top of page

5 Easily Overlooked Points to Watch When Preparing Access Roads for Solar Power Plant Construction

By LRTK Team (Lefixea Inc.)

All-in-One Surveying Device: LRTK Phone
text explanation of LRTK Phone

In solar power plant construction, many processes proceed in sequence, such as site preparation, foundations, racking, module installation, wiring, and substation/electrical equipment work. Among these, one aspect that on-site personnel surprisingly tend to overlook is access road preparation. The access road is not merely a passage but an important foundation that supports the productivity, safety, and quality of the entire construction. If it is inadequate, materials and heavy machinery cannot be brought in as planned, leading to schedule delays, construction errors, and an increased burden in dealing with neighboring residents.


In particular, construction sites for solar power plants are not all flat industrial lots. Terrain and ground conditions are diverse, including mountainous areas, sloping land, land converted from agricultural use, and developed sites that include fill. Therefore, access road preparation must be planned according to the conditions of each site. Even if a route looks passable, problems such as becoming muddy in rainy weather, vehicles being unable to turn, steep gradients that pose a risk of load shifting or collapse, and impacts on existing side ditches or underground buried objects are not uncommon.


Site access road preparation is often underestimated as part of pre-construction preparatory work, but in reality it is closely related to construction planning, temporary works planning, earthworks planning, drainage planning, schedule management, and consideration for nearby residents. On site, attention tends to be focused on arranging the main construction works, so consideration of access roads can fall behind. However, errors in judgment there later appear as significant rework.


In this article, we organize five easily overlooked points to watch for when preparing access roads for solar power plant construction, and clearly explain the practical approach you should adopt in the field. The aim is to enable those responsible for advancing construction preparations to regard access roads not merely as temporary installations but as important planning elements that support the entire site.


Table of Contents

Why access road preparation is important in solar power plant construction

Point 1: Do not assess ground conditions by appearance alone

Point 2: Do not consider road width and turning space only as straight-line measurements

Point 3: Do not postpone drainage planning

Point 4: Do not underestimate impacts on the surrounding environment and existing infrastructure

Point 5: Do not separate schedule coordination from the main construction work

Practical approach to reliably advancing access road preparation

Summary


Why Access Road Preparation Becomes Important in Solar Power Plant Construction

Improving access roads is important because, if construction vehicles and material transport vehicles cannot enter the site, no matter how good the construction plan is, it cannot be executed. In solar power plant construction, various materials and machines are delivered in stages: piles and foundation materials, racking components, panels, cables, piping materials, crushed stone, heavy equipment, and so on. Because the delivery timing and vehicle requirements differ for each, the simple notion that “as long as a vehicle can pass” is not sufficient.


At some sites, vehicles used for the initial earthworks can get in, but long loads or large vehicles needed later in the process may not be able to pass. Alternatively, a vehicle may be able to pass when empty, but when loaded the contact pressure or vehicle weight can damage the roadbed. If these problems are discovered only after work has begun, they become difficult to deal with. Emergency repairs or the installation of detours tend to have negative impacts on both the schedule and safety.


Furthermore, access roads are highly susceptible to weather. Even if there are no problems in fine weather, after rainfall the road surface can soften, causing wheel spin or sinking. This can result in construction vehicles becoming stuck or, when attempting to pass, undermining or collapsing the road shoulder. Solar power plant construction sites are expansive and access routes tend to be long, so a problem in one section can easily propagate through the entire project schedule.


Moreover, access routes for deliveries have great significance in terms of safety management. Insufficient width, poor visibility, steep gradients, muddy conditions, and weak shoulders can lead to vehicle accidents, collisions, and overturning incidents. Site safety is not maintained solely within the work area. Only when safe access routes are secured from the material transport stage can stable construction be achieved.


As such, while the improvement of site access routes is part of temporary works, it is in practice a critical factor that influences construction quality, schedule management, safety assurance, and consideration for neighboring residents. It is precisely the aspects that are easy to overlook that need to be carefully finalized before construction begins.


Caution 1: Do not judge ground conditions by appearance alone

The most easily overlooked issue when preparing access roads is misreading the ground conditions. It is not uncommon for someone to visit the site once and conclude it is fine because the surface appears compact. However, even if the surface looks dry and hard, if the subsurface is weak it may not withstand the passage of heavy vehicles.


