. In solar power plant construction, many materials—pile materials, racking components, modules, cables, junction boxes, PCS, and so on—are brought to the site. Temporary placements that appear fine in clear weather can become problematic in rain, with muddy ground, insufficient protection, load collapse, and pathway obstruction all becoming issues at once. Because poor material management directly affects not only work efficiency but also quality and safety, plans must be designed assuming rainy conditions.
What should be reviewed first is where to place materials that won't be used that day. On site, bringing materials in early to allow a margin often results in unused materials blocking passageways and obstructing heavy equipment and transport routes. When rain makes the ground slippery or muddy, the impact becomes even greater. For that reason, it's important to coordinate the delivery plan with the work schedule and make clear which materials are needed in which section and in what order.
Also, storage methods need to be considered separately for each category. Modules, electrical supplies, equipment, and piling materials are affected by rain in different ways. If they are grouped together in the same storage area, unnecessary handling increases each time items are inspected or dispatched, leading to disorder on site. By organizing storage methods with rain countermeasures included, it becomes easier to maintain at least a minimum level of order even when the weather deteriorates.
Furthermore, the delivery plan should be considered together with temporary access roads and heavy-equipment movement routes. If temporary storage areas become muddy during rain, not only does the quality of the materials themselves suffer, but the access routes to them also deteriorate. As a result, materials often need to be repositioned or re-transported, which slows down the entire schedule. It is not uncommon at solar power plant sites for the flow of materials, rather than the construction work itself, to bring the project to a halt.
Designing material storage and delivery plans to include rain countermeasures is not about simply keeping the site tidy. It is construction process management intended to make the schedule less susceptible to disruption from rain and to protect both materials and site circulation routes. If you want to streamline construction management, you must not think that materials can just arrive; you need to consider from the outset in what condition materials will be brought onto the site and in what condition they will be kept.
Item 6 Standardize procedures for resuming operations after rain and reconfirmation items
The sixth item is to standardize restart procedures and items to recheck after rain. After the rain stops, crews on site tend to want to resume work as quickly as possible. However, if they proceed with the mindset of simply continuing from the previous day, they can easily overlook changes in ground conditions, material condition, positional relationships with existing structures, temporary access routes, and the conditions for electrical work. If you want to restart quickly, it is more important to decide in advance what to inspect before resuming than to rush.
First, what you should check when resuming work is the safety of access routes and work areas. If you start work without checking for mud, the condition of the slope shoulder, puddles, whether heavy equipment can enter, the stability of temporary roads, etc., it can lead to accidents or damage to materials. These should be checked not only by visual inspection but with awareness of any differences from the previous day's condition. After rain, even if the site looks the same, the conditions have definitely changed.
Next, you need to clarify how to resume a process that was stopped partway the previous day. Whether it was in the middle of pile installation, mounting-frame assembly, or wiring work will change what needs to be rechecked. If you resume while work is left half-finished, it becomes difficult to know what has already been verified and where to start over. That’s why it’s effective to have a set of items to check before resuming for each process.
Also, record handling at restart is important. If it isn’t shared what was left unfinished when work was stopped due to rain, which sections still have concerns, or which materials or equipment might be affected, the site on the first day back will begin with re-explanations. This increases the burden on the site. If it’s clear how far things had been closed out the previous day, restarting will be much faster.
Standardizing procedures for restarting work after rainy weather is not something that applies only to special sites. At sites with large areas and many concurrent operations, such as solar power plant construction, having a basic checklist of confirmation items stabilizes the site more than rethinking everything from scratch each time the weather changes. If you want to resume work quickly, you need to create a system that allows action to begin once the prerequisites are in place.
To further advance position verification
As we have seen, to stabilize schedule management during rainy weather in solar power plant construction it is important to review the criteria for stopping work, on-site traffic flow and heavy equipment operation, the pile and racking installation sequence, quality requirements for electrical work, material storage and delivery, and restart procedures after rain. By addressing these points, you can reduce disruption not only on the day it rains but also across the entire subsequent schedule. Schedule management during rainy weather should be regarded not as a binary choice between stopping or proceeding, but as management that decides which activities to halt and which to protect.
If you want to move the site forward, there is room to improve how position checks themselves are handled. In the construction of photovoltaic power plants, there are a large number of position-related checks, such as pile locations, racking locations, equipment locations, wiring routes, and grounding electrode locations. After rain these position checks become even more difficult, and changes in ground conditions and access/traffic flow conditions make rechecking more likely. If these can be handled faster and more clearly, the burden of construction schedule management will be considerably reduced.
When considering such operations, measures that allow integrating high-precision positioning in a form that is easy to use on site—such as LRTK, an iPhone-mounted GNSS high-precision positioning device—are also effective. If stake positions, equipment positions, and section reference checks can be carried out on site in an easy-to-understand way, it becomes easier to match drawings to the field when work resumes after rain. If you want to further stabilize solar power plant construction, it is important to improve not only schedules and materials management but also the position verification that underpins them.
Next Steps:
Explore LRTK Products & Workflows
LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.
LRTK supercharges field accuracy and efficiency
The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.