Particular attention should be paid to locations where only a thin layer of topsoil is compacted, sites immediately after earthworks where compaction is insufficient, areas where fill and cut materials are mixed, and places where water channels remain. Under these conditions, settlement and rutting are likely to occur the moment vehicle loads are applied. Once ruts form on access roads, not only does vehicle stability deteriorate, but poor drainage also becomes more likely, creating a vicious cycle that further degrades the road surface.


On solar power plant construction sites, because the overall site is large, not all parts of the access route necessarily share the same ground conditions. Even if the area near the entrance is connected to an existing road and is stable, weak ground or embankment sections may appear as you proceed further in. Therefore, rather than viewing the access route as a single line, it is important to assess the condition of each section.


Also, the behavior of the ground changes with the seasons. Even if there are no problems during the dry season, passability can suddenly deteriorate during the rainy season or immediately after rainfall. Even if it appears there is no problem on visual inspection, conditions can change rapidly if the weather changes after construction begins. For that reason, it is dangerous to decide based only on a site survey conducted in fine weather. It is important to anticipate post-rain conditions and, if necessary, plan for laying crushed stone or reinforcing the roadbed.


Additionally, the required load-bearing capacity varies depending on the type of vehicle. A pavement that small vehicles can pass over may be insufficient for large vehicles loaded with heavy cargo. Heavy-equipment transporters and long-length material delivery vehicles tend to concentrate large loads when stopping or turning, so the conditions are more severe than during straight-line travel. It is essential to assess not only whether a vehicle can simply drive over the surface, but also stopping, waiting, passing, and turning.


In practice, during on-site inspections it is important to assess not only surface conditions but also the presence of mud, the persistence of tire marks, shoulder settlement, patterns of rainwater pooling, and the condition of existing road base materials, considering them together. If necessary, running a test vehicle over the area to observe the response can also be effective. Rather than relying solely on experience, adopting the approach of defining reinforcement extents based on assumed ground variability will ultimately reduce rework.


Preparation of access roads is a phase that can be easily judged by appearance, but in reality it is an area where misreading the ground conditions can have very large consequences. Carefully assessing ground conditions at an early stage and not hesitating to carry out necessary reinforcement leads to stable construction.


Note 2 Do not consider road width and turning space as straight-line measurements

In access road planning for deliveries, people tend to assume that as long as the roadway width is secured, vehicles can pass. However, in solar power plant construction the locations that actually cause problems are not the straight sections but the curved sections, junctions, passing bays, areas around temporary material storage, and near the delivery gate. In these places the required maneuvers become complex, so simply ensuring roadway width is insufficient.


For example, large vehicles are affected by off-tracking, so even if a road appears to be wide enough, they may ride up onto the shoulder or swing too close to the slope when turning. In locations where the shoulder is weak, even slight riding up can lead to collapse or settlement and render the road impassable. Especially for temporary access roads, because the roadside structure is not as stable as that of a paved road, planning with an adequate margin is necessary.


Additionally, at solar power plant sites, material storage areas and work yards are limited, and access routes and construction areas tend to be in close proximity. Therefore, it is important to confirm in advance whether delivery vehicles can safely reach their designated positions, unload, reverse, or withdraw. Being able to pass through is not the same as being able to carry out the work. If the exit route after delivery is not considered, vehicles can become stuck on site and the entire operation may come to a halt.


Another easily overlooked issue is vehicles passing each other. When work becomes full-scale, material delivery trucks, heavy machinery, water-spraying vehicles, and management vehicles may be operating at the same times. If a single-lane access road lacks passing areas, it becomes difficult for oncoming vehicles to pull over, requiring long waits or reverse guidance. If this repeats, not only does site productivity decline, but the safety risks associated with the guidance work also increase.


Sections where gradients and curves overlap also require attention. When turning while ascending, a vehicle’s trajectory becomes harder to anticipate, increasing the risk of cargo shift and slipping. Even if there is no problem when dry, the road’s passability is greatly reduced in rainy conditions or when the surface is rough. You need to consider not only the roadway width but also gradient, cross slope, curvature, and shoulder strength together.


As on-site personnel, it is important not to stop at simply checking dimensions on the drawings, but to concretely visualize which vehicles will move in what order, how far they will go, where they will stop, and where they will turn. If necessary, verify the travel paths of the primary vehicles on site and identify hazardous or obstructed areas. Delivery routes should be considered not as static drawings but based on the movements of vehicles.


If you plan using only straight-line distance and minimum width, unexpected problems will occur on site. When preparing access routes, it is essential to view the entire sequence — from vehicles safely passing through and carrying out work to exiting — as a continuous flow.


Point 3: Do not delay the drainage plan

Drainage planning is often postponed when preparing access roads for deliveries. However, in practice the quality of drainage measures greatly affects how easy the access road is to use. No matter how much crushed stone is placed, a surface that does not drain will deteriorate quickly. Conversely, if drainage is properly planned, stability can differ greatly even with the same roadbed composition.


Solar power plant construction sites often span large areas with changes in elevation, so rainwater runoff is not uniform. There are various drainage risks on access roads: places where surface water flows in from the uphill side, locations where site grading has altered drainage paths, and low-lying areas where water tends to accumulate. If these are ignored and only the road surface is improved, sections will become muddy after each rainfall and require repeated repairs.


Particularly problematic are cases where water is not adequately drained to the shoulder. If the pavement has no cross slope and water accumulates in the center or on one side, washout of crushed stone and weakening of the roadbed will progress. Furthermore, pooled water can be churned by passing vehicles, causing the surface to become muddy and increasing the likelihood of wheel spin and splattering. This can lead to problems such as mud being tracked onto adjacent roads and vehicle soiling.


Also, in addition to road surface drainage, it is important to address water flowing in from the surrounding topography. At locations that receive runoff from upper slopes, simply reinforcing the access road itself is insufficient; it is necessary to consider side ditches, cross drains, and inflow control measures together. If the access road is planned to cross a valley, even short-term rainfall can cause unexpected water accumulation.


Behind the tendency to postpone drainage planning is a mindset that wants to treat the access route as temporary and simplify it. However, precisely because it is temporary, if the minimum drainage functions are not put in place early, you will be occupied with repair work from immediately after the main construction begins. Repair work consumes both labor and machinery, and if it coincides with material deliveries it will disrupt the entire schedule.


Furthermore, poor drainage does not end as a problem for the access road alone. If the runoff affects surrounding farmland, roads, or adjacent properties, it will lead to neighbor relations and complaint handling. In particular, the discharge of turbid water tends to worsen impressions of the construction and affects initial trust. Paying attention to drainage from the access road preparation stage leads not only to greater efficiency on site but also to reduced risk outside the site.


During on-site inspections, it is important to clearly visualize where water will come from and where it will flow when it rains. If you judge based only on dry ground, you can overlook places where water tends to accumulate. Carefully examine small level changes, the locations of existing side drains, the direction of natural runoff, and how prone low-lying areas are to pooling, and plan the necessary measures in advance—this is the foundation of creating a robust site access road.


Point 4: Do not underestimate the impact on the surrounding environment and existing infrastructure

Preparation of access roads is often regarded as an on-site issue, but in reality it is strongly influenced by the surrounding environment and existing infrastructure. If this is underestimated, the construction itself may proceed, yet the site can end up overwhelmed with handling neighbor relations and restoration work. Areas that are easily overlooked include locations near road boundaries, in the vicinity of existing structures, sections with underground buried objects, and stretches adjoining neighboring houses or farmland.


For example, when the entrance to an access road connects to an existing roadway, one may only consider eliminating level differences and reinforcing the shoulder, overlooking impacts on existing gutters and curbs. Even if temporary access is possible, repeated passage of heavy vehicles can damage gutter covers or cause curb edges to collapse, which would then have to be addressed as off-site damage. Such locations may appear to be outside the scope of the works, but in practice they should be treated as part of the delivery plan.


Also, confirming the locations of underground buried utilities is important. Because the access route is temporary, if you proceed without as rigorous a review as for permanent structures, you may overlook impacts on buried piping, communication equipment, and drainage systems. Even if there appears to be no problem on the surface, vehicle loads can cause settlement or damage. Do not assume it is safe simply because it is within the site; you need to check in advance whether existing equipment or utilities are present.


From the perspective of consideration for the surrounding environment, mud being tracked out, dust, noise, and vibration cannot be overlooked. If site access roads are unmaintained and the road surface is poor, vehicle traffic can carry soil onto public roads, and dust is likely to be generated when conditions are dry. If this affects nearby residents or surrounding facilities, it becomes a source of trouble separate from the construction itself. Improving access roads is necessary not only for construction efficiency but also to minimize impacts on the surrounding area.


Furthermore, boundary management with adjacent properties is also important. You must avoid situations where, intending the change to be temporary, the shoulder is widened slightly and ends up being used beyond the boundary. On site, this is a part where judgment tends to be relaxed in favor of workability, but if it becomes a problem later, repair and explanation become difficult. The more an area tends to expand—such as the shoulder of access routes, lay-bys, and turning spaces—the more it needs to be managed with a strong awareness of the boundary.


In solar power plant construction, sites are large and the construction area can become extensive, so there are many interfaces with the surrounding environment. Therefore, it is important to regard access road preparation not only as an internal site issue but as an external condition that includes connecting roads, nearby facilities, adjacent properties, and existing equipment. Addressing issues after construction has begun incurs high costs in both explanation and time. Taking a broad view of the scope of impact at the initial stage stabilizes site operations.


Note 5 Do not separate schedule coordination from this construction work

What is most easily overlooked in preparing access routes is the coordination of schedules with the main construction work. Because access routes are often treated as preparatory work carried out before construction starts, they tend to be considered separately from the main construction. However, in reality the timing of completion of the access routes, the sections to be used, and the timing of their maintenance and management are closely related to the main construction. If these are considered separately, situations can arise where the routes you need are not available when you need them.


For example, even if you expect to use the same access route as-is after site preparation is completed, the next stage may involve different material volumes and vehicle types, which can expose insufficient reinforcement. Alternatively, the road surface may be left damaged by heavy-equipment traffic in a previous stage, causing material deliveries in later stages to be delayed. An access route should not be treated as something built once and finished; its use and required performance should be expected to change as the project progresses.


Also, as the construction area expands, the starting and ending points of the access route for deliveries may change. While a route from the entrance to the temporary storage area may be sufficient in the initial phase, as rack installation and wiring work progress, access to the rear of the site becomes important. If you prepare without anticipating this change, a new temporary route may become necessary mid-project, making schedule changes and additional work more likely.


In coordinating with this construction work, alignment with the material delivery plan is also essential. If peak traffic loads — for example, periods when delivery volumes concentrate, when long items are delivered, or when multiple contractors operate simultaneously — are not anticipated, even delivery routes that are normally problem-free will lack the capacity to cope. As a result, waiting vehicles can overflow onto public roads, and vehicles may have to wait to unload inside the site. This is undesirable both from a safety perspective and in terms of consideration for the surrounding area.


Furthermore, if responsibility for the maintenance and management of the access road is left unclear, response will be delayed even when deterioration becomes apparent. It is important to decide operational details such as who will carry out inspections, what level of damage requires repairs, whether inspections will be conducted after rain, and what measures will be taken to prevent mud from being tracked off site. If these items are not incorporated into the construction plan, problems will be handled on the spot when they arise, resulting in increased costs and man-hours.


In solar power plant construction, the large site area and the many work stages make temporary access routes prone to change as the work progresses. Rather than treating the preparation of delivery/access roads as an isolated task, regarding it as a traffic-flow plan that supports the entire construction process leads to site operations with minimal rework.


Practical Approaches to Ensuring Reliable Progress in Site Access Road Preparation

The commonality among the five points examined so far is that access route preparation should not be treated as merely creating a passage. To ensure reliable progress in practice, the five factors — ground conditions, vehicles, drainage, surrounding environment, and the construction schedule — should not be considered separately, but connected and treated as conditions of the entire site.


First, the important thing is to increase the resolution of on-site inspections. Because many things cannot be understood from drawings and aerial photographs alone, carefully check the actual elevation differences, ground hardness, rainwater flow patterns, shoulder clearance, positions of obstacles, and how the site ties into existing roads. At this stage, it is important not to judge based only on how it looks in fair weather, but to assess conditions assuming post-rain situations and peak construction periods. The necessary perspective is not whether it is passable now, but whether it can be operated stably throughout the construction period.


Next, specify which vehicles will pass and when. If the targets and timing for material deliveries remain ambiguous, the required performance of the access routes cannot be determined. Different vehicles operate during the site formation stage, foundation stage, support-frame stage, and electrical work stage. Taking this into account, examining road width, passing areas, turning, temporary storage/staging, and reinforced sections will produce an access route plan that closely matches actual operations.


Furthermore, the access road should be planned with post-construction management in mind. Because conditions change during construction due to weather and vehicle traffic, it is important not to stop at initial maintenance but to establish procedures for inspection and repair. In particular, post-rain inspections, early repair of ruts, suppression of mud carryout, and checks of drainage functions should be incorporated into routine management. If small defects are left unattended, major repairs will be required later.


It is also important to align understanding among stakeholders. The more people who will use the delivery route—site supervisors, contractors, materials delivery personnel, heavy equipment operators, etc.—the more rules and information sharing will be needed. If basic policies are shared in advance — such as which sections are passable, where to wait, and how operations should change in rainy weather — it becomes easier to reduce variability in on-site decision-making.


In practice, access routes are sometimes treated as a minor element of the main construction. However, whether the construction site runs smoothly depends greatly on the precision of these supporting parts. Properly preparing the access route at the outset can be regarded as an upfront investment to make subsequent work easier.


In recent years, there has been an increasing need to more accurately confirm the positions of access routes, share the extents of passable areas, and verify temporary routes. On large solar farms, managing traffic flow by oral instruction or visual checks alone easily leads to misalignment in understanding. Proceeding while accurately grasping the start and end points of access routes, pull-out areas, the positions of road shoulders, and their relationship to temporary material storage areas stabilizes on-site decision-making.


In that sense, it is also effective to adopt measures that streamline position confirmation. For example, when checking access routes, identifying temporary circulation paths, or seeking to improve on-site positioning accuracy, one method is to use an iPhone-mounted GNSS high-precision positioning device such as LRTK. On large sites like solar power plants, being able to smoothly confirm the traffic range of access routes and the positional relationships of construction areas contributes to improved planning accuracy. For personnel who want to advance access route preparations more practically, these kinds of digital verification methods become a compelling option to support site operations.


Summary

When preparing access roads for solar power plant construction, it is important not to judge them solely by how easy they appear to be. Overlooking any one of ground conditions, road width and turning radius, drainage, the surrounding environment, or construction coordination can impact the entire project. Even if an access road is temporary, it is the foundation that determines the overall quality and efficiency of the site.


What is especially important for site personnel is to regard the access route not as a temporary task before construction starts but as a traffic-flow plan that supports the entire construction period. By checking not only whether vehicles can pass, but also whether it can be used on rainy days, whether it will cause inconvenience to the surrounding area, and whether it can be operated stably through later processes, it becomes easier to create a site with minimal rework.


Carefully preparing the delivery access route not only prevents schedule delays but also improves safety and reduces the burden of dealing with neighbors. That is why it is important at the pre-construction stage to read site conditions in detail and to organize necessary reinforcements, drainage measures, and operational rules.


Also, when you want to carry out construction on a large site while accurately identifying the locations of delivery routes and temporary traffic routes, using an iPhone-mounted GNSS high-precision positioning device like LRTK can be effective. Because it makes it easier to confirm delivery routes, share the construction area, and perform on-site positioning, it can be a practical option for site managers who want to improve the setup precision of solar power plant construction.


Next Steps:
Explore LRTK Products & Workflows

LRTK helps professionals capture absolute coordinates, create georeferenced point clouds, and streamline surveying and construction workflows. Explore the products below, or contact us for a demo, pricing, or implementation support.

LRTK supercharges field accuracy and efficiency

The LRTK series delivers high-precision GNSS positioning for construction, civil engineering, and surveying, enabling significant reductions in work time and major gains in productivity. It makes it easy to handle everything from design surveys and point-cloud scanning to AR, 3D construction, as-built management, and infrastructure inspection.

bottom of page